PROJECT MANAGEMENT
CE 4460 5560 PROJECT MANAGEMENT NAME:___KEY________
PROJECT IA FALL 2017 ID:___________________
DUE: 6:30 PM ON 5 OCTOBER 2017
1. YOUR ENGINEERING FIRM HAS BEEN CONTRACTED TO DESIGN A RESIDENTIAL STRUCTURE. THE PLAN AND PROFILE ARE GIVEN IN FIGURES 1 AND 2. PREPARE A COST AND SCHEDULE ESTIMATE FOR PREFORMING THE WORK. USE THE FOLLOWING SHEETS FOR YOU ESTIMATE. ANNOTATED MEANS ESTIMATING HANDBOOK COST AND DURATION SHEETS ARE PROVIDED IN A SEPARATE MOODLE DOCUMENT.
A. YOUR HAVE IDENTIFIED THE FOLLOWING ACTIVITIES TO BE
CARRIED OUT ON THIS PROJECT:
· PLACE 6 IN. DIAMETER - PLACE/COMPACT GRANULAR
PVC DRAIN PIPE SOIL BELOW FLOOR SLAB
· SURVEY EXCAVATION - EXCAVATE ALL SOIL TO
PERIMETER BASEMENT LEVEL
· POUR 12 IN. THICK CONCRETE - STRIP/STOCKPILE TOPSOIL
WALL
· REMOVE VEGETATION: - CAST REINFORCED
CLEAR AND GRUB CONCRETE FOOTING
- CAST CONCRETE FLOOR - PLACE GRANULAR SOIL
SLAB AROUND PVC PIPE
- BACKFILL AROUND - REPLACE TOPSOIL
BASEMENT
AC - ACRES: 43,560 FT2/ACRE
CY - CUBIC YARDS: 27 FT3/CY
BCY - CUBIC YARDS: 27 FT3/CY
LF - LINEAR FEET
CE 4460 5560 PROJECT MANAGEMENT -2-
PROJECT IA FALL 2017 NAME:__KEY_________
DUE: 6:30 PM ON 5 OCT 2017 ID:__________________
1. PREPARE THE ACTIVITY SEQUENCE FOR THE STRUCTURE: FILL IN
REMAINING BLANK SPACES.
____ ___SURVEY EXCAVATION PERIMETER________________________
_______ REMOVE VEGETATION: CLEAR AND GRUB _______
_______ STRIP/STOCKPILE TOPSOIL _______________
_______ EXCAVATE ALL SOIL TO BASEMENT LEVEL________________
_______ CAST REINFORCED CONCRETE FOOTING __________________
_______ POUR 12-IN. THICK CONCRETE WALLS _____________________
_______ PLACE/COMPACT GRANULAR SOIL BELOW FLOOR SLAB____
_______ CAST CONCRETE FLOOR SLAB ____________________________
_______ PLACE 6-IN. DIAMETER PVC DRAIN PIPE __________
_______ PLACE GRANULAR SOIL AROUND PVC PIPE _______________
_______ BACKFILL AROUND BASEMENT____________________________
_______ REPLACE TOPSOIL ___________________________
CE 4460 5560 PROJECT MANAGEMENT -3-
PROJECT IA FALL 2017 NAME:___________
DUE: 6:30 PM ON 5 OCT 2017 ID:_______________
2 PREPARE A QUANTITY TAKE OFF FOR THE FOLLOWING ACTIVITIES –
FILL IN BLANKS IN THE FOLLOWING TABLE.
ITEM ACTIVITY UNIT ESTIMATED QUANTITY
1 SURVEY SQ FT 12,096
2 CLEAR/GRUB SQ FT 12,096
3 TOPSOIL CU FT 11,869
4 EXCAVATE CU FT 69,123
5 FOOTING CU FT 1,140
6 WALL CU FT 2,660
7 GRANULAR CU FT 3,121
8 FLOOR SLAB CU FT 3,286
9 PVC DRAIN LN FT 396
10 PIPE GRANULAR CU FT 902
11 BACKFILL CU FT 18,480
12 TOPSOIL CU FT 4,878
BY SIGNING THIS PAGE, I HAVE NOT GIVEN OR RECEIVED HELP FROM THE
OTHER STUDENTS IN THIS CLASS.
NAME:__________________ SIGNATURE:__________________
CE 4460 5560 PROJECT MANAGEMENT -4-
PROJECT IA FALL 2017 NAME:___________
DUE: 6:30 PM ON 5 OCT 2017 ID:_______________
CE 4460 5560 PROJECT MANAGEMENT -5-
PROJECT IA FALL 2017 NAME:___________
DUE: 6:30 PM ON 5 OCT 2017 ID:_______________