Lean Systems, Process & Operations class need within next 12 hrs

profilesareee24
Chapters13_143.pptx

Chapters 13 & 14

Aggregate & Disaggregate planning

Planning covers long (>1 year by senior executives), intermediate (3-18 months by operations managers) and short terms (< 3 months by supervisors).

Good intermediate planning requires coordinating demand forecasts with operations to determine feasibility and strategic fit (called sales and operations planning S&OP)

The outcome of the 3-18 month S&OP is an aggregate plan updated weekly/monthly balancing production quantities, timing and resources needed to meet demand at minimum cost.

Aggregate plan capacity options seek to absorb demand fluctuations by answering?

Should inventories be increased during times of low demand to meet future high demand?

To meet fluctuations in demand should part-time/full time workers be hired, laid off or put on overtime?

Is it possible to acquire temporary capacity through subcontracting?

Aggregate plan demand options seek to influence demand by answering?

Can advertising, price discounts or counter season product mixes be used cover excess capacity during slow periods?

During peak demand are customers willing to accept longer lead times?

Based on capacity & demand options at their disposal aggregate plans might seek to:

Achieve output rates to match demand for each period (chase strategy)

As demand changes a constant production level uses inventory as a buffer (level scheduling).

Use a combination of options to adjust capacity & demand (mixed strategy)

Let’s look at a level scheduling strategy…

To cover the 6,200 unit expected demand over the 124 production days Jan-June, 50 units are made each day.

How many workers does our level production strategy need?

50 units are made per day

It takes 1.6 hrs. to make a unit

A person works 8 hrs./day

Our 10 workers each work 124 days/yr. Assuming they are paid $10 / hr. our labor cost is:

/yr.

What are our inventory costs with the level production strategy?

At the 50 units/day production level we accumulate 252 units of inventory by March and consume all but 5 of them by June

In our example,

The total inventory carried over from one month to the next is 1853 units

With inventory carrying cost @ $5/unit per month, total carrying cost is $9,264 (e.g. 1853*5)

So our level production strategy cost is $101,465

$92,200 in labor & $9,264 in inventory carrying costs.

Besides a level labor strategy, we might consider using part-time labor & subcontracting.

Since we set the workforce size to meet demand in the lowest demand month, no inventory carrying cost

When producing 38 units/day over 124 production days, a total of 4712 units are made (e.g. .

To meet the 6200 units demanded 1488 outsourced units are needed (6200-4712).

At $20/unit subcontracting cost, subcontracting costs $29,760 (

Making 38 units per day requires 7 full time workers and 1 part time worker.

/day

With each worker earning $10/hr. the labor cost is

/yr.

Total cost with this 0 inventory strategy using subcontracting is $105,152/yr. (which is higher than our $101,465 cost carrying inventory and producing at a constant level).

Another production strategy is to make in each month only what is demanded. As demand changes labor is either hired or laid off.

In our example, cost of hiring/training is $300/worker hired and cost of layoffs are $600/worker dismissed.

How many workers does our monthly production strategy need (decimals are part time workers)?

It takes 1.6 hrs. to make a unit

A person works 8 hrs./day

/day

How much do these workers cost/month?

How much does it cost to hire and lay off each month? ($1,850+$1,942)

# of hired workers/month is multiplied by $300

# of workers laid off each month is multiplied by $600

In this example, $102,947 is the cost of trying to flex the workforce size to match monthly demand with no inventory. This is more expensive than our $101,465 lowest cost option of carrying inventory and producing at a constant level

From the aggregate S&OP plan we know in broad terms what needs to be made.

The Master Production Schedule (MPS) breaks down (i.e. disaggregates) the plan into specific products to be made by when.

In the MPS we may be:

Making products to customer orders

Making products to forecasted orders

Making quantities of components required to assemble products (i.e. bill of materials or BOM)

Making subassemblies for integration into products (modular bills)

In this BOM we have 4 levels

Level 0

Level 1

Level 2

Level 3

The 4 parent items (at least 1 level below) are A, B, C & F

The 6 component items (at least 1 level above) are B, C, D, E, F & G

2 items of B & 3 items of C are needed to make 1 item of A

2 items of D & 2 items of E are needed to make 1 item of B

To make 50 items of A, quantities of parts B-G needed are….

Now that we know what is needed, we determine when to launch BOM production based on lead times (time phased product structure).

We need 100 “B” items to make 50 “A” items.

If we want the “A” items by week 8, we need to order the “A” items 1 week earlier in week 7.

To order the “A” items in week 7 we must have 100 “B” items and 150 “C” items on hand by week 7

To have them on hand in week 7, “B” items must be ordered in week 5 and “C” items in week 6

Gross Requirement Plan

Time Phased Product Structure (based on lead times)

In a net requirements plan we go 1 step further. We consider gross required quantities as well as inventories on hand.

In this example, we have 35 items on hand prior to week 1. So our net requirement in week 1 is adjusted from 35 to 0.

In the example, the net requirements plan follow the gross requirements. Our order quantities are matching demand (i.e. no inventory).

The planned order releases match the gross requirements

Another net requirements strategy is to follow an EOQ.

We can express EOQ as:

D=Annual demand (in pieces)

S=Set up cost per batch

H=Annual holding costs per unit

In our example,

=73

D=Annual demand (1,404)

S=Set up cost per batch ($100)

H=Annual holding costs per unit ($1/week* 52 weeks = $52)

In week 1 we release an order for 73 which arrive in week 2.

Weeks 2,3 & 5 we need 80 units. Our EOQ is 73. So in week 5 we need 7 (80-73).

Since our lead time is 1 week we launch the 73 piece production in week 4.

In weeks 5,6 & 7 we need to make 7+40+30 (77 pieces). Our EOQ is 73. So our net requirement in week 7 will be 4 (77-73).

Since we have a 1 week lead time we launch the 73 piece order in week 6

In weeks 9 & 10 we need to make 4+30+55 (89 pieces). Our EOQ is 73. So our net requirement in week 10 will be 16 (89-73).

Since we have a 1 week lead time we launch the 73 piece order in week 9

What are the set up costs?

4

What are the holding costs?

H= Holding costs per unit per year (in our example 10 weeks not 52)

Q=Quantity made per batch

What are the total inventory costs?

Set up costs plus holding costs

($400)+ ($365)=$765

In our example it is less expensive to produce lots to order ($700) size than run EOQ with inventory ($765)

Matching demand is best when set up costs are low and holding costs high

EOQ is effective when demand is fairly constant

The MPS, BOM, lead times & Gross Requirement Plan are inputs into the Material Resource Plan (MRP).

MRP isn’t doing detailed scheduling (job X on machine Y at time Z). It is only telling by week or day when to launch orders. MRP doesn’t consider capacity.

MRP II seeks to tie resources needed to the MRP production plan.

One of those resources is capacity.

Load reports compare work center capacity to work assigned

In this load report we can see of the 12 hrs/day capacity, in days 1 & 4 we have excess capacity while in days 2,3 and 5 we are under capacity

Options include:

Moving orders (e.g. 2 orders in Day 2 to Day 1) to periods where we have capacity (order splitting)

Just as MRP II ties production resources needed to the MRP production plan, Enterprise Resource Planning (ERP) takes integration 1 step further.

ERP coordinates a firm’s entire business using a centralized database to flow information among all business functions.

Expected

demand

Production

days available

Expected

demand per

production day

Jan9002241

Feb7001839

Mar8002138

April12002157

May15002268

June11002055

Total620012450

Sheet1

Expected demand Production days available Expected demand per production day
Jan 900 22 41
Feb 700 18 39
Mar 800 21 38
April 1200 21 57
May 1500 22 68
June 1100 20 55
Total 6200 124 50

Sheet2

Sheet3

Sheet1

Expected demand Production days available Expected demand per production day
Jan 900 22 41
Feb 700 18 39
Mar 800 21 38
April 1200 21 57
May 1500 22 68
June 1100 20 55
Total 6200 124 50

Sheet2

Sheet3

Expected

demand

Days

worked/

monthProd./day

Expected

demand/

day

Ending

inventory

Jan900225041198

Feb700185039198

Mar800215038252

April1200215057-147

May1500225068-396

June1100205055-100

5

Expected

demand

Days

worked/

monthProd./day

Expected

demand/

day

Monthly

inventory

change

Ending

Inventory

Jan900225041198198

Feb700185039198396

Mar800215038252648

April1200215057-147501

May1500225068-396105

June1100205055-1005

51853

Expected

demand

Production

per day

Expected demand

per production

day

Monthly

inventory

change

Ending

inventory

Jan900504199

Feb70050391120

Mar80050381232

April12005057-725

May15005068-187

June11005055-52

Total62002

Sheet1

Expected demand Production per day Expected demand per production day Monthly inventory change Ending inventory
Jan 900 50 41 9 9
Feb 700 50 39 11 20
Mar 800 50 38 12 32
April 1200 50 57 -7 25
May 1500 50 68 -18 7
June 1100 50 55 -5 2
Total 6200 2

Sheet2

Sheet3

Expected

demand

Expected

demand

per

production

day

Workers

needed

Jan900418.2

Feb700397.8

Mar800387.6

April12005711.4

May15006813.6

June11005511.0

Total6200

Sheet1

Expected demand Expected demand per production day Workers needed Days worked per month Production cost Hiring cost Layoff costs
Jan 900 41 8.2 22 14400 0 0
Feb 700 39 7.8 18 11200 600
Mar 800 38 7.6 21 12800 120
April 1200 57 11.4 21 19200 1143
May 1500 68 13.6 22 24000 662
June 1100 55 11.0 20 17600 1582
Total 6200 99200 1805 2302

Sheet2

Sheet3

Expected

demand

Expected

demand

per

production

day

Workers

needed

Days

worked

per

month

Production

cost

Jan900418.22214400

Feb700397.81811200

Mar800387.62112800

April12005711.42119200

May15006813.62224000

June11005511.02017600

Total620099200

Sheet1

Expected demand Expected demand per production day Workers needed Days worked per month Production cost Hiring cost Layoff costs
Jan 900 41 8.2 22 14400 0 0
Feb 700 39 7.8 18 11200 600
Mar 800 38 7.6 21 12800 120
April 1200 57 11.4 21 19200 1143
May 1500 68 13.6 22 24000 662
June 1100 55 11.0 20 17600 1582
Total 6200 99200 1805 2302

Sheet2

Sheet3

Expected

demand

Expected

demand

per

production

day

Workers

needed

Days

worked

per

month

Production

cost

Hired

workers

Hiring

cost

Layoff

workers

Layoff

costs

Jan900418.2221440000

Feb700397.81811200(8.2-7.8)240

Mar800387.62112800(7.8-7.6)120

April12005711.42119200(11.4-7.6)1143

May15006813.62224000(13.6-11.4)662

June11005511.02017600(13.6-11)1582

Total62009920018051942

Sheet1

Expected demand Expected demand per production day Workers needed Days worked per month Production cost Hired workers Hiring cost Layoff workers Layoff costs
Jan 900 41 8.2 22 14400 0 0
Feb 700 39 7.8 18 11200 (8.2-7.8) 240
Mar 800 38 7.6 21 12800 (7.8-7.6) 120
April 1200 57 11.4 21 19200 (11.4-7.6) 1143
May 1500 68 13.6 22 24000 (13.6-11.4) 662
June 1100 55 11.0 20 17600 (13.6-11) 1582
Total 6200 99200 1805 1942

Sheet2

Sheet3

Aggregate Plan

MonthJan

amplifiers1500

MPS

Weeks1234

240 watt amps100100

150 watt amps500500

75 watt amps300

Sheet1

Aggregate Plan
Month Jan Feb
amplifiers 1500 1200
8
MPS 5 6 7
Weeks 1 2 3 4
240 watt amps 100 100
150 watt amps 500 500
75 watt amps 300

Sheet2

Sheet3

Quantity

needed

Part B2*50100

Part C3*50150

Part E2*100+2*150500

Part F2*150300

Part G1*300300

Part D2*100 +1*300500

Sheet1

Aggregate Plan
Month Jan Feb
amplifiers 1500 1200
8
MPS 5 6 7
Weeks 1 2 3 4
240 watt amps 100 100
150 watt amps 500 500
75 watt amps 300
Quantity needed
Part B 2*50 100
Part C 3*50 150
Part E 2*100+2*150 500
Part F 2*150 300
Part G 1*300 300
Part D 2*100 +1*300 500

Sheet2

Sheet3

ABCDEFEDG2wks1 wk3 wks2wks2wks2wks1 wk1 wk1 wkweek1week8

Quantity

needed

Part B2*50100

Part C3*50150

Part E2*100+2*150500

Part F2*150300

Part G1*300300

Part D2*100 +1*300500

ItemsWeeks12345678

ARequired date50

AOrder date50

BRequired date100

BOrder date100

CRequired date150

COrder date150

ERequired date500

EOrder date500

FRequired date300

FOrder date300

GRequired date300

GOrder date300

DRequired date500

DOrder date500

Sheet1

Aggregate Plan
Month Jan
amplifiers 1500 Items Weeks 1 2 3 4 5 6 7 8
A Required date 50
MPS A Order date 50
Weeks 1 2 3 4 B Required date 100
240 watt amps 100 100 B Order date 100
150 watt amps 500 500 C Required date 150
75 watt amps 300 C Order date 150
E Required date 500
E Order date 500
F Required date 300
F Order date 300
G Required date 300
G Order date 300
D Required date 500
D Order date 500
Quantity needed
Part B 2*50 100
Part C 3*50 150
Part E 2*100+2*150 500
Part F 2*150 300
Part G 1*300 300
Part D 2*100 +1*300 500

A

B

C

D

E

F

E

2 wks

1 wk

3 wks

2 wks

2 wks

2 wks

1 wk

1 wk

1 wk

week 1

week 8

Sheet2

Sheet3

Quantity

needed

Part B2*50100

Part C3*50150

Part E2*100+2*150500

Part F2*150300

Part G1*300300

Part D2*100 +1*300500

Hrs/order1

Capacity (hrs/day)12

Day12345

Orders1014131014

Capacity needed (hrs)1014131014

Capacity available (hrs)2-2-12-2

Sheet1

Hrs/order 1
Capacity (hrs/day) 12
Day 1 2 3 4 5
Orders 10 14 13 10 14
Capacity needed (hrs) 10 14 13 10 14
Capacity available (hrs) 2 -2 -1 2 -2

Sheet2

Sheet3

Sheet1

Hrs/order 1
Capacity (hrs/day) 12
Day 1 2 3 4 5
Orders 10 14 13 10 14
Capacity needed (hrs) 10 14 13 10 14
Capacity available (hrs) 2 -2 -1 2 -2

Sheet2

Sheet3