AGGREGATE PLANNING

profilezara__993
Ch13Ex5_1_.xlsx

Sheet1

Trans_agg

CHAPTER 13: Example 5
Aggregate (Production) Planning as a Transportation Model
Cost per unit
Regular time 40.0
Overtime cost 50.0
Subcontract cost 70.0
Holding cost 2.0
Data
COSTS March April May Excess Capacity Capacity
Beginning inventory 0.0 2.0 4.0 6.0 100.0
March reg time 40.0 42.0 44.0 0.0 700.0
March overtime 50.0 52.0 54.0 0.0 50.0
March subcontracting 70.0 72.0 74.0 0.0 150.0
April reg time 999999.0 40.0 42.0 0.0 700.0
April overtime 999999.0 50.0 52.0 0.0 50.0
April subcontracting 999999.0 70.0 72.0 0.0 150.0
May reg time 999999.0 999999.0 40.0 0.0 700.0
May overtime 999999.0 999999.0 50.0 0.0 50.0
May subcontracting 999999.0 999999.0 70.0 0.0 130.0
Demand 800.0 1000.0 750.0 230.0 2550 \ 2780
Production Quantities
March April May Excess Capacity Row Total
Beginning inventory 0 0 0 0 0
March reg time 0 0 0 0 0
March overtime 0 0 0 0 0
March subcontracting 0 0 0 0 0
April reg time 0 0 0 0 0
April overtime 0 0 0 0 0
April subcontracting 0 0 0 0 0
May reg time 0 0 0 0 0
May overtime 0 0 0 0 0
May subcontracting 0 0 0 0 0
Column Total 0 0 0 0 0
Total Cost 0.0

Enter production costs at top. The transportation table will be automatically filled in. Enter capacities and demands in the table. Go to DATA Tab on the ribbon, click on Solver in Data Analysis Group then click SOLVE. For problems, see Help, Solver.