Information Systems Analysis and Design
1
KoKo’s Canine Pet Club
CASE BACKGROUND
About a year ago, Christina Magana found herself facing a dilemma. As a result of a chronic
illness, KoKo, her beloved schnauzer, required medication, a special diet, and daily exercise. While the
medication and special diet were easy to accommodate into a busy life style, ensuring that KoKo received
daily exercise was another matter. Although KoKo’s daily exercise usually took the form of a walk
around the neighborhood, Ms. Magana, as a busy executive, had trouble scheduling KoKo’s daily walks.
Ms. Magana’s friend Ian, would walk KoKo on the days when Ms. Magana was extremely busy. Ms
Magana’s friends and neighbors liked the pet walking idea so much that they approached Ms. Magana
and Ian about walking their dogs as well. What began as a neighborhood walking service has now become
a fledgling, yet growing, metropolitan area business. Ms. Magana has hired you to build a simple yet
effective software program for her business. She needs the system to be able to track data about clients,
pets, walkers, and schedules for when the walkers take out the pets.
Although the service was only started six months ago, it currently provides pet walking services
for 350 pets and is registering on average 5 pets per week. Paperwork is increasing and the owner needs a
better record keeping system.
During a meeting with the owner she explains to you that a new client must register with the
service. During the registration process the new client provides basic information about his pet. Chooses a
preferred walk time and specifies a walker preference. During this time a dog walking fee is determined
and recorded on the pet registration form. The dog-walking fee varies by pet and is based on the pet’s
size, temperament and the number of pets the owner has. The pet owner can request that his pet be walked
in the early morning, late morning, early afternoon, late afternoon, or early evening hours. Available walk
times are currently kept on a clipboard by the phone. However, Ms. Magana wants the available walk
times, as well as walker, client, and pet information, kept in the system that you are building. Everything
now is done on pre-printed paper forms.
Because the business grew so fast Ms. Magana has contracted 20 walkers with alternating
schedules. She has also hired three full-time college students to help with the record keeping and
organization of the files. She is also renting a small storage unit when she keeps all the extra files that she
is not able to keep at home. Below are the recurring costs that she is currently paying. As well as the
benefits that she anticipates gaining by using the newly developed system. She would like to be able to
see how the new system will operate as it is being built because she wants to be able to make some
modifications to it at each stage..
2
DELIVERABLES FOR PROJECT 2
In a word document create a list of tasks needed for this project in table format
Create a WBS list of tasks. Include duration, dependencies and status. Include
all phases of the SDLC in your list o Planning o Analysis o Design o Implementation
Create a Gantt chart for the WBS. Research and select a freeware tool online to create your Gantt chart.
DELIVERABLES INSTRUCTIONS
Turn in your printed project neatly assembled
Upload your digital files to blackboard
Use the cover page at the end of this assignment as the first page.
Title and number each page accordingly
Turn in the assignment in the following order.
o Cover page o Table list of tasks o WBS o Gantt Chart
3
Course: CIS 3150 –Introduction to Systems Analysis and Design
Assignment: Project 2
Student Name: ____________________________________________
Statement of Independent Effort: I _____________________________, attest that
this entire project is my own work.
Signature __________________
Instructor Comments: __________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
Project Grade: __________