© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Closing the Project
9
(Premium)
Teaching Strategies
- The two vignettes in this chapter address the lessons students should have learned during a project in which they participated. The lessons learned should be recorded as the project progresses so they are not forgotten by the time the project is finished. Lessons learned from other projects can be a valuable resource for saving time and money on the current project.
- Becoming accustomed to recording and reflecting on lessons learned from each project can be an invaluable way to help save expenses on the next project. It can help project managers avoid making the same mistakes twice and can help them to implement time saving processes.
- Have students identify lessons learned that can help them in this course or in other courses they are taking.
- Have each student describe a project on which he or she has been a team member. For each project, have the student describe the best lesson learned from the project and one thing that should have been done differently. Record these lessons to create a best practices list for projects and a list of how to improve future projects.
Optional Supplemental Activities
- Have the students read the real-world vignettes and research the Internet for other articles about the two projects covered in the vignettes.
- Have them read the chapter and answer all of the Reinforce Your Learning questions and the end-of-chapter questions.
- Have students present a summary of an article from the project management journal found in the Internet exercise. If possible, have the students contact the author of the article to discuss the contents.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Chapter Concepts
Actions that should be taken when closing a project
Conducting a post-project evaluation
The importance of documenting lessons learned
The need to organize and archive project documents
Obtaining feedback from the customer about the project
Early termination of projects
Chapter Concepts
- This chapter discusses the various activities involved in the process of closing the project. After project work is completed, and all the deliverables are accepted by the customer, the performing phase of the project ends. The project then moves into the fourth and final phase of the project life cycle—closing the project.
Based on the material in this chapter, students will become familiar with:
- Actions that should be taken when closing a project
- Conducting a post-project evaluation
- The importance of documenting lessons learned
- The need to organize and archive project documents
- Obtaining feedback from the customer about the project
- Early termination of projects
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Learning Outcomes
Identify actions that should be taken during the process of closing a project
Conduct a post-project evaluation
Discuss the value and use of lessons learned
Explain the importance of organizing and archiving project documents
Obtain customer feedback about the project
Describe situations that could result in early project termination
Learning Outcomes
After studying this chapter, students should be able to:
- Identify actions that should be taken during the process of closing a project
- Conduct a post-project evaluation
- Discuss the value and use of lessons learned
- Explain the importance of organizing and archiving project documents
- Obtain customer feedback about the project
- Describe situations that could result in early project termination
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Project Integration Management
Project Procurement Management
Project Management Knowledge Areas from PMBOK® Guide
Project Management Knowledge Areas from PMBOK® Guide
Concepts in this chapter support the following Project Management Knowledge Areas of the PMI Guide to the Project Management Body of Knowledge (PMBOK® Guide):
Project Integration Management
Project Procurement Management
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Lessons Learned on the Proving Grounds
What Proterra Did
- Listened to the customer
- Implemented formal PM process
- Overcommunicated expectations to entire team
- Completed a comparative analysis
- Incorporated requests into design prior to production
- Provided an onsite technician to answer maintenance questions
- Developed education sessions
Outcomes
- Saved time on product reviews and changes during production
- Avoided rework
- Improved cash flow by delivering products on time
- Improved customer satisfaction
- Recorded and used their lessons learned
Vignette A: Lessons Learned on the Proving Grounds
Proterra, a U. S. electric bus start-up from Greenville, South Carolina, USA, has used the lessons learned from successfully delivering three buses to the King County Metro Transit, Seattle, Washington, USA, to develop processes to accelerate the delivery of future bus orders. The Metro has been testing the functionality to determine if the buses meet their requirements to serve the customers in the county’s public transportation market. Following a successful test and adoption, Proterra has an option to possibly supply an additional 200 buses over five years.
- What Proterra Did:
- Listened to the customer
- Implemented a more formal project management process
- Overcommunicated of the customer’s expectations to everyone on the bus production team
- Completed a comparative analysis of the standard bus design to the desired specifications
- Incorporated customer and community requests into the design
- Provided an onsite technician to answer maintenance questions
- Developed education sessions
- Outcomes
- Saved time on product reviews and changes during production
- Avoided rework
- Improved cash flow by delivering products on time
- Improved customer satisfaction
Proterra recorded and used their lessons learned to be in position to be efficient and cost effective if they should receive any more orders for buses for the King County Metro Transit. The project team has processes in place to be responsive due to paying attention to the lessons learned.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Learning from the Atomic Age
Increased Nuclear Power Generation
- Closed facilities have reopened
- Construction of new reactors
- Public acceptance
- Regulation changes for fossil fuel use
- Increased need for power
Evaluation Findings
- Variability of qualifications
- Stringent safety standards
- Strict regulatory requirements
- Standardization of design
- Multiple reactor construction
- Modular components
- Well-trained project managers
Vignette B: Learning from the Atomic Age
Incidents at the tsunami damaged Fukushima Daiichi power plant in Japan, Three Mile Island in the United States, and Chernobyl in the former Soviet Union have had an effect on stakeholders, including nuclear-facility project teams, worldwide. These events have been credited with the downturn in the number of projects in the 1970s and the closure of Japanese facilities immediately following the tsunami-influenced meltdown. Together, these terminated projects have left a significant gap in the talent pool for nuclear-experienced workers; many project managers and team members were forced to seek employment in other industries.
- Changes
- Closed Japanese facilities have reopened
- 15 countries are constructing 67 new reactors
- Public acceptance is rising through education and public consultation
- Changes in regulations have decreased the construction rate of fossil fuel-fired facilities for power generation
- Projected power production for 2040 is 624 gigawatts to be generated by nuclear facilities
- Recent growth
- created a demand for talent to staff the project teams for construction and for operation
- catalyzed a need to provide leadership for the projects
- mandated determination of best practices for the industry
- How gather information for future projects
- Examination of completed nuclear power projects
- Post project evaluations
- Evaluation findings
- Variability of the vocational and professional qualifications and work practices for team members from different countries
- Need for stringent safety standards and education for new technologies and processes
- Strict regulatory requirements for the industry - build things exactly the way you say you’re going to build them
- Standardization of design decisions and reduction of design tweaking
- Building of multiple reactors at the same time
- Use of modular components to construct the reactors
Jerry D. Lainhart, PMP, turnover manager, Haiyang AP1000, Westinghouse Electric Co., Haiyang, China, said, “As nuclear construction projects increase, so, too, will the need for project managers who are well-trained, formally qualified and sufficiently experienced to lead this type of large, complex project successfully.” The problems found in the evaluations of the projects could multiply through the growing number of projects to construct nuclear facilities. Careful attention to lessons learned from prior projects might have saved them costly delays.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Project Closing Actions
- Collect and make final payments
- Recognize and evaluate staff
- Conduct post-project evaluation
- Document lessons learned
- Organize and archive project documents
Project Closing Actions
- The process of closing the project involves various actions, including:
- Collecting and making final payments
- Recognizing and evaluating staff
- Conducting a post-project evaluation
- Documenting lessons learned
- Organizing and archiving project documents
- Activities associated with closing the project should be identified and included in the project baseline plan. The figure shown in this slide depicts the project life cycle. We will discuss each of these steps in more detail in the upcoming slides.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Final Payments
Payments from customer
Have activity listed to perform collection
Assure that all the payments have been received
Payments to others
Verify all payments have been made
Record actual costs
Account closing
Perform financial analysis on the project
Compare actual costs versus baseline budget
Final Payments
- Assuring that all payments have been collected from the customer is an activity that must be performed during the closing phase.
- Project managers must also verify that all payments have been made to anyone else involved in the project
- Such as subcontractors, consultants, vendors, or suppliers for any purchased materials or services
- Once all payments have been received and made, the project “books,” or accounting records, can be closed.
- A financial analysis of the project can be made in which final actual costs are compared to the project baseline budget.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Staff Recognition And Evaluation
End project with recognition and celebration
Recognize team members for contributions
Celebrate the success of the project
Prepare individual performance evaluations
Mention how knowledge expanded during project
Identify areas where need further development
Share during individual meetings or give to supervisor
Staff Recognition And Evaluation
- Successful projects should end with some type of recognition and celebration.
- This helps boost the morale of the team members through recognizing their work.
- It also helps to celebrate a successful project.
- The project manager should prepare a written performance evaluation of each member of the project team.
- It should mention how each has expanded her or his knowledge as a result of the project assignment
- It also identifies areas where he or she needs to develop further.
- These evaluations should be shared during individual meetings with the team members, or given to their supervisor to share with them.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Post Project Evaluation
- Review and evaluate project performance
- Identify improvements
- Hold individual meetings with members
- Hold project team meeting
- Prepare written report with lessons learned and recommendations
Post Project Evaluation
- The post-project evaluation stage, which occurs during the closing phase, is an important time to review the project and identify areas that went well and where improvements are necessary.
- Hold individual meetings with team members to give feedback on each one about their performance and to get feedback from them on how to improve future projects.
- At the group meeting with the project team, the project manager should lead a discussion of what happened during performance of the project and solicit specific recommendations for improvement.
- As you can see in the list on this slide, topics to be discussed at group meetings can include.
- Technical performance
- Budget performance
- Schedule performance
- Project planning and control
- Risk management
- Customer relationships
- Stakeholder engagement
- Team relationships
- Communications
- Problem identification and resolution
- Lessons learned
- Recommendations for future projects
- The project manager should prepare a written report of project performance including lessons learned and recommendations.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Lessons Learned
Purpose of identifying and documenting
Capitalize on knowledge and experience gained
Improve performance on future projects
Knowledge base system or repository
Retrieve lessons learned from prior projects
Easily access information by category or subject
Record keeping throughout project
Capture lesson at time of lesson instead of end of project
Have as agenda topic at meetings and in training sessions
Lessons Learned
- The purpose of identifying and documenting lessons learned is to capitalize on the knowledge and experience gained from the project.
- This practice helps to improve performance on future projects.
- The project organization should establish a knowledge base system that includes an easily accessible information storehouse that encourages project managers and teams to retrieve lessons learned and information from previous projects.
- The system should organize information so that it is easily retrievable by category or subject of lesson learned or by key words.
- The project team should not wait until the end of the project to capture and document lessons learned.
- It should be done on an ongoing basis throughout the planning and performing phases of the project.
- Have lessons learned be an agenda topic on a new project and include in project management training.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Archive Project Documents
Organize, file, and archive appropriate documents
Organize system to make information easily retrievable
Create database of common data elements
Analyze elements for trends
Examine records for bidding, planning, and performing future projects
Archive Project Documents
- During project closing, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived.
- Good organization helps make information readily retrievable for future use.
- It can be valuable to create a database of common data elements from past projects.
- Helps to analyze and determine if there are trends or correlations between projects
- Can be helpful in bidding, planning, and/or performing future projects
- This should be done as part of, or in addition to, the documents in the archive
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Customer Feedback
Post-project evaluation meeting with customer
Determine if provided the expected benefits
Assess the level of customer satisfaction
Obtain any feedback with open-ended questions
Discuss future opportunities
Secure permission to use as reference
Participants
Key project team members
Key customer representatives
Project manager
Customer Feedback
- Having a post-project evaluation meeting with the customer or sponsor is just as important as having the internal post-project meetings within the project team members.
- The purposes of this meeting is to:
- Determine whether the project provided the customer with the expected benefits
- Assess the level of customer satisfaction
- Obtain any feedback that would be helpful in future business relationships with this customer or with other customers
- Discuss future opportunities
- Secure permission to use that customer as a reference
- Meeting participants should involve the:
- Key project team members
- Key representatives of the customer’s organization who were involved with the project
- Project manager
- The project manager should schedule the meeting for a time when the customer is in a position to determine whether the project met expectations and achieved the anticipated benefits.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Post-Project Customer Evaluation Survey
- Analyze for trends
- Seek permission for reference
Post-Project Customer Evaluation Survey
- The figure in this slide depicts a post-project customer evaluation survey.
- The evaluation survey can be valuable.
- Analyze it for trends between projects
- Provides an opportunity for ask permission for reference from the client
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
List circumstances that require a project to be terminated before it is completed.
Student Discussion
Not all projects are finished. List some of the circumstances that require a project to be terminated before it is completed.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Possible responses to Student Discussion
Financial situations
Project return on investment change
Dissatisfaction with the project progress
Project needs have changed
List circumstances that require a project to be terminated before it is completed.
- There may be circumstances that require a project to be terminated before it is completed.
- Projects can be terminated by the sponsor or customer because of:
- Financial situations (the client runs out of money or the project becomes too expensive)
- Project return on investment change (perhaps from a change in the economy, such as a recession)
- Dissatisfaction with the project progress (sometimes the client orders a project terminated because it is progressing too slowly)
- Project needs have changed (the original project no longer suits the client’s requirements)
- Project managers must monitor the level of customer satisfaction continually throughout the project and take corrective action at the first hint of any dissatisfaction.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Critical Success Factors
Recognize the project team and celebrate accomplishments throughout the project.
Regularly ask the customer about the level of satisfaction with the performance and progress of the project and take corrective action at the first hint that the customer is not satisfied.
After the conclusion of a project, the project performance should be evaluated to learn what could be improved if a similar project were to be done in the future. Feedback should be obtained from the customer and the project team.
Capture and document lessons learned throughout the performance of the project.
Establish a knowledge base of lessons learned and ensure that they are communicated and used on future projects.
Organize and archive project documentation and analyze key data that could be helpful in bidding, planning, or performing future projects.
Retain customer evaluation and feedback information that could be valuable in developing proposals for other projects for the same customer in the future.
Critical Success Factors
- Recognize the project team and celebrate accomplishments throughout the project.
- Regularly ask the customer about the level of satisfaction with the performance and progress of the project and take corrective action at the first hint that the customer is not satisfied.
- After the conclusion of a project, the project performance should be evaluated to learn what could be improved if a similar project were to be done in the future. Feedback should be obtained from the customer and the project team.
- Capture and document lessons learned throughout the performance of the project.
- Establish a knowledge base of lessons learned and ensure that they are communicated and used on future projects.
- Organize and archive project documentation and analyze key data that could be helpful in bidding, planning, or performing future projects.
- Retain customer evaluation and feedback information that could be valuable in developing proposals for other projects for the same customer in the future.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Summary
The fourth and final phase of the project life cycle is closing the project.
An important project closing action is staff recognition and evaluation.
Conduct post-project evaluation meetings within the project team or organization with individual team members and a group meeting with the project team to gather team feedback for improved future performance.
Identify and document lessons learned to capitalize on the knowledge and experience gained on the project in order to improve performance on future projects.
The project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that they can be readily retrieved for future use.
Conduct a post-project evaluation meeting, or distribute a customer evaluation survey to the customer or sponsor to determine whether the project provided the customer with expected benefits; assess the level of customer satisfaction; and obtain any feedback that would be helpful in future business relationships with this customer or with other customers.
Projects may be terminated before completion for various reasons.
Summary
- The fourth and final phase of the project life cycle is closing the project.
- An important project closing action is staff recognition and evaluation.
- Conduct post-project evaluation meetings within the project team or organization with individual team members and a group meeting with the project team to gather team feedback for improved future performance.
- Identify and document lessons learned to capitalize on the knowledge and experience gained on the project in order to improve performance on future projects.
- The project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that they can be readily retrieved for future use.
- Conduct a post-project evaluation meeting, or distribute a customer evaluation survey to the customer or sponsor to determine whether the project provided the customer with the expected benefits; assess the level of customer satisfaction; and obtain any feedback that would be helpful in future business relationships with this customer or with other customers.
- Projects may be terminated before completion for various reasons.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Chapter Questions
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 1
The process of closing the project involves various actions, including:
Collecting and making final payments
Recognizing and evaluating staff
Conducting a post-project evaluation
Documenting lessons learned
Organizing and archiving project documents
These activities are important to:
Make sure that the customer is satisfied
Gather information about how to improve for future projects
Determine if additional opportunities are available with the customer
Obtain permission to use the customer as a reference
Discuss what needs to be done as part of closing a project.
Why are these activities important?
1. Discuss what needs to be done as part of closing a project. Why are these activities important?
- The process of closing the project involves various actions, including:
- Collecting and making final payments
- Recognizing and evaluating staff
- Conducting a post-project evaluation
- Documenting lessons learned
- Organizing and archiving project documents
- These activities are all important to:
- Ensure that the customer is satisfied
- Gather information about how to improve for future projects
- Determine if additional opportunities are available with the customer
- Obtain permission to use the customer as a reference
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 2
The internal post-project evaluation process involves holding meetings with:
The project team or organization that performed the project
Individual team members
The group, including the project team, to gather team feedback for improved future performance
The individual meetings allow the project manager to gather information from the individual team members and let the project manager share the performance appraisal of the team member describing how the team member's skills advanced while working on the project.
The post-project team meeting is a time for the project manager to lead a discussion about how the team performed.
Discuss the internal post project evaluation process and the two types of meetings involved.
2. Discuss the internal post project evaluation process and the two types of meetings involved.
- The internal post-project evaluation process involves holding meetings with:
- The project team or organization that performed the project
- Individual team members
- The group, including the project team, to gather team feedback for improved future performance
- The individual meetings allow the project manager to gather information from the individual team members and let the project manager share the performance appraisal of the project team member describing how the team member's skills advanced while working on the project.
- The post-project team meeting is a time for the project manager to lead a discussion about how the team performed.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 3
The post-project evaluation could use a variety of open- and closed-ended questions to assess the customer’s level of satisfaction and to gather detailed comments about the parts of the project with which the customer was satisfied or dissatisfied.
Open-ended questions help the customer to describe the situation. Some examples are questions to be asked are:
How has the organization changed now that the project is complete?
What pleased you most about the project? What disappointed you during the project? How were those disappointments met by the project team?
Is the solution meeting the desired need?
How did the communication plan meet or not meet the communication needs for the project?
Descriptions of what the student would change in the next project or would improves should be related to the possible responses to the questions that the asked. For example, if an evaluation question was about the timeliness of communications, then the student’s suggestions would be to provide the customer with a communication plan and schedule for the customer to approve.
List several questions that you would ask during a post-project evaluation and describe changes that you would make in your next project to improve based upon possible responses to the questions.
3. List several questions that you would ask during a post-project evaluation and describe changes that you would make in your next project to improve based upon possible responses to the questions.
The post-project evaluation could use a variety of open- and closed-ended questions to assess the customer’s level of satisfaction and to gather detailed comments about the parts of the project with which the customer was satisfied or dissatisfied. Open-ended questions help the customer to describe the situation. Some examples are questions to be asked are: How has the organization changed now that the project is complete? What pleased you most about the project? What disappointed you during the project? How were those disappointments met by the project team? Is the solution meeting the desired need? How did the communication plan meet or not meet the communication needs for the project?
Descriptions of what the student would change in the next project or would improves should be related to the possible responses to the questions that the asked. For example, if an evaluation question was about the timeliness of communications, then the student’s suggestions would be to provide the customer with a communication plan and schedule for the customer to approve.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 4
The post-project evaluation can be conducted as a meeting with open-ended questions, or as a customer evaluation survey.
The information is used to assess the level of satisfaction of the customer, the opportunities for future work, and as a chance to ask permission to use the customer as a reference.
What are some ways you can obtain feedback from a customer after a project has been completed?
How would you use this information?
4. What are some ways you can obtain feedback from a customer after a project has been completed? How would you use this information?
- The post-project evaluation can be conducted as a meeting with open-ended questions, or as a customer evaluation survey.
- The information is used to assess the level of satisfaction of the customer, the opportunities for future work, and as a chance to ask permission to use the customer as a reference.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 5
Projects also can be terminated by the sponsor or customer for a variety of reasons including:
Financial situations
Project return on investment change
Dissatisfaction with project progress
Project needs have changed
It is wise to terminate a project
If the cost of doing the project outweighs the benefits
If the project is no longer needed
If the project is not being carried out in a satisfactory manner
Why are some projects terminated before they are completed?
When would it be wise to do so?
5. Why are some projects terminated before they are completed? When would it be wise to do so?
- Projects also can be terminated by the sponsor or customer for a variety of reasons including:
- Financial situations
- Project return on investment change
- Dissatisfaction with the project progress
- Project needs have changed
- It is wise to terminate a project if:
- The cost of doing the project outweighs the benefits
- The project is no longer needed
- If the project is not being carried out in a satisfactory manner
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Question 6
Responses will be dependent upon the project. Common lessons learned include:
Increase project team communication
Have more frequent project team meetings
Analyze project progress to be more proactive when tasks are delayed
Have more meetings with the customer
Document changes more thoroughly
Discuss risks at each project team meeting
Not all lessons learned are due to negative experiences. Positive experiences on how to implement a technology solution are also valuable lessons.
Lessons learned inform future projects because the team can implement the suggestions from prior projects and thereby avoid the same problems.
List several lessons learned from a project in which you were a project team member or project manager.
How will these lessons learned inform your future projects?
6. List several lessons learned for a project in which you were a project member or project manager. How will these lessons learned inform your future projects?
- Responses will be dependent upon the project.
- Common lessons learned include:
- Increase project team communication
- Have more frequent project team meetings
- Analyze project progress to be more proactive when tasks are delayed
- Have more meetings with the customer
- Document changes more thoroughly
- Discuss risks at each project team meeting
- Not all lessons learned are due to negative experiences. Positive experiences on how to implement a technology solution are also valuable lessons.
- Lessons learned inform future projects because the team can implement the suggestions from prior projects and thereby avoid the same problems.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Completed Project Reports
Project Lessons Learned
Post-Project Evaluations
Project Management Standards
Project Management Journals
Internet Exercises
Internet Exercises
Assign the Internet Exercises to your students as homework or complete them together in a computer lab.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Internet Exercises
Use search terms that include the project topic of interest to help find project outcomes.
The searches for "project lessons learned," "post-project evaluations," and "project management standards" result in definitions, tools, and descriptions of each.
Project management journals contain a variety of articles. Some journals have a theme and others accept articles that are of interest to the project management community.
Using your favorite Web search engine, perform a search for reports of completed projects.
Do several Web searches for "project lessons learned," "post-project evaluations," and "project management standards.”
Search for project management related journals and review several articles.
Internet Exercises
- Many projects are documented on the Internet. For example, if a student is interested in drug trials that have been completed, the search terms could be: “pharmaceutical drug trial project outcomes.”
- Have students share their search terms and record the terms to supply the information to other classes as lessons learned.
- The searches for "project lessons learned," "post-project evaluations," and "project management standards" result in definitions, tools, and descriptions of each.
- Have students share any additional terms they may have included to further refine their searches.
- Project management journals contain a variety of articles. Some journals have a theme and others accept articles that are of interest to the project management community.
- Have students examine the trends in the themes of the articles to see if a particular topic is more frequently presented, or if there is a pattern to the topics.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Factory Expansion Project
Case Study 1
Case Study #1: Factory Expansion Project
This activity involves an electronics company whose sales are expanding and requires additional capacity.
Group Activity
Divide the course participants into groups of three or four to develop responses to the case questions. Have each group choose a spokesperson to present its responses to the entire class.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 1
Question 1
Andy barged into Jacob’s office without an appointment and without respecting that Jacob might be in the middle of other business.
Andy should have scheduled an appointment and listened to Jacob.
What should Andy Gibson have done differently in his meeting with Jacob Clemson in Jacob’s office?
1. What should Andy Gibson have done differently in his meeting with Jacob Clemson in Jacob’s office?
- Andy barged into Jacob’s office without an appointment and without respecting that Jacob might be in the middle of other business.
- Andy should have scheduled an appointment and listened to Jacob.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 1
Question 2
Clearly, Andy needs to work on his communication skills. He also needs to learn to listen to Jacob’s concerns.
What are some things Andy could have done differently from his initial contact with Mr. Clemson and during the project?
2. What are some things Andy could have done differently from his initial contact with Mr. Clemson and during the project?
- Clearly, Andy needs to work on his communication skills.
- He also needs to learn to listen to Jacob’s concerns.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 1
Question 3
Jacob needs to stop and think about the message he wants to convey and then work on stating his views clearly.
Jacob should have explored the reputation of Andy's company and determined if there were other companies that did similar work in the area.
Jacob could have documented the problems with the project and communicated those problems in writing.
Jacob also can withhold the final payments and the bonus until the project is completed to his specifications.
What are some things Jacob could have done differently from the time he met Andy Gibson initially and during the project?
3. What are some things Jacob could have done differently from the time he met Andy Gibson initially and during the project?
- Jacob needs to stop and think about the message he wants to convey and then work on stating his views clearly.
- He should have explored the reputation of Andy's company and determined if there were other companies that did similar work in the area.
- Jacob could have documented the problems with the project and communicated those problems in writing.
- Jacob also can withhold the final payments and the bonus until the project is completed to his specifications.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 1
Question 4
Gerri clearly thinks Andy is being unethical and she should re-think their business relationship.
Some respondents may believe that Gerri should leave this company because she disagrees with the management style and find a position that is more suited to her ethical standards.
Other responses may propose solutions for how to help with the project communications and to help avoid the unethical proposal to obtain the bonus money.
What should Gerri do?
4. What should Gerri do?
- Gerri clearly thinks Andy is being unethical and she should re-think their business relationship.
- Some respondents may believe that Gerri should leave this company because she disagrees with the management style and find a position that is more suited to her ethical standards.
- Other responses may propose solutions for how to help with the project communications and to help avoid the unethical proposal to obtain the bonus money.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Market Research Report Project
Case Study 2
Case Study #2: Market Research Report Project
This activity involves a project manager and her communication plan with the customer.
Group Activity
Divide the course participants into groups of three or four to develop responses to the case questions. Have each group choose a spokesperson to present its responses to the entire class.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 2
Question 1
Christine was the project customer and it seemed that Christine and Sarah were communicating.
Meghan's assumption that Sarah was communicating to Christine may have been problematic and contributed to Christine’s dissatisfaction at the point of distribution.
After making the changes that Christine outlined, she would be satisfied.
Did Meghan’s team satisfy the customer? Why or why not?
1. Did Meghan’s team satisfy the customer? Why or why not?
- Christine was the project customer and it seemed that Christine and Sarah were communicating.
- Meghan's assumption that Sarah was communicating to Christine may have been a problem and contributed to Christine’s dissatisfaction at the point of distribution.
- After making the changes that Christine outlined, she would be satisfied.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 2
Question 2
Christine is the customer that contracted with Meghan's team for the project and it is important to communicate with the customer.
Meghan should have included Christine on the prior communications.
Communications should clear and comprehensive so there are no surprises for either the customer or the contractor at the project’s close.
Meghan should respond with a plan to implement corrections because the customer is not satisfied and has not accepted the product.
How should Meghan respond to the comments from Christine after Sarah had given feedback and approval for the final report?
2. How should Meghan respond to the comments from Christine after Sarah had given feedback and approval for the final report?
- Christine is the customer that contracted with Meghan's team for the project and it is important to communicate with the customer.
- Meghan should have included Christine on the prior communications.
- Communications should clear and comprehensive so there are no surprises for either the customer or the contractor at the project’s close.
- Meghan should respond with a plan to implement the necessary corrections because the customer is not satisfied and has not accepted the product.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 2
Question 3
Meghan should plan the work necessary to make the corrections to the product and meet with the project team to determine if they can be completed within the allotted slack time of a week.
The project team had gone through the steps of closing this project.
They have one week of slack in the schedule before they would be causing another project to be delayed. What should Meghan do with her team?
3. The project team had gone through the steps of closing this project. They have one week of slack in the schedule before they would be causing another project to be delayed. What should Meghan do with her team?
Meghan should plan the work necessary to make the corrections to the product and meet with the project team to determine if they can be completed within the allotted slack time of a week.
*
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use.
Case Study 2
Question 4
Even though Christine said that she did not have time to devote to the project, Christine should have been copied on all the communications with Sarah, her project manager.
Both Christine and Meghan were surprised at the end of the project and neither the contractor nor the customer should be surprised at a project’s close.
Any changes to the project should be approved by the customer in writing.
What should Meghan have done differently in the project?
4. What should Meghan have done differently in the project?
- Even though Christine said that she did not have time to devote to the project, Christine should have been copied on all the communications with Sarah, her project manager.
- Both Christine and Meghan were surprised at the end of the project and neither the contractor nor the customer should ever be surprised at a project’s close.
- Any changes to the project should be approved by the customer in writing.
*
(Premium)
Teaching Strategies
- The two vignettes in this chapter address the lessons students should have learned during a project in which they participated. The lessons learned should be recorded as the project progresses so they are not forgotten by the time the project is finished. Lessons learned from other projects can be a valuable resource for saving time and money on the current project.
- Becoming accustomed to recording and reflecting on lessons learned from each project can be an invaluable way to help save expenses on the next project. It can help project managers avoid making the same mistakes twice and can help them to implement time saving processes.
- Have students identify lessons learned that can help them in this course or in other courses they are taking.
- Have each student describe a project on which he or she has been a team member. For each project, have the student describe the best lesson learned from the project and one thing that should have been done differently. Record these lessons to create a best practices list for projects and a list of how to improve future projects.
Optional Supplemental Activities
- Have the students read the real-world vignettes and research the Internet for other articles about the two projects covered in the vignettes.
- Have them read the chapter and answer all of the Reinforce Your Learning questions and the end-of-chapter questions.
- Have students present a summary of an article from the project management journal found in the Internet exercise. If possible, have the students contact the author of the article to discuss the contents.
*
Chapter Concepts
- This chapter discusses the various activities involved in the process of closing the project. After project work is completed, and all the deliverables are accepted by the customer, the performing phase of the project ends. The project then moves into the fourth and final phase of the project life cycle—closing the project.
Based on the material in this chapter, students will become familiar with:
- Actions that should be taken when closing a project
- Conducting a post-project evaluation
- The importance of documenting lessons learned
- The need to organize and archive project documents
- Obtaining feedback from the customer about the project
- Early termination of projects
*
Learning Outcomes
After studying this chapter, students should be able to:
- Identify actions that should be taken during the process of closing a project
- Conduct a post-project evaluation
- Discuss the value and use of lessons learned
- Explain the importance of organizing and archiving project documents
- Obtain customer feedback about the project
- Describe situations that could result in early project termination
*
Project Management Knowledge Areas from PMBOK® Guide
Concepts in this chapter support the following Project Management Knowledge Areas of the PMI Guide to the Project Management Body of Knowledge (PMBOK® Guide):
Project Integration Management
Project Procurement Management
*
Vignette A: Lessons Learned on the Proving Grounds
Proterra, a U. S. electric bus start-up from Greenville, South Carolina, USA, has used the lessons learned from successfully delivering three buses to the King County Metro Transit, Seattle, Washington, USA, to develop processes to accelerate the delivery of future bus orders. The Metro has been testing the functionality to determine if the buses meet their requirements to serve the customers in the county’s public transportation market. Following a successful test and adoption, Proterra has an option to possibly supply an additional 200 buses over five years.
- What Proterra Did:
- Listened to the customer
- Implemented a more formal project management process
- Overcommunicated of the customer’s expectations to everyone on the bus production team
- Completed a comparative analysis of the standard bus design to the desired specifications
- Incorporated customer and community requests into the design
- Provided an onsite technician to answer maintenance questions
- Developed education sessions
- Outcomes
- Saved time on product reviews and changes during production
- Avoided rework
- Improved cash flow by delivering products on time
- Improved customer satisfaction
Proterra recorded and used their lessons learned to be in position to be efficient and cost effective if they should receive any more orders for buses for the King County Metro Transit. The project team has processes in place to be responsive due to paying attention to the lessons learned.
*
Vignette B: Learning from the Atomic Age
Incidents at the tsunami damaged Fukushima Daiichi power plant in Japan, Three Mile Island in the United States, and Chernobyl in the former Soviet Union have had an effect on stakeholders, including nuclear-facility project teams, worldwide. These events have been credited with the downturn in the number of projects in the 1970s and the closure of Japanese facilities immediately following the tsunami-influenced meltdown. Together, these terminated projects have left a significant gap in the talent pool for nuclear-experienced workers; many project managers and team members were forced to seek employment in other industries.
- Changes
- Closed Japanese facilities have reopened
- 15 countries are constructing 67 new reactors
- Public acceptance is rising through education and public consultation
- Changes in regulations have decreased the construction rate of fossil fuel-fired facilities for power generation
- Projected power production for 2040 is 624 gigawatts to be generated by nuclear facilities
- Recent growth
- created a demand for talent to staff the project teams for construction and for operation
- catalyzed a need to provide leadership for the projects
- mandated determination of best practices for the industry
- How gather information for future projects
- Examination of completed nuclear power projects
- Post project evaluations
- Evaluation findings
- Variability of the vocational and professional qualifications and work practices for team members from different countries
- Need for stringent safety standards and education for new technologies and processes
- Strict regulatory requirements for the industry - build things exactly the way you say you’re going to build them
- Standardization of design decisions and reduction of design tweaking
- Building of multiple reactors at the same time
- Use of modular components to construct the reactors
Jerry D. Lainhart, PMP, turnover manager, Haiyang AP1000, Westinghouse Electric Co., Haiyang, China, said, “As nuclear construction projects increase, so, too, will the need for project managers who are well-trained, formally qualified and sufficiently experienced to lead this type of large, complex project successfully.” The problems found in the evaluations of the projects could multiply through the growing number of projects to construct nuclear facilities. Careful attention to lessons learned from prior projects might have saved them costly delays.
*
Project Closing Actions
- The process of closing the project involves various actions, including:
- Collecting and making final payments
- Recognizing and evaluating staff
- Conducting a post-project evaluation
- Documenting lessons learned
- Organizing and archiving project documents
- Activities associated with closing the project should be identified and included in the project baseline plan. The figure shown in this slide depicts the project life cycle. We will discuss each of these steps in more detail in the upcoming slides.
*
Final Payments
- Assuring that all payments have been collected from the customer is an activity that must be performed during the closing phase.
- Project managers must also verify that all payments have been made to anyone else involved in the project
- Such as subcontractors, consultants, vendors, or suppliers for any purchased materials or services
- Once all payments have been received and made, the project “books,” or accounting records, can be closed.
- A financial analysis of the project can be made in which final actual costs are compared to the project baseline budget.
*
Staff Recognition And Evaluation
- Successful projects should end with some type of recognition and celebration.
- This helps boost the morale of the team members through recognizing their work.
- It also helps to celebrate a successful project.
- The project manager should prepare a written performance evaluation of each member of the project team.
- It should mention how each has expanded her or his knowledge as a result of the project assignment
- It also identifies areas where he or she needs to develop further.
- These evaluations should be shared during individual meetings with the team members, or given to their supervisor to share with them.
*
Post Project Evaluation
- The post-project evaluation stage, which occurs during the closing phase, is an important time to review the project and identify areas that went well and where improvements are necessary.
- Hold individual meetings with team members to give feedback on each one about their performance and to get feedback from them on how to improve future projects.
- At the group meeting with the project team, the project manager should lead a discussion of what happened during performance of the project and solicit specific recommendations for improvement.
- As you can see in the list on this slide, topics to be discussed at group meetings can include.
- Technical performance
- Budget performance
- Schedule performance
- Project planning and control
- Risk management
- Customer relationships
- Stakeholder engagement
- Team relationships
- Communications
- Problem identification and resolution
- Lessons learned
- Recommendations for future projects
- The project manager should prepare a written report of project performance including lessons learned and recommendations.
*
Lessons Learned
- The purpose of identifying and documenting lessons learned is to capitalize on the knowledge and experience gained from the project.
- This practice helps to improve performance on future projects.
- The project organization should establish a knowledge base system that includes an easily accessible information storehouse that encourages project managers and teams to retrieve lessons learned and information from previous projects.
- The system should organize information so that it is easily retrievable by category or subject of lesson learned or by key words.
- The project team should not wait until the end of the project to capture and document lessons learned.
- It should be done on an ongoing basis throughout the planning and performing phases of the project.
- Have lessons learned be an agenda topic on a new project and include in project management training.
*
Archive Project Documents
- During project closing, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived.
- Good organization helps make information readily retrievable for future use.
- It can be valuable to create a database of common data elements from past projects.
- Helps to analyze and determine if there are trends or correlations between projects
- Can be helpful in bidding, planning, and/or performing future projects
- This should be done as part of, or in addition to, the documents in the archive
*
Customer Feedback
- Having a post-project evaluation meeting with the customer or sponsor is just as important as having the internal post-project meetings within the project team members.
- The purposes of this meeting is to:
- Determine whether the project provided the customer with the expected benefits
- Assess the level of customer satisfaction
- Obtain any feedback that would be helpful in future business relationships with this customer or with other customers
- Discuss future opportunities
- Secure permission to use that customer as a reference
- Meeting participants should involve the:
- Key project team members
- Key representatives of the customer’s organization who were involved with the project
- Project manager
- The project manager should schedule the meeting for a time when the customer is in a position to determine whether the project met expectations and achieved the anticipated benefits.
*
Post-Project Customer Evaluation Survey
- The figure in this slide depicts a post-project customer evaluation survey.
- The evaluation survey can be valuable.
- Analyze it for trends between projects
- Provides an opportunity for ask permission for reference from the client
*
Not all projects are finished. List some of the circumstances that require a project to be terminated before it is completed.
*
- There may be circumstances that require a project to be terminated before it is completed.
- Projects can be terminated by the sponsor or customer because of:
- Financial situations (the client runs out of money or the project becomes too expensive)
- Project return on investment change (perhaps from a change in the economy, such as a recession)
- Dissatisfaction with the project progress (sometimes the client orders a project terminated because it is progressing too slowly)
- Project needs have changed (the original project no longer suits the client’s requirements)
- Project managers must monitor the level of customer satisfaction continually throughout the project and take corrective action at the first hint of any dissatisfaction.
*
Critical Success Factors
- Recognize the project team and celebrate accomplishments throughout the project.
- Regularly ask the customer about the level of satisfaction with the performance and progress of the project and take corrective action at the first hint that the customer is not satisfied.
- After the conclusion of a project, the project performance should be evaluated to learn what could be improved if a similar project were to be done in the future. Feedback should be obtained from the customer and the project team.
- Capture and document lessons learned throughout the performance of the project.
- Establish a knowledge base of lessons learned and ensure that they are communicated and used on future projects.
- Organize and archive project documentation and analyze key data that could be helpful in bidding, planning, or performing future projects.
- Retain customer evaluation and feedback information that could be valuable in developing proposals for other projects for the same customer in the future.
*
Summary
- The fourth and final phase of the project life cycle is closing the project.
- An important project closing action is staff recognition and evaluation.
- Conduct post-project evaluation meetings within the project team or organization with individual team members and a group meeting with the project team to gather team feedback for improved future performance.
- Identify and document lessons learned to capitalize on the knowledge and experience gained on the project in order to improve performance on future projects.
- The project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that they can be readily retrieved for future use.
- Conduct a post-project evaluation meeting, or distribute a customer evaluation survey to the customer or sponsor to determine whether the project provided the customer with the expected benefits; assess the level of customer satisfaction; and obtain any feedback that would be helpful in future business relationships with this customer or with other customers.
- Projects may be terminated before completion for various reasons.
*
1. Discuss what needs to be done as part of closing a project. Why are these activities important?
- The process of closing the project involves various actions, including:
- Collecting and making final payments
- Recognizing and evaluating staff
- Conducting a post-project evaluation
- Documenting lessons learned
- Organizing and archiving project documents
- These activities are all important to:
- Ensure that the customer is satisfied
- Gather information about how to improve for future projects
- Determine if additional opportunities are available with the customer
- Obtain permission to use the customer as a reference
*
2. Discuss the internal post project evaluation process and the two types of meetings involved.
- The internal post-project evaluation process involves holding meetings with:
- The project team or organization that performed the project
- Individual team members
- The group, including the project team, to gather team feedback for improved future performance
- The individual meetings allow the project manager to gather information from the individual team members and let the project manager share the performance appraisal of the project team member describing how the team member's skills advanced while working on the project.
- The post-project team meeting is a time for the project manager to lead a discussion about how the team performed.
*
3. List several questions that you would ask during a post-project evaluation and describe changes that you would make in your next project to improve based upon possible responses to the questions.
The post-project evaluation could use a variety of open- and closed-ended questions to assess the customer’s level of satisfaction and to gather detailed comments about the parts of the project with which the customer was satisfied or dissatisfied. Open-ended questions help the customer to describe the situation. Some examples are questions to be asked are: How has the organization changed now that the project is complete? What pleased you most about the project? What disappointed you during the project? How were those disappointments met by the project team? Is the solution meeting the desired need? How did the communication plan meet or not meet the communication needs for the project?
Descriptions of what the student would change in the next project or would improves should be related to the possible responses to the questions that the asked. For example, if an evaluation question was about the timeliness of communications, then the student’s suggestions would be to provide the customer with a communication plan and schedule for the customer to approve.
*
4. What are some ways you can obtain feedback from a customer after a project has been completed? How would you use this information?
- The post-project evaluation can be conducted as a meeting with open-ended questions, or as a customer evaluation survey.
- The information is used to assess the level of satisfaction of the customer, the opportunities for future work, and as a chance to ask permission to use the customer as a reference.
*
5. Why are some projects terminated before they are completed? When would it be wise to do so?
- Projects also can be terminated by the sponsor or customer for a variety of reasons including:
- Financial situations
- Project return on investment change
- Dissatisfaction with the project progress
- Project needs have changed
- It is wise to terminate a project if:
- The cost of doing the project outweighs the benefits
- The project is no longer needed
- If the project is not being carried out in a satisfactory manner
*
6. List several lessons learned for a project in which you were a project member or project manager. How will these lessons learned inform your future projects?
- Responses will be dependent upon the project.
- Common lessons learned include:
- Increase project team communication
- Have more frequent project team meetings
- Analyze project progress to be more proactive when tasks are delayed
- Have more meetings with the customer
- Document changes more thoroughly
- Discuss risks at each project team meeting
- Not all lessons learned are due to negative experiences. Positive experiences on how to implement a technology solution are also valuable lessons.
- Lessons learned inform future projects because the team can implement the suggestions from prior projects and thereby avoid the same problems.
*
Internet Exercises
Assign the Internet Exercises to your students as homework or complete them together in a computer lab.
*
Internet Exercises
- Many projects are documented on the Internet. For example, if a student is interested in drug trials that have been completed, the search terms could be: “pharmaceutical drug trial project outcomes.”
- Have students share their search terms and record the terms to supply the information to other classes as lessons learned.
- The searches for "project lessons learned," "post-project evaluations," and "project management standards" result in definitions, tools, and descriptions of each.
- Have students share any additional terms they may have included to further refine their searches.
- Project management journals contain a variety of articles. Some journals have a theme and others accept articles that are of interest to the project management community.
- Have students examine the trends in the themes of the articles to see if a particular topic is more frequently presented, or if there is a pattern to the topics.
*
Case Study #1: Factory Expansion Project
This activity involves an electronics company whose sales are expanding and requires additional capacity.
Group Activity
Divide the course participants into groups of three or four to develop responses to the case questions. Have each group choose a spokesperson to present its responses to the entire class.
*
1. What should Andy Gibson have done differently in his meeting with Jacob Clemson in Jacob’s office?
- Andy barged into Jacob’s office without an appointment and without respecting that Jacob might be in the middle of other business.
- Andy should have scheduled an appointment and listened to Jacob.
*
2. What are some things Andy could have done differently from his initial contact with Mr. Clemson and during the project?
- Clearly, Andy needs to work on his communication skills.
- He also needs to learn to listen to Jacob’s concerns.
*
3. What are some things Jacob could have done differently from the time he met Andy Gibson initially and during the project?
- Jacob needs to stop and think about the message he wants to convey and then work on stating his views clearly.
- He should have explored the reputation of Andy's company and determined if there were other companies that did similar work in the area.
- Jacob could have documented the problems with the project and communicated those problems in writing.
- Jacob also can withhold the final payments and the bonus until the project is completed to his specifications.
*
4. What should Gerri do?
- Gerri clearly thinks Andy is being unethical and she should re-think their business relationship.
- Some respondents may believe that Gerri should leave this company because she disagrees with the management style and find a position that is more suited to her ethical standards.
- Other responses may propose solutions for how to help with the project communications and to help avoid the unethical proposal to obtain the bonus money.
*
Case Study #2: Market Research Report Project
This activity involves a project manager and her communication plan with the customer.
Group Activity
Divide the course participants into groups of three or four to develop responses to the case questions. Have each group choose a spokesperson to present its responses to the entire class.
*
1. Did Meghan’s team satisfy the customer? Why or why not?
- Christine was the project customer and it seemed that Christine and Sarah were communicating.
- Meghan's assumption that Sarah was communicating to Christine may have been a problem and contributed to Christine’s dissatisfaction at the point of distribution.
- After making the changes that Christine outlined, she would be satisfied.
*
2. How should Meghan respond to the comments from Christine after Sarah had given feedback and approval for the final report?
- Christine is the customer that contracted with Meghan's team for the project and it is important to communicate with the customer.
- Meghan should have included Christine on the prior communications.
- Communications should clear and comprehensive so there are no surprises for either the customer or the contractor at the project’s close.
- Meghan should respond with a plan to implement the necessary corrections because the customer is not satisfied and has not accepted the product.
*
3. The project team had gone through the steps of closing this project. They have one week of slack in the schedule before they would be causing another project to be delayed. What should Meghan do with her team?
Meghan should plan the work necessary to make the corrections to the product and meet with the project team to determine if they can be completed within the allotted slack time of a week.
*
4. What should Meghan have done differently in the project?
- Even though Christine said that she did not have time to devote to the project, Christine should have been copied on all the communications with Sarah, her project manager.
- Both Christine and Meghan were surprised at the end of the project and neither the contractor nor the customer should ever be surprised at a project’s close.
- Any changes to the project should be approved by the customer in writing.
*