Compute the takt time for a system where the total time per shift is 430 minutes, there is one shift, and workers are given 3 12-minute breaks and 30 minutes for lunch. Daily demand is 348 units. (Round your answer to 2 decimal places.)

Takt time minutes per cycle

What cycle time would match capacity and demand if demand is 161 units a day, there are 2 shift(s) of 446 minutes each, and workers are given three 35 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)