Coca Cola Supply Chain Management Software Development

Institutional Affiliation: Strayer University

Student’s Name: Elif Sam

Course: BUS 419

Submission Date: 11/22/2020

WBS

Project estimate: 300 hours: Coca Cola Supply Chain Management Software Development

1. Project set-up – 20 hours

1.1 Project process definition = 5 hours (project manager)

1.2 Environment set-up = 5 hours (technical engineer)

1.3 Determine initial sprint = 5 hours (technical engineer)

1.4 Project setup completion = 5 hours (project manager)

2. Sprint 1 UI- 40 hours

2.1 sprint 1 plan = 10 hours (sprint organizer)

2.2 selection of sprit 1 user stories = 10 hours (sprint organizer)

2.3 user stories assignment = 10 hours (sprint organizer)

2.4 sprint 1 plan completion = 10 hours (sprint organizer)

3. User Interface = 30 hours

3.1 User interface design = 5 hours (user interface designer)

3.2 Building user interface = 5 hours (user interface engineer)

3.3 Testing user interface = 5 hours (user interface tester)

3.4 UI’s UAT = 5 hours (user interface designer)

3.5 Correcting issue from UAT UI = 5 hours (user interface engineer)

4. Sprint 2 reports = 40 hours

4.1 sprint 2 plan = 10 (technical writer)

4.2 selecting sprint 2 user stories = 10 (sprint manager)

4.3 assigning user stories = 10 (sprint manager)

4.4 sprint 1.1 plan completion = 10 (sprint manager)

5. Client Specified Reports = 20 hour

5.1 Design reports = 5 hours (project designer)

5.2 Building reports = 5 hours (project designer)

5.3 Test reports = 5 hours (project tester)

5.4 UAT reports = 5 hours (project designer)

5.5 Correcting issues from UAT of Reports

6. Sprint 3 Platform = 30 hours

6.1 Sprint 3 plan = 5 hours (platform designer)

6.2 user stories selection = 5 hours (platform designer)

6.3 user stories assignment = 10 hours (platform designer)

6.4 completion of sprint 3 = 10 hours (platform designer)

7. Gross Platform Support = 40 hours

7.1 Designing cross platform support = 10 hours (support engineer)

7.2 Building Cross platform support = 10 hours (support engineer)

7.3 Testing cross platform = 10 hours (testing engineer)

7.4 UAT of CPS = 10 hours (support engineer)

8. Project End = 20 hours

8.1 Obtain project client signoff = 10 hours (project manager)

8.2 Provide project reports out = 5 hours (project manger

8.3 Project end celebration = 5 hours (project staff)