production environment. SMEs and business users worked extensively to cleanse master data and open transactions. This data earlier was thoroughly tested and approved by the respective user and the same was uploaded in production environment. Uploaded data was validated by the respective user and confirm correctness. A crucial step was to ensure that all the users were defined in the final production environment with appropriate roles. Considering the user strength and dispersed locations, this period was regarded as the most stressful period of the project from further co-ordination point of view. A Help desk was setup and all the contacts of help desk were released to all the users to ensure un-interrupted support.
PHASE VII – GO LIVE
Earlier, the go-live date announced during the kick-off was July 1, 2015, but the project was delayed by 2 months due to the following reasons:
• Legacy data cleansing had many issues such as duplicates, removal of the redundant data, confirmation of the data from the respective projects and regions.
• Many developments needed re-work at the last moment.
• Some of the key users were not able to participate in the final testing process due to official commitment.
‘Go Live’ was finally announced on July 1, 2015 and old legacy systems were discontinued to ensure no user would log on to the old legacy system and feed the data. Old system was kept open to the extent of viewing the reports. Go live posed some practical issues and listed as under:
• Some of the users were not defined.
• Roles were not maintained for some of the users; either some of them were not created properly or given appropriate rights for executing the processes and hence, users were not able to proceed in the system.
• Some of the document print programs had issues. For example, some of the region level taxation issues were not configured and hence, purchase orders to suppliers were not committed.
• A few of the issues were conceptual and resolved by the help desk.
Go live related issues lingered for about 15 days and were resolved towards the end of the month. New SAP/R3 is well accepted after 1-1/2 months of go live and its benefits over the earlier legacy system are evident.
REALIZATION
SAP/R3 was live since last 9 months (with effect from July 1, 2015 – March 31, 2016) and project UTKARSH started delivering the perceived benefits. All the four divisions
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
185Volume 24 No. 3
were on a common platform using common processes, and standardization of the documents was completely achieved. This means that at the enterprise level, all the business users, SMEs were talking the same processes from SAP, and saw the existence of a single version of truth in terms of reporting. Having the same processes in the organization, has released some burden off the HR in terms of utilizing the resources across the divisions by way of transfers or deputation. Deputation or transfers to other divisions required little induction or virtually no induction in the newly inducted division.
Tight Control of budget variations in procurement and consumption booking was possible. Robust process of monthly closure for materials and financial transactions was achieved. Project cost and financial accounting data was integrated leading to same source of facts and gave complete real time visibility of all the critical resources across the enterprise, online. Clear and consistent view of project profitability to top management with a variance analysis was achieved. There was reduction in unapproved purchases to the tune of 20% (alternate – There was up to 20% reduction in unproved purchases). To begin with, 15% improvement in equipment availability and utilization was seen.
Project Manager, Mr. Roy quotes “Earlier I have seen top management used to spend valuable time in sorting out the transactional issues such as reconciliation between project costing and accounting profit and loss statements. With the introduction of SAP/R3, these trivial issues are eliminated and focus is achieved on strategic decisions”.
The Leadership team appreciated the efforts put in by UTKARSH team and all the team members by recognizing and suitably awarding them for their commendable efforts.
CEO, EPCI Business, Mr. Gandhi quotes “My business unit has a much improved visibility of project performance post SAP go live and that is helping my team to manage overall business risk . Scalability and flexibility of SAP processes is helping our business to facilitate growth in different business segments and new geographies.”
Head of Plant and Machinery, Engineering and Construction Division, Mr. Naik puts in “With SAP we have a tighter integration between equipment, tools, tackles and capital assets data to effectively manage and control operational and accounting life cycle. ETM module has given a greater visibility and ease of deployment of expensive construction equipment leading to better utilization.”
CEO, CMG Business, Mr. Sharma remarked “It gives me great pleasure to place on record our appreciation, as one of the user Groups of SAP, of the role played by the Project UTKARSH Team, that SAP implementation has provided my business with improved visibility of project performance and risk management capability.”
SOUTH ASIAN JOURNAL OF MANAGEMENT
186Volume 24 No. 3
TEACHING NOTE Implementing an ERP System in a Multi-business Company in India: The case of
MBPEL
This teaching note was prepared for the sole purpose of aiding classroom instructors in the use of the case to discuss. It provides questions that could be used to energize the classroom discussion. This case is not intended to serve as an endorsement, source of primary data, or as an illustration of effective or ineffective management.
SYNOPSIS
Marc & Brown Principles Enterprise Limited (MBPEL) was a flagship company of the 60+-year-old Marc & Brown Group. MBPEL was headquartered in Pune, India, and it had operations in over nine countries. The company had four major business divisions, namely, Engineering & Construction, Real Estate, EPCI and Interiors and Architectural. The company had 21 regional offices in India, and, employed over 7000 people.
Different business divisions of MBPEL were using different processes resulting in issues relating to uniform policies, procedure implementation, reorientation of employees transferred from one division to another, etc. MBPEL had always used home-grown systems, where the information and processes were handled in silos, and, the reporting was done in Excel. MBPEL was a growing organization acquiring projects in different geographies, developing capabilities to handle newer product lines, and, employing people across nationalities. To add to this, it was imperative to handle the changes in business laws and regulatory framework required greater control and standardization of business processes across all its divisions.
MBPEL had successfully deployed SAP/R3 as its enterprise solution. It was decided to go for Big Bang approach with a single go live covering the entire business scope across all the division. The total time taken to implement this project was 12 months, which was quiet aggressive considering complexity and diversity of businesses. The journey described in the case has been one of the best projects, which had a set of clear business objectives, and the organization strategy to work around three important dimensions, i.e., people, processes and Information Technology (IT) platform.
LEARNING OBJECTIVES
The case presents a real time scenario where ERP, SAP was the need and was well understood by the people of MBPEL, an engineering and construction company which exists from last 60 years. The case is designed for MBA students to understand the following concepts:
• To highlight the importance and requirement of high-end integrated solution, i.e., an ERP in engineering and construction company.
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
187Volume 24 No. 3
• To highlight the importance of standardization among all the process and to motivate the collaboration based practices in the organization.
• To identify the critical success factors in the adoption of ERP implementation in a complex and large organization.
• To understand the risk factors associated in ERP project in the engineering and construction company and adopting the strategies to mitigate these risks.
• To emphasize the importance of managing technological and social change management within the organization.
POSITION IN COURSE
This case was designed for use in an MBA program for the course of Enterprise Systems to teach the concept of practices of large and complex implementation of Enterprise Resource Planning (ERP). This case study would fit into a management course for executives covering:
• Change Management and Innovation;
• Information System for Management; and
• Managing Technology.
RELEVANT READINGS
1. Boersma, K., & Kingma, S. (2005). Developing a cultural perspective on ERP. Business Process Management Journal, 11(2), 123-136.
2. Isikdag, U., Underwood, J., Kuruoglu, M., & Acikalin, U. (2013). Data integration capability evaluation of ERP systems: A construction industry perspective. International Journal of Enterprise Information Systems (IJEIS), 9(3), 113-129.
3. Shaul, L., & Tauber, D. (2013). Critical success factors in enterprise resource planning systems: Review of the last decade. ACM Computing Surveys (CSUR), 45(4), 1-39.
ASSIGNMENT QUESTIONS
1. Any implementation of IT or IT road map must be aligned to the organization’s strategy by setting the ultimate objectives. Discuss the business objectives relating to SAP/R3 implementation in MBPEL and how well aligned is SAP/R3 implementation in relation with organization’s strategy. Discuss the takeaways from their journey.
2. Would you say that the entire implementation of ERP, MBPEL was carried out effectively? Discuss the challenges faced by MBPEL during the implementation?
3. “The efforts put in by MBPEL team in by Standardizing and Rationalizing benefited the organization in a big way.” Discuss the MBPEL journey.
SOUTH ASIAN JOURNAL OF MANAGEMENT
188Volume 24 No. 3
4. Leadership plays a pivotal role in the success of ERP implementation life cycle. According to you, what do you feel that which “leadership best practices” MBPEL managers engaged in for this project?
5. Analyze the entire change management process in the implementation of ERP project in MBPEL. Is MBPEL positioned to meet future challenges in line with its vision statements after the successful implementation of SAP/R3 HANA platform?
TEACHING PLAN
PRE-CLASS PREPARATION
Three-four hours of pre -class reading by the student and his analysis based on assignment questions is recommended. Basic exposure and knowledge of the important processes handled in engineering and construction industry is recommended. This case could be discussed in the class within 75-90 minutes.
The Class Plan could be as follows:
Introduction (10-15 minutes)
Case could be opened by engaging the students in a generic discussion related to enterprise systems and its importance to various industries in today’s environment.
Question 1 (10-15 minutes)
The instructor now could initiate the discussion on this question which focuses on the role of organization strategy in delivery the reliable and effective ERP deployment project. Also the role of critical success factors in scenario of MBPEL.
Question 2 (10-15 minutes)
The instructor should discuss the various issues and challenges faced by the MBPEL during the implementation of ERP from people, process and technology point of view. This will enable the students to think about how all these dimensions can effectively contribute to the smooth implementation of ERP in company like MBPEL.
Question 3 (10-15 minutes)
The instructor should bring the role of - standardization, Automation and bring-in the best practices in accelerating the business of MBPEL using SAP/R3 ERP solution.
Question 4 (10-15 minutes)
Best practices have to be discussed based on various stages in the entire project implementation phase beginning from requirement analysis to roll-out in MBPEL company.
Question 5 (15-20 minutes)
The instructor might ask the students to analyse the change management process in MBPEL for the multiple categories like executive support, and customer involvement.
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
189Volume 24 No. 3
Finally, he concludes the case by emphasizing the need to make a shift to meet the future challenges.
ANALYSIS
1. Any implementation of IT or IT road map must be aligned to the organization strategy by setting the ultimate objectives. SAP/R3 implementation in MBPEL has set certain business objectives. Discuss these objectives. How did MBPEL devise the strategy to implement these objectives? Discuss the takeaways from their journey.
This question initiates a discussion about setting the overall objectives mapped with their vision and need for change at MBPEL which is engineering and construction company. This question also throws light on the critical success factors (CSF) which are essential to implement these objectives in such an environment.
The Engineering & Construction (E&C) industry is recognised as an un-organised sector. This means business processes are yet to mature and the right kind of skill sets availability is always a scarcity. On top of these there are several other challenges posed by the regulatory authority in terms of releasing the land on time for the construction, stringent health, and safety and environment rules. However, deployment of right kind of technology and the monitoring of project management processes given different outlook to this industry and many players have entered in the segment and made market more competitive and challenging. ERP is being used in all stages from project planning to execution, and with project sites, where data on activities is digitized like
a. Pre-construction cycle
b. Project Delivery Cycle
c. Assets Management Cycle
d. Human Resource Management
e. Financial Management
f. Sourcing and Procurement cycle
MBPEL is in the field of Engineering and Construction for last 60 years. Over this time the firm has not only built a reputation for very high quality of work and on time delivery, but also created an organization diversified to cover entire value chain in the construction business. For over a decade, the divisions of MBPEL, namely, engineering and construction, EPCI, real estate and interiors and architectural businesses were using home grown systems, where the information and processes were handled in silos and reporting was mainly done in Excel. Heterogeneous processes across divisions were used, making it difficult to apply the same set of policies and procedures across these divisions. Further, they did not provide accurate, consistent and accessible data for timely decision-making to
SOUTH ASIAN JOURNAL OF MANAGEMENT
190Volume 24 No. 3
enhance the performance of capital assets or for that matter retirement of assets. The earlier home-grown and ageing systems did not lend itself fully to a modern IT infrastructure to cater to the needs of growing business in a dynamic environment such as addressing various geographical needs in the areas of taxation, powerful business intelligence tools, governance structure, etc. to monitor key performance indicators of construction business. The changes in business laws and regulatory frame work required a greater control and standardization of business processes across all its 4 divisions. Lack of integration in these business were seen from process side and was creating lot of disconnect especially across planning, budgeting, procurement, inventory management and consumption and governance. This scenario caused inconsistency in data across functions, again making it difficult to get a complete and consistent picture, for example, plant and machinery module was not integrated with capital assets.
The leadership has set objectives for improving cost competitiveness and operational margins, which will be achieved through acquiring capabilities of
a. Improved estimation and planning
b. Sound Budgeting / Cost control and inventory management
c. Improved procurement and inventory management
d. Improved utilization of capital and short term assets
e. Reducing process cycle times
The ultimate objective is to enable the business performance and flexibility for strategic options (acquisitions and partnerships). Exhibit 8 represents the ultimate objectives which were set up as top management and common processes which were essential to achieve these objectives.
Their strategies to achieve each of these require standardization, standardization and controlling key business processes as per best practices opted for Engineering and Construction Industry. The project was given a name through suggestion and selection process as UTKARSH.
ROAD MAP
a. To standardize all common and key processes across all divisions, with as much automation as possible in execution and controls.
b. To replace the existing system with a more robust, real time integrated ERP, which can address diverse needs of all the divisions
c. Aim to get the best international IT software which can support MBPEL across globe.
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
191Volume 24 No. 3
d. To choose that product which can upgrade and keep up with the latest technological opportunities e.g. open architecture, ease of integration, mobility.
MBPEL strategy is to understand numerous factors, which if not addressed properly and proactively, can be a potential show stopper. In depth analysis of the case brings out the following critical success factors:
a. People Commitment: This starts right from the very top and needs to be percolated to the operating levels.
b. Pragmatic business Requirement Mapping: While adoption of SAP standard practices is the most ideal approach, there are many requirements, which require customization. All stakeholders should decide the business value arising out of such requirements and quickly decide either way and move ahead.
Exhibit 8: Mapping of Objectives with Common Business Platform and Adoption of SAP/R3
Source: Company Data/Interviews
Ultimate objective
MBPEL’s Common Business Platform
MBPEL’s Business Processes
• Comply with environmental regulations and other legislations • Enable aggregation of data, business processes and MB end • Enable enterprise visibility of programs and customers • Enable flexibility for strategic options (acquisitions and partnerships) • Enable business performance improvement • Enterprise performance visibility and analytics • Executive reporting and key performance metrics dashboard • Provide IT transformation platform
• Foundation for future business growth • Single face to the customer • End-to-end supplier, program and customer visibility • Harmonize data and reporting across businesses • Leverage processes across business • Enterprise shared services portal content and applications • Ability to make resource decisions across businesses • Ability to integrate new business models
• Functionality to improve • Financial Management • Accounting, Consolidation, Reporting Analytics • Project Management • IT integration (SAP NetWeaver and Analytics infrastructure • Human capital Management • Manage end to end employee life cycle • Employee/Manager Self-service and Portal • Customer and Sales Management • Operations Management • Equipment and Tools Management • Gain Competitive advantage leveraging best available technology
SOUTH ASIAN JOURNAL OF MANAGEMENT
192Volume 24 No. 3
c. Testing: Creation of a robust test plan is a key to success of any project. Listing of all scenarios and preparing detailed integrated test scripts, providing real data for testing and performing adequate testing are all part of this managing this factor.
d. Data Migration: Data is the life and blood of any system. Data preparation and migration needs to begin very early in project life cycle. Data extraction, transformation and loading needs stringent quality checks and sign offs at every stage.
e. User Training: This factor is a key to a successful go live and stabilization. A dedicated team for creation of user training documentation and conduct training was moved in at the end of realization period. MBPEL used SAP’s new tools called Workforce Performance Workbench (WPB) to automate training document creation and creating it in various forms (Power Point, Word or PDF). This really helped in creating high quality documents with information integrity at minimum efforts.
The journey described above has been one of the projects that, had a set of clear business objectives, and a strategy to use key levers i.e. People, Processes and IT, together with a committed execution strategy, was delivered it on time. CSF’s ranking was done based on its importance in the MBPEL (1: strongly determine the success, 2: determine the success, 3: necessary for success) is described in Exhibit 9.
2. Would you say that the entire implementation of ERP, MBPEL was carried out effectively? Discuss the challenges faced by MBPEL during the implementation?
In MBPEL, different IT platforms were used by different divisions, making it impossible to get a complete view from a single source of data. The information was
Exhibit 9: CSF’s Ranking Done Based on its Importance in MBPEL
Top Management Support 1 Strongly determine the success
ERP Strategy 1
Change Management 1
Organization Culture 1
Effective Communication 1
Business Process Reengineering/Improvement 2 Determine the success
Retain the experienced employee 2
Problem Anticipation (troubleshooting, bugs, etc.) 2
Consultant and Vendor Support 3 Necessary for success
Monitoring and Evaluation of performance 3
Source: Interview with MBPEL, (Validated by Group Financial Controller Mr. Srinivasan, and Mr. Roy who was appointed as Project Manager of MBPEL)
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
193Volume 24 No. 3
with individuals and reporting mainly in Excel and power point. There exist different heterogeneous processes across divisions, making it difficult to apply same set of controls and KPIs. Also the lack of real time integration, causing inconsistency in data across functions, was making it difficult to get a complete and consistent picture, e.g. Plant and Machinery module was not integrated with capital assets was one of the biggest bottlenecks in its diverse business. Understanding the entire business process is itself a challenging. It was decided to go for Big Bang approach with a single go live covering the entire business scope across all the division. The total time to implement was planned as 12 months, which was quiet aggressive considering complexity and diversity of businesses. However MBPEL and Partner were confident of achieving after a detailed risk analysis and mitigation plan.
MAJOR CHALLENGES FACED AND ADDRESSED
a. Supporting unique construction processes (Rate analysis, Quantity and rate controls etc.), where standard SAP functionalities were found to be inadequate. A decision was taken to customize those processes to retain the key business controls
b. Volume of data: MBPEL had a significantly high volume of data as compared to the size of this implementation. Early preparation and strict quality control on the input data helped in meeting the timelines. A dedicated master data team was set up to handle this track
c. Users training: MBPEL had 100-120 plus projects across 21 regional offices in India, some of them located in remote sites. Training almost 2500 users on a new set of processes and system was a mammoth task. Here again a very pragmatic approach of Train the trainer and developing a team of power users across various regional offices helped to organize this
d. Support after go live: Support processes were set up before go live, which were on the lines of to ITIL framework. Support team was on boarded before go live to ensure adequate Knowledge Transition, but developing familiarity with user interactions.
3. “The efforts put in by MBPEL team in by standardizing, and automating benefited the organization in a big way.” Discuss the MBPEL journey.
Things, however, were not all positive and in their favour. In the era of rapid growth in construction and entry of new players entering this field, MBPEL was faced with growth opportunity on one hand but also a severe pressure on margins. The changes in business laws and regulatory frame work required a greater control and standardization of business processes across all its divisions. Disconnected business unit’s offers unnecessary complexity. Lack of integration was creating lot of
SOUTH ASIAN JOURNAL OF MANAGEMENT
194Volume 24 No. 3
disconnect especially across planning, budgeting, procurement, inventory management and consumption, which was driven by client contract and controlled as per budgets.
Standardization, Automation and bringing in best practices are the most important pillar which leads to success in the implementation of ERP-SAP project within short time. Planning was done in advance on the technical side, had the right implementation partner and expert before the start of the project. Team was aligned with the process much earlier, i.e., before 6-8 month before the project. This initial thought process and the input that has gone makes the process simpler and efficient. The right support and commitment of the top management was there. Considering these, technical and commercial challenges are there but they are more transactional in nature. Strategic and Change Management are the two most important critical success factors for MBPEL. Total of 45 dedicated members and 17 part time members were there in team. These part time members are based on their domain and subject knowledge. ‘Process Owner’ tag was given to some of the team members to ensure the accountability of the processes. This was seen as a good step to motivate the team members.
In one of statement of project manager, mentioned that “In 15 years of my SAP implementation experiences, I have never seen such an efficient and harmonized team which is the best part”.
4. Leadership plays a pivotal role in the success of ERP implementation life cycle. According to you, what do you feel that which “leadership best practices” MBPEL managers engage in for this project?
MBPEL leadership was actively supportive of this initiative and a steering committee consisting of all SBU Lead, Group Function leads, CIOs from 3 group companies and leadership team of implementation partner was formed before kicking off the project. The steering committee nominated process owners, who in turn nominated their top performers as core team members. This 3-tier structure ensured not only a robust approval and escalation process, but also it was a key element of change management by creating early engagement and ownership of all stakeholders in some manner. Thus at the peak there were almost 60 plus business representatives from very top, senior and middle levels participating in this project. Few observations are as follows:
a. The project leadership design was not a matter of assigning the task to a small group of people, but required a very different leadership structure.
b. MBPEL set up the high power steering committee much before the project team was put together.
c. A change management sub-committee was formed to look at any critical change issues.
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
195Volume 24 No. 3
d. Alignment of purpose and methodology by the steering committee was the major factor that helped the project. This ensured the core team members from diverse business entities heard the same message from their functional heads.
e. This commitment of standardization empowered team members to take some of the minor business decisions without any issues.
f. At the same time, the project managers were fully empowered to drive the project to ensure quality and timely completion of milestones.
In summary, responsible, collaborative and committed leadership style, with alignment to the purpose and empowerment of the people on the ground really helped MBPEL to deliver this project in 12 months. Exhibit 10 displays the mapping of leadership best practices for each of the phases.
Exhibit 10: Leadership Best Practices at MBPEL
Phases Issues Best Practices Outcome Role of
Leadership
Planning
Vendor Selection
Analysis
Business Process Redesign
Involving businesses to involve best of their resources.
Domain knowledge, HANA know- how.
Large number of As Is processes (540) across all businesses
Standardization of processes across diverse business units. EC&O MB specific practices and Indian taxation was complicated
Continuous engagement with the leadership team
Detailed RFP was floated and involved all the business and service heads to participate
Detailed documentation, reviews and identification of opportunities of standardization at this stage
Common workshops, open discussions and detailed documentation of issues and options
Looking at the sensitivity of the project best of the teams were deployed
With the consensus of everyone selected the best service provider to implement SAP
Detailed As Is process repository with expected changes in Blue Print and list of standardization opportunities
Harmonized processes across all businesses
Communicated the importance of the project to all the business heads and took the commitment
Shared the vision to service provider to sensitize the importance of the project and delivery dates with the quality deliverable
Regular reviews, time commitment of people. Sharing pains with current operations
Take pragmatic decisions and differentiate between core requirements V/S legacy / nice to have features
SOUTH ASIAN JOURNAL OF MANAGEMENT
196Volume 24 No. 3
5. Analyze the entire change management process in the implementation of ERP project in MBPEL. Is MBPEL positioned to meet future challenges in line with its vision statements after the successful implementation of SAP/R3 HANA platform?
Students’ attention should be brought to the fact that launching SAP/R3 HANA was not easy for MBPEL. During the implementation, there were various concerns especially related to change management.
Leadership at MBPEL could identify the need to make a shift from a purely bureaucratic and hierarchical and silos systems in the organization towards a standardized and centralized one. The organization with the top executive support prepared itself to meet the future challenges in line with its vision and mission. The following categories in the change management is accountable in the implementation of ERP project in MBPEL.
Support from top management is the most important factor in the entire life cycle of ERP implementation.
Exhibit 10 (Cont.)
Phases Issues Best Practices Outcome Role of
Leadership
Implementation Phase
Quality Assurance and Testing Phase
Training and Documentation
Cooling Phase (Rollout)
High number of modifications to be delivered in time and with right quality
Test data and comprehensive scenario capture. Manual testing
Training document creation and execution was logistically challenging
Big bang approach covering 1600 users, created large load on support process
Detailed documentation for Gap definition, Business MB specifications and technical reviews
Detailed test scripts to ensure right level of testing
Use if SAP’s tool for creation of documents (WPB). Train the trainer method
User support team and service desk was set up prior to go live
Critical developments were delivered before go live
All transactional processes were tested on priority
All user documents were created before training
Not many show stoppers after o live and it reduced gradually with time
Pragmatic decisions on prioritization of modifications
Facilitation of testing by bringing in right end users and being solution seeker in issues
Providing separated team for training documentation creation and execution
Investment in on boarding support team prior to go live for KT and practice
Source: Interview with MBPEL (Validated by Mr. Roy who was appointed as Project Manager of MBPEL)
IMPLEMENTING AN ERP SYSTEM ON A MULTI-BUSINESS COMPANY IN INDIA: THE CASE OF MBPEL
197Volume 24 No. 3
a. Responsible for the dispute resolution mainly for adopting SAP/R3’s processes which were different from the legacy processes.
b. Responsible for providing best of the manpower to ensure successful implementation.
c. Review the progress of the project in a timely manner and plug in right kind of support to make sure no slippages in the project.
d. Motivate project team .
The next priority at MBPEL is – involvement of process owner (important is at medium level):
a. Conduct change management process workshops effectively to ensure all users are adequately conversant with the new processes.
b. Make sure all the users are well trained. To ensure this process owners are expected to prepare training material and prepare the live cases to simulate real life situations during the training sessions.
c. Data ownership is one of the most important tasks to be owned by the process owner. They are expected to make sure legacy data is cleansed and migrated to the new system and more importantly data is made available during testing, training and in the go live phases.
WHAT HAPPENED?
SAP/R3 was live since July, 2015 and the project team ensured proper maintenance by recording change request, a software tool provided by SAP. Four major steps were identified to take this implementation further. An Immediate step was to have project monitoring dashboards using Business Objects and all the requisite KPIs, well defined. By June, 2016 the project team is confident to deliver these dashboards. Real estate division of MBPEL came up with the need of implementation of Customer Relationship Management (CRM) system. SAP/R3 was a logical choice to implement the same. Time lines are drawn to complete the implementation by December 2016.
Looking at the success of SAP/R3 in the business, employees would like to have their leave processing using mobile based applications. The Project team has consolidated other requirements for mobile based applications such as creating and approving purchase requisitions, approving purchase orders, leave applications and approvals, travel and expense approvals, etc. SAP/R3’s FIORI has been chosen as the platform for development.
Encouraged by the success of project UTKARSH for Indian operations for construction business of MBPEL, the international business division has decided to
SOUTH ASIAN JOURNAL OF MANAGEMENT
198Volume 24 No. 3
roll out the same solution using existing SAP system and hardware to its operations spanning in Middle East and Africa. MB International has 2,800 own staff and 10,000 plus workmen engaged across almost 50 plus projects across these countries. This project, scheduled to be kicked off by October 1, 2016, will be completed by March 2016.
Copyright of South Asian Journal of Management is the property of South Asian Journal of Management and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.