BUS472 Unit 3 Assignment Template
Instructions: Fill in the only the yellow fields:
1. Qualitative Risk Assessment
Identified risk factors Likelihood
1. Key team members pulled off project High
2. Chance of economic downturn Low
3. Project funding cut Medium
4. Project scope changes High
5. Poor spec. performance Low
Based on the above risk factors and likelihood, how would you rate the consequences (use your own judgement) and offer why.
Consequence Why?
1
2
3
4
5
For example if you were to classify all risks with a medium consequence, then populate the numbers as follows:
Now that you have the likelihood and consequence for each risk, populate the risk number(s) in the below matrix.
Consequence Consequence
Low Medium High Low Medium High
Likelihood High Likelihood High 1, 4
Medium Medium 3
Low Low 2, 5
2. Risk Mitigation Strategies
From the five risks from above, what would be your suggested risk mitigation approach. Justify your reason for choosing.
Mitigation Approach Why?
1
2
3
4
5
If you were to prioritize your efforts, which risk factors would you address first? Why?
3. Quantitative Risk Assessment
Assume the following information:
Probability of Failure Consequences of Failure
Maturity = .3 Cost = .1
Complexity = .3 Schedule = .7
Dependency = .5 Performance = .5
Calculate the overall risk factor for this project:
Pf=
Cf=
RF= How would you classify this level of risk:
Why:
4. Cost of Labor
Compute the cost of labor for the following team members
Name Hours Needed Overhead Charge Personal Time Rate Hourly Rate Fully Loaded Labor Cost
Sandy 60 1.35 1.12 $ 18
Chuck 80 1.75 1.12 $ 31
Bob 80 1.35 0 $ 9
Penny 40 1.75 1.12 $ 30
5. Planned and Cumulative Costs
Compute the Plan and Cumulate costs for the project:
Work Package Budget Week 1 Week 2 Week 3 Week 4 Week 5
Staffing $ 500 $ 400 $ 100
Blueprinting $ 800 $ 100 $ 600 $ 100
Prototyping $ 1,200 $ 200 $ 800 $ 200
Full Design $ 2,400 $ 400 $ 1,000 $ 1,000
Plan:
Cumulative:
6. Complexity Cost Weighting
Consider the data provided below and compute the total estimated of function points
Function Number of Screens Complexity
Input 8 Low
Output 6 Low
Interfaces 15 High
Queries 5 High
Files 25 Medium
Complexity Weighting
Function Low Medium High Total
Input 2 x 4 x 6 x
Output 3 x 6 x 12 x
Interfaces 6 x 12 x 18 x
Queries 4 x 6 x 8 x
Files 2 x 4 x 8 x
Calculate the total expected cost of the project:
Assume that each resource can complete five function points per month and each programmer costs $4,000 per month.
Total Number of Functions:
Total Number of person-months needed:
Total cost for the Project: