using a project valuation method OR feasibility study approach, a risk analysis and a cost-benefit analysis
|
|
Business Case Check List
|
Item |
· |
Comments/Suggestions |
|
1. Does the Executive Summary provide concise information about the following: · Why the project is necessary · What alternatives were evaluated · How the recommendation addresses the specific business issues · What the goals and objectives are · What are the measurable cost and savings |
|
Must answer · What you want to do · What will LH get out of the project (e.g. Strategic Goals) · How much will it cost (Estimate) · How long will it take to return the investment (estimated) |
|
2. Have the issues that are resulting in the need for the project been documented and agreed to? |
|
|
|
3. Have the major goals and objectives of the project been identified? |
|
|
|
4. Does the purpose and scope state very clearly: · What you are requesting · What functional areas in LH are impacted · What is expected to result from this project (key deliverables) |
|
· Someone who is not familiar with your project should be able to pick up the business case and understand what you want to do |
|
5. Can someone who does not know your project, pick up the business case and understand: · What is the background that is leading to this project · What you are asking for · What will be deliverables or results from the project |
|
Write the business case and then put it down. Pick it up later (perhaps the next day) and re-read it. Is it written for “you” or for the “reader” |
|
6. Have all relevant costs been considered? Such as: · LH FTE’s (Internal labor costs) · Hardware · Hardware annual maintenance · Software Development · Application Buy /Software License fees · User Training · Outside contractor/consulting · Advertising campaigns · Etc |
|
· Schedule a meeting with the principal people or areas involved to get their input and how this may or may not impact other projects |
|
7. Have all tangible benefits/savings been considered? Such as: · One time savings in cash flows (process Improvements) · Increased revenues / New Business · FTEs reductions |
|
|
|
8. Have all individual departments responsible for the projected savings been contacted and do they agree with the savings projections/rationale? |
|
|
|
9. Have costs and savings been spread over a multi-year projection (typically 5 years)? |
|
|
|
10. How will you measure the projected savings? |
|
|
|
11. Have intangible savings been considered? |
|
|
|
12. Have you considered how this project may interface with other projects within LH? |
|
|
|
13. Are the objectives and goals for this project SMART · S pecific · M easurable · A chievable · R ealistic · T ime constrained (have a time factor associated with them) |
|
|
|
14. Have all assumptions made for the business case been documented and agreed to? |
|
|
|
15. What is the likelihood of realizing the projected savings? |
|
|
|
16. Have other alternatives been identified that may achieve similar goals and objectives? |
|
|
|
17. Have other departments whose resources may be required to support the project been contacted and are they in concurrence? |
|
|
|
18. Has a return on investment and payback years been calculated? |
|
Summarize this in the executive summary |
|
19. Has a general time frame for implementation been defined? |
|
|