International project management
LEARNING IN AND LEARNING FROM INTERNATIONAL PROJECTS
Chapter 11
INTERNATIONAL PROJECTS AND ORGANIZATIONAL LEARNING (1)
Organizational learning:
Individual learning is a prerequisite for organizational learning. Another prerequisite is effective communication between the individual learners embedded in the organization’s culture and organizational structure.
Due to their time limitations, resource constraints, great complexity, diversity, and risk propensity, international projects are a rich source of organizational learning.
Purpose of learning from projects:
Reduction of project risk.
Development of project competencies.
Creation of sustainable innovativeness and competitive advantage.
2
KNOWLEDGE AND KNOWLEDGE MANAGEMENT
Knowledge:
We have to distinguish between data, information, and knowledge.
By patterning them in a certain way, unstructured, isolated, context-independent data are transformed to information.
Knowledge is created if cognitive behavioural patterns or heuristics are applied to this information.
Explicit knowledge:
Can be expressed in words or figures.
It is documented and easily accessible.
Tacit knowledge:
Resides in an individual’s actions and experience, as well as in his values and attitudes.
Knowledge Management is about sharing and leveraging knowledge within and outside of the organization.
To enhance organizational learning, knowledge management needs to be applied in and to international projects.
3
INTERNATIONAL PROJECTS AND ORGANIZATIONAL LEARNING (2)
Categories of knowledge derived from international projects:
Technical knowledge regarding the product with its components of the service, including its underlying technologies.
Procedural knowledge regarding manufacturing a product or delivering a service, including the application of a certain project management methodology.
Organizational knowledge regarding communication, leadership, and co-operation.
4
‘Strong‘
knowledge,
including true
beliefs backed
up by valid
justifications,
easy to make
explicit and
transfer
throughout the
organization.
‘Weak‘ knowledge,
tacit, sticky in local
projects, difficult to
globalize or
transfer.
Discerned
elements (e.g.
number of warranty
claims, test data)
Data that is
processed and
patterned
Actionable
information
transformed into
knowledge
Knowledge
embedded into
indiv. and org.
processes adding
value to the
organization
Learning 1. Data 2. Information
4. Individual and
organizational
processes
3. Knowledge
Context External
environment
Strategy (implemented
via international
projects)
Organizational IT
infrastructure and
systems
Organizational
culture
National culture
of workforce
Educational
background of
employees
Common corporate language
5
Knowledge management cycle in international projects
PROJECT LEARNING AND CULTURAL CONTEXT
As shown on the previous slide, learning in and from international projects is embedded in context.
Part of this context is national or regional culture.
Tacit knowledge reflects culture and needs to be interpreted with a cultural lens on.
In the Arab and Chinese world, individuals are socialized in networks (wasta / guanxi) with their own rules regarding knowledge creating and sharing.
Intercultural knowledge is not only needed to interpret tacit knowledge, but also to turn tacit knowledge into explicit knowledge.
The following slides explore the details how culture impacts learning in and from international projects.
6
People from individualistic cultures may tend to
regard knowledge as their personal possession they
can or cannot share with anybody else. People from
group-oriented cultures may tend to consider
knowledge as something belonging to and residing
in the group.
Individual Group
Individuals from universal cultures may tend to strive
for universally applicable knowledge and apply one
fits all solutions globally. Individuals from
circumstantial cultures may tend to adapt knowledge
to its specific context.
Universal Circumstan-
tial
Individuals from task-oriented cultures often are low-
context communicators. They tend to codify
knowledge using ICT-supported knowledge mgmt
tools. Individuals from relationship-oriented cultures
may focus on tacit knowledge residing in the people
of their network and prefer high-context information
modes.
Task Relationship
Individuals from rather theory-oriented cultures will
tend to learn from abstract knowledge and focus on
cause and effect relations. Individuals from pragmatic
cultures will tend to prefer cases and easily
transferable knowledge focusing on useful results.
Theoretical Pragmatic
7
Cultural impact on learning
• Avoidance of loss of face
• Impact of collectivism
• Impact of multi- disciplinarity
• Discontinuities
• Fragmentation
• Lack of time
• Lack of transparency
• Focus on evaluation at the end
• Marginality of sender
• Stereotypes of and against the sender
• Linguistic ability of the sender and the receiver
• Lack of support by organizational culture
• Not Invented Here Syndrome
• Lack of incentives and motivation
• Lack of discipline
• Lack of skills
Issues regarding learning in and from
international projects related to…
… cultural
diversity
… the nature of
a project
… communica-
tion
… the overall
organization
8
Impediments to project learning
Great diversity reflected in multi-culturalism, differences in language, organizational culture,
functional culture, or educational background, complicates learning in and from international
projects.
METHODS OF LEARNING IN AND FROM INTERNATIONAL PROJECTS
All approaches aiming at capturing knowledge and experience derived from international projects need to:
Link the knowledge with the context in which it was created.
Span geographical and organizational boundaries.
Human-centred methods:
Knowledge networks / Communities of practice.
New roles dedicated to knowledge management.
Mentor relationships.
Process-based methods:
Project audit.
Structured project walkthrough.
Content-based approaches:
Micro article
Learning history.
9
10
Name of Method Description Main Advantages Main Disadvantages
Knowledge
networks /
community of
practice (IPMs)
Individuals with the role of
international project managers
exchange experience via email
or intranet and meet to maintain
their networks personally at
regular intervals
Tacit knowledge can be shared on the
face-to-face meetings but also easily
via phone, email or intranet crossing
organizational, cultural, and geographic
boundaries
PMs of international projects
may be too heterogeneous
to create common reference
frame
New roles
dedicated to
knowledge
management
New roles such as regional
engineering managers who
collect learning from projects
and other relevant knowledge
and disseminate it in their
networks around the globe
External and internal knowledge is
collected and disseminated; due to
personal networks, tacit knowledge can
be shared across organizational,
cultural and geographic boundaries
Effectiveness of the new
roles dependent on
qualification (including
cultural intelligence) of
individuals assigned to the
new roles. Difficult to span
functional boundaries
Mentor
relationships
Experienced international
project manager is shadowed by
to-be project manager
Good tool to share tacit knowledge,
also across organizational, cultural, and
geographic boundaries
Time consuming,
effectiveness depends on
the performance of mentor
and relation between the
two
Project audit Project-external auditors sit
down with PM to check project
documentation for compliance
and deviations from plan. Most
adequate for learning if based
on issue log
Neutral view on evaluation; adequate
for fostering project management
methodology across organizational,
cultural and geographic boundaries.
Tends to focus on
compliance issues at the
expense of organizational
learning
Overview of methods of project learning (1)
11
Name of Method Description Main Advantages Main Disadvantages
Structured project
walkthrough
Method focusing on project
team, face-to-face. Project team
controls the evaluation process
determining its own evaluators
and rules
Atmosphere of trust leads to honest
reflection; crosses organizational,
cultural and geographic boundaries;
effectiveness of sharing tacit knowledge
depends on documentation of
walkthrough process
Lack of intercultural skills
may interfere with process;
cost intensive to gather
international project team at
one site
Micro article Short articles of maximum one
page comprising key experience
or lesson learnt from a project
highly visualized, written in an
entertaining way, and
disseminated digitally
Sharing of tacit knowledge possible due
to inclusion of context. Can be
disseminated also as video clips,
cartoons or other visualized forms
travelling well across organizational,
cultural and geographic boundaries
Takes time and resources to
create articles. Strict
anonymity required in case
of negative lessons learnt
due to potential loss of face
for certain cultures
Learning history Documents of 20 – 100 pages
narrating the history of the
project chronologically quoting
directly project participants
anonymously. Distributed as
hard copies at a special
workshop
Through the direct input of project
participants very authentic and through
comments of editors very context rich.
Good to turn tacit knowledge into
explicit knowledge. If workshops are
carried out in different locations,
suitable for the whole organization
Takes a lot of time and
resources. Only meaningful
for strategic and big projects
Overview of methods of project learning (2)
THE PHASE OF PROJECT COMPLETION
The process-oriented project learning methods are especially linked to the project completion or project termination phase.
Evaluation-based learning is one of the main tasks of this phase. The project manager or project auditor evaluates the actual project results versus plan regarding:
Project schedule.
Accuracy of the resource estimates.
Impact of resources availability of shortages on the project.
Typically, evaluation-based learning focuses solely on the hard facts as mentioned above. The soft factors are frequently neglected.
Another important task is the handover of the project or service to the customer and to ensure customer satisfaction with the deliverables.
12
• Project budgets and actuals
• Project schedule with estimates
and actuals
• Customer’s goal
• Technical specifications
• Change requests
• Issue log
Input
• Finalized project documentation
including project acceptance
document signed by internal or
external customer
• Explicit and tacit technical,
procedural and organizational
knowledge packaged to make it as
easy to re-use as possible in form
of:
•Analysed project performance
statistics
•Stories/Analogies/Cases/Project
histories
•Re-using project team as is or
experience of project team via
communities of practice
OutputCompletio
n Phase
Controls:
Organization‘s
project mgmt
standards/
procedures
Constraints:
strategic, financial,
time, legal, cultural,
environmental,
ethical
Mechanisms: Debriefing workshop
Project audit
Project walkthrough
etc.
13
Main inputs and outputs of the project completion phase
Integrating project learning
into project management methodology
Establishing knowledge enablers:
Moving towards the ideal of a learning
organization
• Trust
• Motivation
• Absorption
capacity 14
Fostering project learning in an international context