Project Charts
Name
Institution
Project Charts
Project Activities Plan
Gantt Chart Showing the Schedule of the Project Activities
Applications Implementation Re-engineering process Customization Project Interface Project Architecture Project Conersion Project Testing Employees Training Project End 43586 43593 43600 43607 43607 43610 43616 43635 43639 Duration Applications Implementation Re-engineering process Customization Project Interface Project Architecture Project Conersion Project Testing Employees Training Project End 28 14 14 7 14 6 5 4 3 Start Week
Week
0123456789
MayMayMayMayMayJunJunJunJunJul
1815222951219263
Phase
Applications Implementation
One
Re-engineering
Customization
Phase
Project Interfaces
Two
Project Architecture
Project Conversion
Project Testing
Final Project Specification
Phase Review and Approval
Phase
Three
Employees Training
Project End
Milestone: additional funds
May 1, 2019
Starting