International project management
PLANNING THE INTERNATIONAL PROJECT IN TERMS OF TIME,
COST, AND QUALITY
Chapter 5
THE CHALLENGE OF PLANNING AN INTERNATIONAL PROJECT
Why planning a project?
Planning reduces uncertainty and brings structure into chaos.
Issues with planning in international project.
Planning needs to be constantly revised due to a fast changing international environment.
The international environment is complex and difficult to predict.
More factors need to be included into project planning than for planning standard projects.
2
THE PLANNING PROCESS
The planning process can be divided into four major tasks:
1. Planning time.
2. Scheduling under resource constraints.
3. Planning cost.
4. Planning quality.
The objective of planning is to:
Minimize project duration.
Minimize the resource availability cost.
Maximize quality.
3
Required inputs:
1
3 2
4
Planning
Time
Scheduling
under
resource
constraints
Planning
Cost
Planning
Quality
Planning
Time, Cost,
Quality of the
International
Project
1. Work Breakdown Structure
2. Organizational Breakdown Structure
3. Analysis of skill sets of available staff beyond academic and job titles (based on CVs and interviews)
4. Overview of holiday entitlements of international staff in different locations
Main output: Gantt chart or network diagram
Required tools and
techniques:
- Project Network Diagram, mainly Activity on Arrow (AoA)
as basis for CPM, CPA, PERT, PDM etc.
- Gantt chart or bar chart
1. Project Scope Statement
2. Work Breakdown Structure
3. Estimates for activity duration
4. Establishment of relationships between single activities in form of precedence
5. Calendar with international holidays relevant to the international project
Main output: Resource loaded Gantt chart
Required tools and techniques:
- Loaded Gantt chart
Required inputs: 1. Financial objective / available budget
2. Cost estimates
3. Overview of international locations
involved in the project
4. Overview of salaries, facilities,
equipment and other costs in the
relevant international locations
5. Cost for risk mitigation or contingency
plans (cf. Chapter 4)
6. Development of currency fluctuations
Required tools and techniques: - Step counting cost-estimating techniques
- Exponential cost-estimating techniques
- Parametric cost-estimating techniques
- Even-loading, front-loading, back-loading budget
methods
- Periodic cost spreadsheet
- Cumulative cost spreadsheet
Required inputs:
Required inputs:
1. Project scope statement incl. cross-check of
customer’s expectation level
2. Cultural gap analysis regarding perception of quality
in involved countries and cultures
3. Functionality of product/service/project result
Not
discussed
in this book
Main output: Budget spreadsheets
Required tools and techniques: - Standard quality control techniques
- Pareto diagrams
- Checklists for partner selection
- Spider diagrams for training assessments
Main output: Definition of quality known to all project
members
Water-tight specification sheets
Final output of cycle: project master
plan (additional input needed for master plan: OBS/responsibility chart cf. Chapter
6)
Cf.
Chapter
6
Not discussed in this
book
Not
discussed
in this
book
4
CULTURAL IMPACT ON PLANNING
National culture determines the attitude of a project member or stakeholder towards the effectiveness of planning.
It also has an influence on the detail level and structure of the plans.
The attitude towards planning is influenced by the external environment, e.g. frequency of natural disasters, reliability of infrastructure.
The following two slides will use the cultural gap tool and apply it to the area of project planning.
5
Project managers who are rather hierarchy-
oriented tend to create a plan on their own.
More equality-oriented PMs will tend to involve
their team.
Equality Hierarchy
Project managers and members who are
afraid of risk tend to put more effort on
planning details than risk embracing project
managers and teams.
Embracing
Risk
Avoiding
Risk
Project managers and other stakeholders with
a universal background tend to create a
Master Plan which is to be applied at all sites
and to situations. Circumstantial people tend
to stick to high-level planning with flexibility.
Universal Circumstan-
tial
Project managers and other stakeholders who
are task-oriented tend to create Work
Breakdown Structures and to-do lists.
Relationship-oriented individuals tend to
spend much more time on networking with
main stakeholders than on creating a plan.
Task Relationship
CULTURAL GAP TOOL FOR PLANNING (1 )
6
Achievement Standing /
Status
Project managers and members with a
sequential approach tend to follow the
planning process, with the creation of
estimates of time, cost, and links to resource
availability. People from synchronic cultures
may put less effort in sequencing.
Sequential Synchronic
Project managers and members who are more
oriented towards theory tend to attach more
importance and put more effort into planning.
People from pragmatic cultures may tend to
focus on learning by doing and spend less
time on the creation of plans.
Theoretical Pragmatic
Project managers who are more
achievement-oriented tend to ‘follow the
textbook’ in order to obtain the given targets.
Project managers and members with a
stronger status orientation might have a
separate agenda partially contradictory to the
project goal.
CULTURAL GAP TOOL FOR PLANNING (2)
7
SCHEDULING
Scheduling comprises of the following activities:
Estimating the duration of the activities outlined in the Work Breakdown Structure.
Determining the sequence of these activities.
Optimizing the sequencing of activities to minimize the overall duration of the project.
Tools used for scheduling:
Gantt chart.
Network diagram.
The prerequisite of scheduling is the assumption that time can be measured, and duration needs to be minimized. This prerequisite is not given in all local cultures.
8
Integration
start
0 Finalize
new
strategy
10
Decide on
new
processes
5
Test pilot
10
Roll out
new
processes
30
Integration
end
0
Build new
intranet
14
Feed with
new
processes
7
Identify key
users among
personnel
5
Language
trainings
15
General
process
trainings
8
9
Estimating activity durations in an activity on arrow network diagram
Activity 1 Activity 2
Activity 1 Activity 2
Activity 1 Activity 2 10
After durations have been estimated, the logical relation between activities needs to be determined.
Determining relations between activities
Activity Name
Earliest
Start Time
Latest
Start Time
Latest
Finish Time
Earliest
Finish Time
Float or Slack
Activity Duration
1 2
34 5
11
The structure of a node of a network diagram
Integration
start
0 Finalize
new
strategy
0
0 10
1010
-
Decide on
new
process
10
10 15
155
-
Test pilot
15
15 25
2510
-
Roll out
new
process
25
25 55
5530
-
Integration
end
55
55 55
550
Build new
intranet
0
4 18
1414
4
Feed with
new
processes
15
18 25
227
3
Identify key
personnel
0
27 32
155
17
Language
trainings
15
32 47
3015
17
General
process
trainings
30
47 55
388
17 12
The complete network diagram with duration, float, and interdependencies
Factors impacting
international project
scheduling
Additional time for coordination,
communication and training
Additional time for local adaptations (of processes, products,
or services)
Additional time for team building
activities
Consideration of different public holidays and vacation time
Consideration of different calendars and auspicious days
13
Particularities of scheduling international
projects
ADDING RESOURCES TO SCHEDULING (1)
To finalize the scheduling activities, the project manager has to take quantitative and qualitative aspects of resources into account:
Quantitative aspects means that sufficient financial and human resources need to be available to carry out the tasks as depicted in the WBS.
Qualitative aspects are extremely important for scheduling international projects:
Availability of qualified staff.
Limited mobility and flexibility of staff.
Task allocation to minimize interfaces.
14
ADDING RESOURCES TO SCHEDULING (2)
Staff planning involves the following main activities:
Determine whether the team members are 100 per cent dedicated to the project.
Perform resource levelling in case of over-commitment of resources:
Re-schedule tasks.
Re-prioritize tasks.
Negotiate for additional time or resources.
Reduce the scope of the project.
15
Peak Units:
Calendar week
Calendar week
TL: Team leader
Over-allocated
resources
Allocated
resources
16
Example of resource-loaded Gantt chart
PLANNING COST
Purpose of cost planning:
Minimization of financial resources needed to realize the project’s objective.
Cost planning activities:
Estimating cost.
Putting cost into a budget.
Controlling/monitoring cost in order to revise estimations where necessary.
Types of costs:
Direct costs.
Solely linked to the project the budget is planned for.
Indirect costs.
Costs that cannot clearly be allocated to one single project, such as general administrative costs.
17
EXAMPLES OF COST COMPONENTS
Labour
Materials
Plant and equipment
Travel and transportation
Subcontract
Training
Legal support
Investment cost
Rent
Overhead and administration
Fees and taxation
Inflation
Contingency (covers oversights or unknowns as a sort of buffer) 18
Simplified Cumulative Cost Spreadsheet: Production Transfer from Europe to China
P = Plan
Total Budget € 1 million A = Actual
Cost
categories
Period to date in months
1 2 3 4 5 6 7 8 9 10
Labour
P 20,000 45,000 75,000 115,000 200,000 260,000 330,000 410,000 480,000 550,000
A
Travel /
expenses
P 16,000 32,000 64,000 96,000 130,000 170,000 200,000 240,000 300,000 380,000
A
Others
(consulting,
supplier
dev.,
prototypes,
logistics
etc.)
P 0 3,000 7,000 14,000 20,000 28,000 35,000 43,000 61,000 70,000
A
Total 36,000 80,000 146,000 225,000 350,000 458,000 565,000 693,000 841,000 1,000,000
19
Example of budget for international project
PARTICULARITIES OF INTERNATIONAL PROJECTS REGARDING COST AND TIME ESTIMATES
Fluctuations of currency rates need to be closely monitored.
Travel expenses
There is the tendency to underestimate cost for travel in international projects.
Selection of sites involved
Check infrastructure level of sites involved to avoid additional costs and delays.
Pay attention to local laws, e.g. on Health and Safety. These may incur additional costs, e.g. required translations of documents.
20
PARTICULARITIES OF INTERNATIONAL PROJECTS REGARDING QUALITY PLANNING
There needs to be a common understanding about quality among the major project stakeholders.
Never take things for granted
Are the specifications clear?
Are the specifications comprehensive?
Is the applied measurement system commonplace?
Are the specifications adapted to the markets where the product/service is used?
Pay special attention to training needs and the selection of co- operation partners.
21