CE 4460 PROJECT MANAGEMENT

profilejim hdr 23
CE44605560PROJECTIA.docx

CE 4460 5560 PROJECT MANAGEMENT NAME:_______________

PROJECT IA FALL 2017

1. YOUR ENGINEERING FIRM HAS BEEN CONTRACTED TO DESIGN A RESIDENTIAL STRUCTURE. THE PLAN AND PROFILE ARE GIVEN IN FIGURES 1 AND 2. PREPARE A COST AND SCHEDULE ESTIMATE FOR PREFORMING THE WORK. USE THE FOLLOWING SHEETS FOR YOU ESTIMATE. ANNOTATED MEANS ESTIMATING HANDBOOK COST AND DURATION SHEETS ARE PROVIDED IN A SEPARATE MOODLE DOCUMENT.

A. YOUR HAVE IDENTIFIED THE FOLLOWING ACTIVITIES TO BE

CARRIED OUT ON THIS PROJECT:

· PLACE 6 IN. DIAMETER - PLACE/COMPACT GRANULAR

PVC DRAIN PIPE SOIL BELOW FLOOR SLAB

· SURVEY EXCAVATION - EXCAVATE ALL SOIL TO

PERIMETER BASEMENT LEVEL

· POUR 12 IN. THICK CONCRETE - STRIP/STOCKPILE TOPSOIL

WALL

· REMOVE VEGETATION: - CAST REINFORCED

CLEAR AND GRUB CONCRETE FOOTING

- CAST CONCRETE FLOOR - PLACE GRANULAR SOIL

SLAB AROUND PVC PIPE

- BACKFILL AROUND - REPLACE TOPSOIL

BASEMENT

AC - ACRES: 43,560 FT2/ACRE

CY - CUBIC YARDS: 27 FT3/CY

BCY - CUBIC YARDS: 27 FT3/CY

LF - LINEAR FEET

CE 4460 5560 PROJECT MANAGEMENT -2-

PROJECT IA FALL 2017 NAME:_______________

1. PREPARE THE ACTIVITY SEQUENCE FOR THE STRUCTURE: FILL IN

REMAINING BLANK SPACES.

____ ____________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

CE 4460 5560 PROJECT MANAGEMENT -3-

PROJECT IA FALL 2017 NAME:___________

2 PREPARE A QUANTITY TAKE OFF FOR THE FOLLOWING ACTIVITIES –

FILL IN BLANKS IN THE FOLLOWING TABLE.

ITEM ACTIVITY UNIT ESTIMATED QUANTITY

1

2

3

4

5

6

7

8

9

10

11

12

CE 4460 5560 PROJECT MANAGEMENT -4-

PROJECT IA FALL 2017 NAME:___________

C:\Users\mahajame\Pictures\img183.jpg

CE 4460 5560 PROJECT MANAGEMENT -5-

PROJECT IA FALL 2017 NAME:___________

C:\Users\mahajame\Pictures\img184.jpg