Discussion and responses (ITP)

profileteja_injjam
Chapter15-FinishingtheProjectandRealizingtheBenefits.pptx

CONTEMPORARY PROJECT MANAGEMENT, 4E

Timothy J. Kloppenborg

Vittal Anantatmula

Kathryn N. Wells

‹#›

Finishing the Project & Realizing the Benefits

Chapter 15

‹#›

Chapter 15 Core Objectives:

Describe how to determine when a project should be terminated early & the process for terminating a project in normal completion time.

Describe the importance of the project closing activities & how to perform them.

Create & present a transition plan for the project, including a plan for ongoing support and sharing lessons learned.

Capture and share project lessons learned.

Chapter 15 Technical Objectives:

Close your projects administratively using MS Project 2016

Chapter 15 Behavioral Objectives:

Secure customer feedback & acceptance of the project.

Assist senior management in managing talent & managing resources for upcoming projects.

Celebrating Project Success Trinmar

It was only later that I was sheepishly advised by one of my fellow consultants that he had offered to have our company sponsor the celebration, and did not have the chance to tell me in advance. But the true impact of the celebration—reflected in the sincere joy and pride of the project team members as they received the sincere thanks of their CEO—had already proven the value of the event.

Bruce Miller, PMP, managing partner,

Xavier Leadership Center, Xavier University

6

Finishing the Project & Realizing the Benefits

A project moves into the closing stage when its customers accept the project deliverables

A project can close as planned or be terminated early

Complete closing activities

Validate Scope

Formal acceptance of project deliverables

Buyer provides the seller with formal written acceptance

Transition from executing stage to closing stage

Use a project closeout checklist to itemize project activities and/or deliverables

Validate scope – formally accepting the completed project deliverables

Terminate Projects Early

Mutual Agreements

What deliverables or partial deliverables go to the buyer

What compensation goes to the seller

Resolve outstanding issues with negotiated settlement

Terminations for Default

Problems with the project’s cost, schedule, or performance

Lost confidence in the contractor

Terminations for Convenience of Buyer

Buyer faces unexpected difficulties or changing priorities

Customer’s needs change

Often requires a payment to the contractor

Heading Off Early Termination

Find other stakeholders who can provide funds

Look internally to find ways of continuing with the project

PMs make recommendations for early termination if they feel it is warranted

Communicate quickly and honestly

Close Project

Write Transition Plan

Knowledge Management

Create the Closeout Report

Finalize all activities needed to finish the project

Write Transition Plan

Charter/instruction manual for how to use the project deliverables

Provide appropriate documentation to users

Ensure quality problems are avoided

Ensure project deliverables transition into operational role

Ensure maintenance, upgrades, & training take place

Breakout session!

Write a short transition plan to give to your customers, detailing any information they will need to successfully use/implement the deliverables created by your project.

Knowledge Management

Should occur throughout the project life

Most apparent as a project comes to a close

Capture lessons learned

Disseminate and use lessons learned in order to help your organization improve

Pertains to 4th area of the balanced scorecard—growth & innovation

Solicit Customer Feedback

Capture Lessons Learned

At milestones and at the end of project

Identify major project issues

One issue at a time to determine what went wrong & how it might be avoided in future projects.

List significant successes and discuss what caused each

What worked well?

Where might a different method yield better results?

Lessons Learned Example Project Closing Document

See many lessons learned examples in Exhibit 15.4 on p.507 in textbook

Disseminate and Use Lessons Learned

Key to knowledge management!

Establish method for documenting & sharing lessons learned

Decide how to store lessons for easy access

Code each lesson by type of project, stage in project life cycle, or issue it concerns

Create the Closeout Report

This formal report includes summary of:

Project’s original justification

Ultimate status

Lessons learned

Did the project accomplish what it was originally approved to do?

Closeout Report Template

Post- Project Activities

Reassign Workers

Celebrate Success & Reward Participants

Provide Ongoing Support

Ensure Project Benefits are Realized

Reassign Workers

Update personnel records

Make honest recommendations

Help team members secure next assignments

“Helping good workers secure follow-on work is one of the most important things a project manager must do.”

Celebrate Success and Reward Participants

Challenge

Energize

Limit

Exert

Believe

Recognize

Acknowledge

Transition

Ease Stress

“the project is over; we will limit any additional work on this project.”

Provide Ongoing Support

Ultimate project goal is to provide capable customers, who will…

Use the deliverables you provided

Recommend you for future work

Often requires support after project is complete

Ensure Project Benefits are Realized

How well are customers able to use the deliverables?

Consider use by direct customers and other stakeholders

May require following up with customers weeks or months after project’s end

Using MS Project for Project Closure

Creating Project Progress Reports

Archiving project work

Using MS Project for Project Closure

Creating Project Progress Reports

Creating a customizable canned report

Sharing Report—can be printed or saved as PDF

Export report to MS Excel

See detailed instructions in

textbook, pp.511-512

Using MS Project for Project Closure

Archiving project work

Complete schedule to maximize future usefulness

Applying performance data

Applying approved changes

Ensuring all activities are complete

Archive schedule for use as template or “starter file”

Capture & publish lessons learned

Detailed instructions on textbook p. 514

Success celebrated

Lessons learned recorded

Summary

Projects may be terminated early

Mutual agreement

Default

Convenience of customer

Whether project finishes successfully as planned or not, a variety of closeout procedures is required

Money paid & accounted for

Documentation completed & distributed

Workers reassigned & rewarded

The Power of Lessons Learned

PM IN ACTION

“Successful people learn from Their mistakes AND the mistakes of OTHERS.” —Sir John Templeton

PMBOK Exams

Make sure you are studying from most current (6th) PMBOK edition, since there have been substantial changes made within the Closing Process Group

All closing activities—whether contractual, administrative, or other—now fall under the Close Project or Phase process.

Remember the importance of capturing, storing, & disseminating lessons learned (throughout the project but especially at project’s end). This needs to take place whether or not the project reaches a successful conclusion.

Since the PM often has limited authority, the sponsor should be involved in Close Project.

Casa de Paz Development Project

What would you include in a transition plan?

How would you capture lessons learned?

Who would you share those lesson with and how?