OM FINAL
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
CHAPTER TWO: CAPITAL BUDGETING
Yi Zhou
Associate Professor Department of Finance
College of Business San Francisco State University
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
NET PRESENT VALUE NPV EXAMPLES NPV’S ADVANTAGES & DISADVANTAGES
NET PRESENT VALUE
Net present value (NPV ): the difference between an investment’s market value and its cost.
NPV is a measure of how much value is created or added today by undertaking an investment, and how well the project will meet the goal of increasing shareholder wealth.
The capital budgeting process can be viewed as a search for investments with positive net present values.
NPV > 0: Project is expected to add value to the firm will increase the wealth of the owners. NPV = 0: Project’s inflows are exactly sufficient to repay the invested capital.
We estimate NPV by using discounted cash flow, or DCF, valuation.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
NET PRESENT VALUE NPV EXAMPLES NPV’S ADVANTAGES & DISADVANTAGES
NPV EXAMPLE 1
Suppose we are asked to decide whether or not a new consumer product should be launched. Based on projected sales and costs, we expect that the cash flows over the five-year life of the project will be $2,000 in the first two years, $4,000 in the next two, and $5,000 in the last year. It will cost about $10,000 to begin production. We use a 10 percent discount rate to evaluate new products. What should we do here?
NPV = −10, 000 + 2, 000 1.10
+ 2, 000 1.102
+ 4, 000 1.103
+ 4, 000 1.104
+ 5, 000 1.105
(1)
= −10, 000 + 1, 818 + 1, 653 + 3, 005 + 2, 732 + 3, 105 (2) = 2, 313 (3)
This is positive; we should take on the project.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
NET PRESENT VALUE NPV EXAMPLES NPV’S ADVANTAGES & DISADVANTAGES
NPV EXAMPLE 2
Assume that Gerhardt Corporation is considering an investment of $50 million in a capital project that will return after-tax cash flows of $16 million per year for the next four years plus another $20 million in year five. The required rate of return is 10 percent.
NPV = −50 + 16
1.101 +
16 1.102
+ 16
1.103 +
16 1.104
+ 20
1.105 (4)
= −50 + 14.545 + 13.223 + 12.021 + 10.928 + 12.418 (5) = 13.136 (6)
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
NET PRESENT VALUE NPV EXAMPLES NPV’S ADVANTAGES & DISADVANTAGES
NPV EXAMPLE 3
Consider the Hoofdstad Project, which requires an investment of $1 billion initially, with subsequent cash flows of $200 million, $300 million, $400 million, and $500 million. What is the net present value of the Hoofdstad Project if the required rate of return of this project is 5%?
NPV = −1, 000 + 200
1.051 +
300 1.052
+ 400
1.053 +
500 1.054
(7)
= −1, 000 + 190.48 + 272.11 + 345.54 + 411.35 (8) = 219.46 (9)
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
NET PRESENT VALUE NPV EXAMPLES NPV’S ADVANTAGES & DISADVANTAGES
NPV’S ADVANTAGES & DISADVANTAGES
Advantages
Easy to understand (i.e., value added).
Considers the time value of money.
Considers all project cash flows.
Disadvantages
Result is a monetary amount, not a return.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
PAYBACK PERIOD
PAYBACK PERIOD
The payback period is the length of time it takes to recover the initial cash outlay of a project from future incremental cash flows. In the following example, the payback occurs in the last year, Year 4:
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
PAYBACK PERIOD
PAYBACK PERIOD: IGNORING CASH FLOWS
The payback period for both Project X and Y is three years, even through Project X provides more value through its Year 4 cash flow:
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INTERNAL RATE OF RETURN (IRR) IRR’S ADVANTAGES & DISADVANTAGES
INTERNAL RATE OF RETURN (IRR)
Consider the following Project, which requires an investment of $1 billion initially, with subsequent cash flows of $200 million, $300 million, $400 million, and $500 million. What is the IRR?
0 = −1, 000 + 200
(1 + IRR)1 +
300 (1 + IRR)2
+ 400
(1 + IRR)3 +
500 (1 + IRR)4
(10)
After several rounds of trials and errors
IRR = 12.826%
You will NOT be tested on how to calculate IRR in the final exam of FIN 351.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INTERNAL RATE OF RETURN (IRR) IRR’S ADVANTAGES & DISADVANTAGES
IRR’S ADVANTAGES & DISADVANTAGES
Solved iteratively. The problem is that we cannot solve directly for IRR, but rather must either iterate (trying different values of IRR until the NPV is zero) or use a financial calculator or spreadsheet program to solve for IRR.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS
When evaluating more than one project at a time, it is important to identify whether the projects are independent or mutually exclusive. This makes a difference when selecting the tools to evaluate the projects.
Independent projects are projects in which the acceptance of one project does not preclude the acceptance of the other(s). Example: A large conglomerate is introducing a new soup and a new peanut butter substitute.
Mutually exclusive projects are projects in which the acceptance of one project precludes the acceptance of another or others. Example: An airline requires a single jet for a new route. The airline can buy a jet from Boeing or Airbus, but cannot buy one from each.
If projects are independent, accept if NPV > 0 produces the same result as when IRR > r. If projects are mutually exclusive, accept if NPV > 0 may produce a different result than when IRR > r.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
EXAMPLE: RANKING CONFLICTS
Consider two mutually exclusive projects, Project P and Project Q: Which project is preferred and why?
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
EXAMPLE: PROJECT P AND PROJECT Q
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
NPV PROFILES: PROJECT P AND PROJECT Q
From IRR only, Project Q is preferred. However, from NPV, the choice is more complicated.
For required rates of return less than 4.89%, Project P is preferred (that is, higher NPV).
For required rates of return between 4.89% and 12.11%, Project Q is preferred.
For required rates of return above 12.11%, both projects are rejected.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
THE MULTIPLE IRR PROBLEM
If cash flows change sign more than once during the life of the project, there may be more than one rate that can force the present value of the cash flows to be equal to zero. This scenario is called the “multiple IRR problem."
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INDEPENDENT VS. MUTUALLY EXCLUSIVE PROJECTS EXAMPLE: RANKING CONFLICTS THE MULTIPLE IRR PROBLEM
EXAMPLE: THE MULTIPLE IRR PROBLEM
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
BEGINNING: INVESTMENT OUTLAY AFTER-TAX OPERATING CASH FLOW (OCF) TERMINAL YEAR MACRS SCHEDULE
CASH FLOW PROJECTIONS
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
BEGINNING: INVESTMENT OUTLAY AFTER-TAX OPERATING CASH FLOW (OCF) TERMINAL YEAR MACRS SCHEDULE
BEGINNING: INVESTMENT OUTLAY
Investment Outlay = FCInv + NWCInv − (1 − T)Sal0 − TB0
FCInv = Investment in new fixed capital
NWCInv = Investment in net working capital
Sal0(1 − T) = After-tax salvage value from sale of old fixed capital if applicable.
T = Tax rate
B0 = Book value of old fixed capital if applicable.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
BEGINNING: INVESTMENT OUTLAY AFTER-TAX OPERATING CASH FLOW (OCF) TERMINAL YEAR MACRS SCHEDULE
AFTER-TAX OPERATING CASH FLOW (OCF)
After-tax Operating Cash Flow =
OCF = (S − C − D)(1 − T) + D = (S − C)(1 − T) + TD.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
BEGINNING: INVESTMENT OUTLAY AFTER-TAX OPERATING CASH FLOW (OCF) TERMINAL YEAR MACRS SCHEDULE
TERMINAL YEAR
Terminal Year OCF = OCFT + SalT (1 − T) + NWCInv + TBT
SalT (1 − T) = After-tax salvage value.
NWCInv = Investment in working capital.
BT = Book value of fixed capital on termination date if applicable.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
BEGINNING: INVESTMENT OUTLAY AFTER-TAX OPERATING CASH FLOW (OCF) TERMINAL YEAR MACRS SCHEDULE
MACRS SCHEDULE
Will be Provided at All Tests.
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
EXAMPLE: CASH FLOW ANALYSIS
EXAMPLE: CASH FLOW ANALYSIS
Suppose a company has the opportunity to bring out a new product, the Vitamin-Burger. The
initial cost of the assets is $95 million, and the company’s working capital would increase by
$13 million during the life of the new product. The new product is estimated to have a useful
life of four years, at which time the assets would be sold for $16 million. Management expects
company sales to increase by $140 million the first year, $175 million the second year, $155
million the third year, and then trailing to $65 million by the fourth year because competitors
have fully launched competitive products. Operating expenses are expected to be 70% of sales,
and depreciation is based on an asset life of three years under MACRS (modified accelerated
cost recovery system). Year 1: 33.33%, Year 2: 44.45%, Year 3: 14.81% and Year 4: 7.41%.If
the required rate of return on the Vitamin-Burger project is 8% and the company’s tax rate is
30%, should the company invest in this new product?
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
EXAMPLE: CASH FLOW ANALYSIS
EXAMPLE: CASH FLOW ANALYSIS
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INPUT VARIABLES AND NPV FOR SCENARIO ANALYSIS PESSIMISTIC SCENARIO MOST LIKELY SCENARIO OPTIMISTIC SCENARIO
INPUT VARIABLES AND NPV FOR SCENARIO ANALYSIS
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INPUT VARIABLES AND NPV FOR SCENARIO ANALYSIS PESSIMISTIC SCENARIO MOST LIKELY SCENARIO OPTIMISTIC SCENARIO
PESSIMISTIC SCENARIO
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INPUT VARIABLES AND NPV FOR SCENARIO ANALYSIS PESSIMISTIC SCENARIO MOST LIKELY SCENARIO OPTIMISTIC SCENARIO
MOST LIKELY SCENARIO
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
NET PRESENT VALUE PAYBACK PERIOD
INTERNAL RATE OF RETURN (IRR) RANKING CONFLICTS: NPV VS. IRR
CASH FLOW PROJECTIONS EXAMPLE: CASH FLOW ANALYSIS
SCENARIO ANALYSIS
INPUT VARIABLES AND NPV FOR SCENARIO ANALYSIS PESSIMISTIC SCENARIO MOST LIKELY SCENARIO OPTIMISTIC SCENARIO
OPTIMISTIC SCENARIO
YI ZHOU CHAPTER TWO: CAPITAL BUDGETING
- Net Present Value
- Net Present Value
- NPV Examples
- NPV's Advantages & Disadvantages
- Payback Period
- Payback Period
- Internal rate of return (IRR)
- Internal rate of return (IRR)
- IRR's Advantages & Disadvantages
- Ranking conflicts: NPV vs. IRR
- Independent vs. mutually Exclusive projects
- Example: Ranking conflicts
- The multiple IRR problem
- Cash flow projections
- Beginning: Investment Outlay
- After-tax Operating Cash Flow (OCF)
- Terminal year
- MACRS Schedule
- Example: Cash Flow analysis
- Example: Cash Flow analysis
- Scenario Analysis
- Input Variables and NPV for Scenario Analysis
- Pessimistic Scenario
- Most Likely Scenario
- Optimistic Scenario