CE 4460 PROJECT MANAGEMENT
CE 4460 5560 PROJECT MANAGEMENT NAME:_______________
PROJECT IA FALL 2017
1. YOUR ENGINEERING FIRM HAS BEEN CONTRACTED TO DESIGN A RESIDENTIAL STRUCTURE. THE PLAN AND PROFILE ARE GIVEN IN FIGURES 1 AND 2. PREPARE A COST AND SCHEDULE ESTIMATE FOR PREFORMING THE WORK. USE THE FOLLOWING SHEETS FOR YOU ESTIMATE. ANNOTATED MEANS ESTIMATING HANDBOOK COST AND DURATION SHEETS ARE PROVIDED IN A SEPARATE MOODLE DOCUMENT.
A. YOUR HAVE IDENTIFIED THE FOLLOWING ACTIVITIES TO BE
CARRIED OUT ON THIS PROJECT:
· PLACE 6 IN. DIAMETER - PLACE/COMPACT GRANULAR
PVC DRAIN PIPE SOIL BELOW FLOOR SLAB
· SURVEY EXCAVATION - EXCAVATE ALL SOIL TO
PERIMETER BASEMENT LEVEL
· POUR 12 IN. THICK CONCRETE - STRIP/STOCKPILE TOPSOIL
WALL
· REMOVE VEGETATION: - CAST REINFORCED
CLEAR AND GRUB CONCRETE FOOTING
- CAST CONCRETE FLOOR - PLACE GRANULAR SOIL
SLAB AROUND PVC PIPE
- BACKFILL AROUND - REPLACE TOPSOIL
BASEMENT
AC - ACRES: 43,560 FT2/ACRE
CY - CUBIC YARDS: 27 FT3/CY
BCY - CUBIC YARDS: 27 FT3/CY
LF - LINEAR FEET
CE 4460 5560 PROJECT MANAGEMENT -2-
PROJECT IA FALL 2017 NAME:_______________
1. PREPARE THE ACTIVITY SEQUENCE FOR THE STRUCTURE: FILL IN
REMAINING BLANK SPACES.
____ ____________________________________________________________
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
CE 4460 5560 PROJECT MANAGEMENT -3-
PROJECT IA FALL 2017 NAME:___________
2 PREPARE A QUANTITY TAKE OFF FOR THE FOLLOWING ACTIVITIES –
FILL IN BLANKS IN THE FOLLOWING TABLE.
ITEM ACTIVITY UNIT ESTIMATED QUANTITY
1
2
3
4
5
6
7
8
9
10
11
12
CE 4460 5560 PROJECT MANAGEMENT -4-
PROJECT IA FALL 2017 NAME:___________
CE 4460 5560 PROJECT MANAGEMENT -5-
PROJECT IA FALL 2017 NAME:___________