Reflection

profilesaurabhvairagade
Chapter9.ProjectSchedulingNetworksDurationEstimationandCriticalPath.pptx

Project Management: Achieving Competitive Advantage

Fifth Edition

Chapter 9

Project Scheduling: Networks, Duration Estimation, and Critical Path

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:

1) MathType Plugin

2) Math Player (free versions available)

3) NVDA Reader (free versions available)

1

Learning Objectives (1 of 2)

9.1 Understand the importance of project scheduling techniques.

9.2 Understand and apply key scheduling terminology.

9.3 Develop an activity network using Activity-on-Node (A O N) technique.

9.4 Perform activity duration estimation based on the use of probabilistic estimating techniques.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Learning Objectives (2 of 2)

9.5 Construct the critical path for a project schedule network using forward and backward passes, determine project slack, and calculate the probability of finishing on time.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

P M B o K Core Concepts

Project Management Body of Knowledge (P M B o K) covered in this chapter includes:

Plan Schedule Management (P M B o K 6.1)

Define Activities (P M B o K 6.2)

Sequence Activities (P M B o K 6.3)

Estimate Activity Resources (P M B o K 6.4)

Estimate Activity Durations (P M B o K 6.5)

Develop Schedule (P M B o K 6.6)

Control Schedule (P M B o K 6.7)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Project Scheduling

Project scheduling requires us to follow some carefully laid-out steps, in order, for the schedule to take shape. P M B o K states, “an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.”

Project planning, as it relates to the scheduling process, has been defined by the P M B o K as:

The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Network Diagram—Serial Sequential Logic

Figure 9.2A Alternative Activity Networks for Term Paper Assignment

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Network Diagram – Nonserial Sequential Logic

Figure 9.2B Alternative Activity Networks for Term Paper Assignment

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Project Scheduling Terms (1 of 4)

Project Network Diagram: Any schematic display of the logical relationships of project activities.

Path: A sequence of activities defined by the project network logic.

Event: A point when an activity is either started or completed.

Node: One of the defining points of a network; a junction point joined to some or all of the other dependency lines (paths).

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Project Scheduling Terms (2 of 4)

Predecessors: Those activities that must be completed prior to initiation of a later activity in the network.

Successors: Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks.

Early start (E S) date: The earliest possible date the uncompleted portions of an activity can start.

Late start (L S) date: The latest possible date that an activity may begin without delaying a specified milestone.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Project Scheduling Terms (3 of 4)

Forward pass: Network calculations to determine earliest start/earliest finish for an activity through working forward through each activity in network.

Backward pass: Network calculations to determine late start/late finish for uncompleted tasks through working backward through each activity in network.

Merge activity: An activity with two or more immediate predecessors.

Burst activity: An activity with two or more immediate successors.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Project Scheduling Terms (4 of 4)

Float: The amount of time an activity may be delayed from its early start without delaying the finish of the project.

Critical path: The path through project network with the longest duration.

Critical Path Method: A network analysis technique used to determine the amount of schedule flexibility on logical network paths in project schedule network and to determine minimum project duration.

Resource-limited schedule: Start and finish dates reflect expected resource availability.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

A O A Versus A O N

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Node Labels

Figure 9.3 Labels for Activity Node

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Serial Activities

Serial activities are those that flow from one to the next, in sequence.

Figure 9.5 Project Activities Linked in Series

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Concurrent Activities

When the nature of the work allows for more than one activity to be accomplished at the same time, these activities are called concurrent, and parallel project paths are constructed through the network.

Figure 9.6 Activities Linked in Parallel (Concurrent)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.7 Merge Activity

Activity D can only begin following the completion of activities A, B, and C.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.8 Burst Activity

Activities B, C, and D can only begin following the completion of activity A.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Complete Activity Network

Figure 9.10 Complete Activity Network for Project Delta

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Duration Estimation Methods

Experience

Expert opinion

Mathematical derivation—Beta distribution

Most likely (m)

Most pessimistic (b)

Most optimistic (a)

Two assumptions used to convert m, a, and b into time estimates (T E) and variances

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.14 Symmetrical (Normal) Distribution for Activity Duration Estimation

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.15 Asymmetrical (Beta) Distribution for Activity Duration Estimation

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Activity Duration Estimates (1 of 2)

Table 9.2 Activity Duration Estimates for Project Delta

Name: Project Delta

Durations are listed in weeks

Activity Description Optimistic Most Likely Pessimistic
A Contract signing 3 4 11
B Questionnaire design 2 5 8
C Target market I D 3 6 9
D Survey sample 8 12 20
E Develop presentation 3 5 12
F Analyze results 2 4 7
G Demographic analysis 6 9 14
H Presentation to client 1 2 4

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

22

Activity Duration Estimates (2 of 2)

Table 9.3 Estimated Project Activity Times Using Beta Distribution

Name: Project Delta

Durations are listed in weeks

Activity Description T E start fraction left parenthesis 1:4:1 ration right parenthesis over 6
A Contract signing 5
B Questionnaire design 5
C Target market I D 6
D Survey sample 12.7
E Develop presentation 5.8
F Analyze results 4.2
G Demographic analysis 9.3
H Presentation to client 2.2

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Constructing the Critical Path

Forward pass—an additive move through the network from start to finish

Backward pass—a subtractive move through the network from finish to start

Critical path—the longest path from end to end which determines the shortest project length

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.16 Partial Project Activity Network with Task Durations

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.18 Activity Network with Forward Pass

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.19 Activity Network with Backward Pass

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.20 Project Network with Activity Slack and Critical Path

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.24 A O N Network with Laddering Effect

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 9.25 Example of a Hammock Activity

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Options for Reducing the Critical Path

Eliminate tasks on the critical path.

Replan serial paths to be in parallel.

Overlap sequential tasks.

Shorten the duration on critical path tasks.

Shorten early tasks.

Shorten longest tasks.

Shorten easiest tasks.

Shorten tasks that cost the least to speed up.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Summary (1 of 2)

Understand the importance of project scheduling techniques.

Understand and apply key scheduling terminology.

Develop an activity network using Activity-on-Node (A O N) technique.

Perform activity duration estimation based on the use of probabilistic estimating techniques.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Summary (2 of 2)

Construct the critical path for a project schedule network using forward and backward passes, determine project slack, and calculate the probability of finishing on time.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Copyright

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

s

2

)

(

are:

++

==

a4

ActivityDurationTE

6

mb

-

æö

==

ç÷

èø

ba

s

2

2

ActivityVariance

6

(

)

TE 1:4:1 ratio/6