PROJECT MANAGEMENT

profilejim hdr 23
CE44605560PROJECTIA-3.docx

CE 4460 5560 PROJECT MANAGEMENT NAME:___KEY________

PROJECT IA FALL 2017 ID:___________________

DUE: 6:30 PM ON 5 OCTOBER 2017

1. YOUR ENGINEERING FIRM HAS BEEN CONTRACTED TO DESIGN A RESIDENTIAL STRUCTURE. THE PLAN AND PROFILE ARE GIVEN IN FIGURES 1 AND 2. PREPARE A COST AND SCHEDULE ESTIMATE FOR PREFORMING THE WORK. USE THE FOLLOWING SHEETS FOR YOU ESTIMATE. ANNOTATED MEANS ESTIMATING HANDBOOK COST AND DURATION SHEETS ARE PROVIDED IN A SEPARATE MOODLE DOCUMENT.

A. YOUR HAVE IDENTIFIED THE FOLLOWING ACTIVITIES TO BE

CARRIED OUT ON THIS PROJECT:

· PLACE 6 IN. DIAMETER - PLACE/COMPACT GRANULAR

PVC DRAIN PIPE SOIL BELOW FLOOR SLAB

· SURVEY EXCAVATION - EXCAVATE ALL SOIL TO

PERIMETER BASEMENT LEVEL

· POUR 12 IN. THICK CONCRETE - STRIP/STOCKPILE TOPSOIL

WALL

· REMOVE VEGETATION: - CAST REINFORCED

CLEAR AND GRUB CONCRETE FOOTING

- CAST CONCRETE FLOOR - PLACE GRANULAR SOIL

SLAB AROUND PVC PIPE

- BACKFILL AROUND - REPLACE TOPSOIL

BASEMENT

AC - ACRES: 43,560 FT2/ACRE

CY - CUBIC YARDS: 27 FT3/CY

BCY - CUBIC YARDS: 27 FT3/CY

LF - LINEAR FEET

CE 4460 5560 PROJECT MANAGEMENT -2-

PROJECT IA FALL 2017 NAME:__KEY_________

DUE: 6:30 PM ON 5 OCT 2017 ID:__________________

1. PREPARE THE ACTIVITY SEQUENCE FOR THE STRUCTURE: FILL IN

REMAINING BLANK SPACES.

____ ___SURVEY EXCAVATION PERIMETER________________________

_______ REMOVE VEGETATION: CLEAR AND GRUB _______

_______ STRIP/STOCKPILE TOPSOIL _______________

_______ EXCAVATE ALL SOIL TO BASEMENT LEVEL________________

_______ CAST REINFORCED CONCRETE FOOTING __________________

_______ POUR 12-IN. THICK CONCRETE WALLS _____________________

_______ PLACE/COMPACT GRANULAR SOIL BELOW FLOOR SLAB____

_______ CAST CONCRETE FLOOR SLAB ____________________________

_______ PLACE 6-IN. DIAMETER PVC DRAIN PIPE __________

_______ PLACE GRANULAR SOIL AROUND PVC PIPE _______________

_______ BACKFILL AROUND BASEMENT____________________________

_______ REPLACE TOPSOIL ___________________________

CE 4460 5560 PROJECT MANAGEMENT -3-

PROJECT IA FALL 2017 NAME:___________

DUE: 6:30 PM ON 5 OCT 2017 ID:_______________

2 PREPARE A QUANTITY TAKE OFF FOR THE FOLLOWING ACTIVITIES –

FILL IN BLANKS IN THE FOLLOWING TABLE.

ITEM ACTIVITY UNIT ESTIMATED QUANTITY

1 SURVEY SQ FT 12,096

2 CLEAR/GRUB SQ FT 12,096

3 TOPSOIL CU FT 11,869

4 EXCAVATE CU FT 69,123

5 FOOTING CU FT 1,140

6 WALL CU FT 2,660

7 GRANULAR CU FT 3,121

8 FLOOR SLAB CU FT 3,286

9 PVC DRAIN LN FT 396

10 PIPE GRANULAR CU FT 902

11 BACKFILL CU FT 18,480

12 TOPSOIL CU FT 4,878

BY SIGNING THIS PAGE, I HAVE NOT GIVEN OR RECEIVED HELP FROM THE

OTHER STUDENTS IN THIS CLASS.

NAME:__________________ SIGNATURE:__________________

CE 4460 5560 PROJECT MANAGEMENT -4-

PROJECT IA FALL 2017 NAME:___________

DUE: 6:30 PM ON 5 OCT 2017 ID:_______________

C:\Users\mahajame\Pictures\img183.jpg

CE 4460 5560 PROJECT MANAGEMENT -5-

PROJECT IA FALL 2017 NAME:___________

DUE: 6:30 PM ON 5 OCT 2017 ID:_______________

C:\Users\mahajame\Pictures\img184.jpg