Research Paper - Construction Law

profileeaenandtrey2020
Ch18.pdf

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

© 2015 Cengage Learning Engineering. All Rights Reserved. 1

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Learning Objectives

 Understanding the underlying risk allocation and rationale for the system of change orders and change claims in construction contracts.

 Highlighting the differences between change orders and modifications.

 Identifying potential theories of recovery for contractors for completed work on changes that are not requested through the change order process.

© 2015 Cengage Learning Engineering. All Rights Reserved. 2

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Changes: Differing Perspectives

 Owner’s perspective:

 Designs and methods may become inadequate over time.

 Changes present risks of eventual delays or cost overruns.

 Loose changes clause risks turning a fixed price contract into an open-ended costs contract.

 Owners want some flexibility for changes, but not too much.

© 2015 Cengage Learning Engineering. All Rights Reserved. 3

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Changes: Differing Perspectives

 Contractor’s perspective:

 Contractors are concerned about receiving adequate compensation and time allowances for changes that require additional work.

 Changes may force contractors to pull resources from other projects or overhead to complete the change.

 Contractors may feel that a change has occurred even though not formally requested through the changes process, and pursue a changes claim against the owner.

© 2015 Cengage Learning Engineering. All Rights Reserved. 4

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Common Law Approach to Changes

 Default rules and contract interpretation in absence of a contract provision on changes.

 Case Study: Chong v. Reebaa Construction Company.

 Inherent difficulties of oral contracts.

 Interpreting uncertainty in the terms of the contract, particularly as changes occur over time.

© 2015 Cengage Learning Engineering. All Rights Reserved. 5

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

The Changes Clause  Under a contract provision, the owner may

unilaterally direct changes to be made without obtaining the contractor’s consent to perform the work.

 Changes that add work.

 Changes that delete work.

 Changes that substitute one item of work for another item of work.

 Different from a modification, where both parties mutually agree to a change.

 Role of change order formality requirements.

© 2015 Cengage Learning Engineering. All Rights Reserved. 6

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Changes under AIA Documents

 AIA documents use different terminology which can be misleading.

 Three primary AIA mechanisms for making changes:

 Change order (CO), similar to a typical contract modification, requiring both parties to agree on change.

 Construction change directive (CCD), similar to a typical change order, unilateral.

 Order for minor change in the work.

© 2015 Cengage Learning Engineering. All Rights Reserved. 7

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Changes: Shifts in Bargaining Power

 Initially, owner has superior bargaining power during bidding, allowing it to push for favorable contract terms.

 Contractor then later has superior bargaining power during performance as it could refuse to complete changes unless receiving agreed allowances.

 Changes provisions in the contract favors the owner and rebalances bargaining power by forcing the contractor to make some changes.

© 2015 Cengage Learning Engineering. All Rights Reserved. 8

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Changes  Case Study: Watson Lumber Company v.

Guennewig.

 Facts of the case?

 What must the contractor prove in order to recover for “extras”?

 Waiver of formal change requirements.

 Abusing the changes system.

 Administrative costs of managing changes.

© 2015 Cengage Learning Engineering. All Rights Reserved. 9

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Components of the Changes Process

 The changes process involves:

 Exercise of a power to order a change or a direction the contractor contends is a change in the work.

 Methods for the contract or the parties to price the change and its effect on time requirements.

 A residuary provision that controls the price in the event the parties do not agree.

 Changes process is necessary for design flexibility and cost control.

© 2015 Cengage Learning Engineering. All Rights Reserved. 10

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Limitation on Power to Order Changes

 Changes system has potential for abuses.

 In the absence of an agreed-upon price, whether the contractor must perform depends on the magnitude of the change in comparison to the contract as a whole.

 Minor changes must be performed or risk claims for breach of contract.

 AIA documents limit scope for acceleration changes.

 Special considerations for public contracts.

© 2015 Cengage Learning Engineering. All Rights Reserved. 11

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Authority to Order Change

 Absent contract provisions, default rules from agency law apply as to who may order changes (on behalf of owner).

 Express contract authorization needed to create authority for design professional, construction manger or project representative to order changes on behalf of owner.

 Work in emergency situations.

© 2015 Cengage Learning Engineering. All Rights Reserved. 12

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Misrepresentation of Authority

 Situation: contractor performs additional work at direction of design professional who lacks actual authority from owner to order changes.

 Unlikely that contractors can reasonably rely on apparent authority of design professional.

 Concept of ratification.

© 2015 Cengage Learning Engineering. All Rights Reserved. 13

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Pricing Changed Work

 Preferred to price work by reference to or analogy to unit prices already specified in the contract.

 Cost plus percentage of cost for overhead, etc.

 “Equitable adjustments” and “reasonable expenditures.”

 Administrative burden of overseeing changes costs.

© 2015 Cengage Learning Engineering. All Rights Reserved. 14

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Deductive Change (Deletion)

 Special issues:

 Standard of within the scope of the work doesn’t apply for deletions.

 Effects of deduction on contracts with subcontractors.

 Breach of contract if deduct work from one contract to give that work to another contractor.

© 2015 Cengage Learning Engineering. All Rights Reserved. 15

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Waiver: Excusing Formal Requirements

 Situation: contractor completes change work according to order that does not meet formal requirements, then owner refuses to pay, asserting no valid change order.

 Contractor claims owner waived formal requirements. Issues:

 Is the requirement waivable?

 Who has the authority to waive the requirement?

 Did the facts claimed to create waiver lead the contractor to reasonably believe that the requirements have been eliminated?

© 2015 Cengage Learning Engineering. All Rights Reserved. 16

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Waiver: Excusing Formal Requirements

 Only parties with authority to order changes can waive formal requirements.

 Waiver can be based on conduct, including payment for changed work done while not meeting formality requirements.

 Contractors are well advised to follow formality requirements rather than rely on later court arguments on waiver.

© 2015 Cengage Learning Engineering. All Rights Reserved. 17

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Contractor’s Changes Claims  Cardinal changes:

 Cardinal change doctrine provides a theory of recovery for contractors for changes that go beyond the scope of the work.

 One shot scope changes and aggregate scope changes claims.

 Constructive changes:

 Actual change in performance from contract requirements and some order or directive from owner, even if not meeting formality requirements.

 Claim by contractor for equitable adjustment.

© 2015 Cengage Learning Engineering. All Rights Reserved. 18

Construction Law for Design Professionals, Construction Managers, and Contractors Sweet and Schneier

Summary

 Changes are an important and common part of many projects, to provide design flexibility and control costs.

 However, changes can have significant effects on the risks and obligations of both parties, and in particular the contractor.

 Beyond the change order process, cardinal and constructive change claims help to protect the contractor and provide a theory of recovery for work performed on changes.

© 2015 Cengage Learning Engineering. All Rights Reserved. 19