Project Management Processes-8
Project Management: Process, Methodologies, and Economics
Third Edition
Chapter 9
Project Scheduling
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:
1) MathType Plugin
2) Math Player (free versions available)
3) NVDA Reader (free versions available)
Figure 9-1 W B S for a Microcomputer
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-2 Modular Array of Project Schedules
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-3 Frequency Distribution of an Activity Duration
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-4 Normal Distribution Fitted to the Data
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 90-5 Beta Distribution Fitted to the Data
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-6 Three cases of the beta distribution: (a) symmetric, (b) skewed to the right, and (c) skewed to the left
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-7 Two Examples of Activity Duration as a Function of Length
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-8 Typical Scatter Diagram
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-1 Data for Regression Analysis
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-9 Data Points and Regression Surface for the Example
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-10 Lead-Lag Relationships in Precedence Diagramming
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-2 Data for Example Project
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-11 Gantt Chart for an Early-Start Schedule
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-12 Gantt Chart for an Early-Start Schedule
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-13 Gantt Chart for the Microcomputer Development Example
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-14 Extended Gantt Chart with Task Details
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-15 Network Components
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-16 Use of a Dummy Arc Between Two Nodes
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-17 (a) Incorrect and (b) Correct Representation
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-18 Subnetwork with Two Dummy Arcs: (a) Incorrect, (b) Correct
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-19 Subnetwork with Complicated Precedence Relations: (a) Incorrect, (b) Correct
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-20 Partial Plot of the Example A O A Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-21 Using Dummy Activities to Represent Precedence Relations
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-22 Network with Activities F and G Included
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-23 Complete A O A Project Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-24 Network for Example 9-4
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-3 Sequences in the Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-4 Summary of Event Time Calculations
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-5 Summary of Start and Finish Time Analysis
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-25 A O N Network for the Example Project
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-6 Early Start and Early Finish of Project Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-7 Late Finish and Late Start of Project Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-26 Serial Activities in Simple C P M Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-27 Gantt Chart for Serial Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-28 Serial Network with Lead and Lag Constraints
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-29 Gantt Chart for Network with Lead and Lag Constraints
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-30 Partitioning of Overlapping Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-31 A O N Network of Partitioned Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-32 Second Example of an A O N Network with Serial Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-33 Compressed Network for Second Example
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-34 A O N Expansion of Second Example
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-35 Compressed Schedule for Second Example Based on Earliest Start Times
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-36 Compressed Schedule for Second Example Based on Latest Start Times
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-37 Example of a Hammock Activity
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-8 Statistics for Example Activities
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-9 Summary of Simulation Runs for Example Project
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-38 Distribution of Project Length for Simulation Runs
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-39 Example of Probabilistic Analysis with P E R T
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-40 Stochastic Network
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-41 Performance Time Distribution for the Two Sequences
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-42 Stochastic Network with Dependent Sequences
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-10 Mean Length and Standard Deviation for Sequences in Example Project
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-11 Probability of Completing Each Sequence in 22 Weeks
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-12 Principal Assumptions and Criticisms of P E R T/C P M
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-13
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-14
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-15
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Figure 9-43 Networks for Exercise 9-16
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-16
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-17
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-18
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-19
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-20
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9-21
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9B-1 Learning Curve Values for nβ
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9B-2 Cumulative Learning Curve Values for nβ
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved
Table 9C-1 Cumulative Probabilities of the Normal Distribution (areas under the standardized normalized curve from −∞ to z)
Copyright © 2017, 2005, 1994 Pearson Education, Inc. All Rights Reserved