Energy management (building project)
Marina Park Energy Study BC Housing
Marina Park is located at 4843 48 Ave, Delta, BC and includes fifty (50) one-bedroom apartments of
social housing and a common amenity room. Marina Park is a three-story wooden framed building built
in 1988, approx. 35,500 ft2.
The windows are original to the building. One (1) natural gas boiler original to the building and installed
in 1988 supplies heating hot water to perimeter hydronic baseboards in the suites and common areas.
Domestic hot water (DHW) is produced by one (1) natural gas hot water boiler also original to the
building and stored in a hot water storage tank. Both boilers, DHW storage tank and all pumps are located
in the central mechanical room.
Ventilation is provided by two (2) supply fans located on the roof and in the 3rd floor ceiling space. Both
supply fans are original to the building and provide unconditioned outdoor air to the corridors via ducting
and supply grilles.
3 �
Existing Facility / Building Description
Table 2 – Building Information
Building Information Description
Fortis Account Number 734459 Premise Number 505495
BC Hydro Account Number 1955 8200 082 Natural Gas Utility Rate $8.43/GJ
Electricity Utility Rate $0.114/kWh Construction Type Wood framed
Age 30 years (Built in 1988) Major Renovations None
General Physical Condition Average Floor Area Conditioned 3,300 m2 (35,500 ft2)
Floor Area Non-conditioned 0 Total Floor Area 3,300 m2 (35,500 ft2)
Number of Floors 3 Occupancy Schedule 24/7
Number of Residential Units 50 one-bedroom apartments and amenity room of social housing General System Description In suite heating via hydronic baseboards, DHW and space heating
provided through NG fired central heating plant. See page 17 for detailed description of the building systems.
Energy Use Analysis
Utility consumption and cost from August 2017 to July 2018 was 174,700 kWh at $19,900 for Electricity
with a rate of $0.114/kWh, and 1,820 GJ at $15,300 with a rate of $8.43/GJ for Natural Gas.
Table 3 presents actual natural gas usage for last year.
4 �
Table 3 – Monthly Natural Gas Consumption for 2017
Natural Gas End-Use Breakdown
Natural Gas is utilized by the central heating boiler that supplies hot water to the perimeter baseboards.
The central DHW boiler also utilizes Natural Gas for DHW production.
Table 4 presents actual natural gas usage for the past 3 years
Table 4 - Natural Gas End-Use Breakdown
Electricity Total Consumption
0
50
100
150
200
250
2017 Monthly Consumption (GJ)
5 �
Available Electricity utility data is for 3 years.
Table 5 presents actual electricity usage for last year.
Table 5 – Monthly Electricity Consumption for 2017
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
2017 Monthly Electricity Usage (kWh)
The existing space heating boiler has an input
capacity of 1,080 MBH. We have calculated the total
heating requirement to be closer to 400 MBH for
full heating at peak loads. The existing DHW boiler
has an input capacity of 399 MBH with a 115-gal
storage tank.
Existing space heating boiler
Existing DHW boiler
The HVAC ductwork is in overall poor condition. Some exhaust ductwork are not sealed, which is a code violation.
The majority of outdoor lighting at Marina Park currently utilizes conventional incandescent fixtures with
some CFL replacements. Outdoor lighting consists of pole lighting and wall packs on the building exterior,
all controlled by photocells.
Existing outdoor pole lighting
Existing building exterior wall packs
The building envelope is deemed to be in average condition. Some envelope deficiencies were observed including high rates of outdoor air infiltration through poorly sealed windows.
Interior lighting of the common areas at Marina Park is
exclusively by fluorescent bulbs in the common corridors. Some
fixtures have already been replaced with LEDs and the
remaining fluorescent tubes are currently being replaced with
LEDs.
Existing indoor hallway lighting
17 �
System Description
Heating, DHW and Ventilation Systems
Ventilation to the hallways is provided by two (2) supply fans located on the roof and in the ceiling space
above the 3rd floor. Both fans are original to the building and are ducted to two (2) supply air grilles on
each floor. As there is no heating of ventilation air, both fans supply unconditioned outdoor air so it is
presumed that these fans are turned off during the winter.
Heating hot water for space heating is supplied by one (1) natural gas boiler and domestic hot water is
produced by one (1) natural gas hot water boiler. Both boilers are located in the Mechanical room and are
original to the building. Space heating is delivered by perimeter hydronic baseboards in the suites and
common areas.
The central boiler plant consists of one (1) AAE Super Hot 1080 MBH boiler for space heating, one (1)
Lars Mighty Therm 399 MBH hot water boiler for DHW production and one (1) Rheem 115-gal indirect
heated storage tank for DHW. Delivery temperature for the DHW hot water is determined by the storage
tanks. Both boilers are nearing their end of life expectancy.
Mechanical room including existing DHW boiler, DHW storage tank and space heating boiler
18 �
Control equipment
For the major equipment in the mechanical room, controls are
local to the equipment.
Space heating baseboards respond to local manual dial wall
mounted controls in the suites and common areas while some
baseboards are controlled by a manual dial on the unit itself.
Plumbing Fixtures
None of the existing plumbing fixtures on site were observed to
be low flow.
Electrical Systems
Other than lighting, the main components of the common electrical systems are the heating water and
DHW circulation pumps, the ventilation fans, and the elevator.
Each suite has a refrigerator and stove, neither of which are ENERGY STAR rated. There is also a kitchen
exhaust hood in each suite but no bathroom exhaust.
Lighting Systems
Interior lighting of the common areas is a combination of CFL PL lighting in wall mounted fixtures in the
hallways, some ceiling dome LED fixtures, and fluorescent T8 fixtures in the amenity room, laundry
room, office and stairwells. However, it was observed that all fluorescent T8 lamps are currently being
replaced with ballast ready LED lamps.
Lighting in the suites predominantly consists of incandescent lighting with some LED and fluorescent
lighting in the living rooms and kitchens.
Existing indoor entrance lobby LED lighting
Existing in-suite manual dial control for hydronic baseboards
19 �
Outdoor lighting is a combination of incandescent and CFL bulbs for
the pole lighting, incandescent wall packs on the building exterior, and
one (1) HID fixture on the building exterior. Exterior lighting is
controlled by photocells.
Envelope System
The building is wooden framed with a sloped roof and windows are standard double pane with aluminum
frames.
Existing building exterior lighting
Existing indoor amenity room lighting
ECM 01: Boiler Replacement
"Very common in all buildings of this vintage, boilers are oversized for what is actually needed to
meet heating requirements."
Total ECM 01 cost: $36,800
ECM 02: Lighting
a) Outdoor Lighting
The majority of outdoor lighting at Marina Park currently utilizes conventional incandescent
fixtures with some CFL replacements. Outdoor lighting consists of pole lighting and wall packs
on the building exterior, all controlled by photocells.
Total ECM 02a cost: $4,980
b) Indoor Lighting of Common Areas
Interior lighting of the common areas at Marina Park is exclusively by fluorescent bulbs in the
common corridors.
Total ECM 02b cost: $1,030
Consumption Consumption
kWh GJ ekWh ekWh
January 16,676 135.88 37,639 54,316
February 14,731 213.53 59,148 73,878
March 15,622 217.06 60,125 75,747
April 14,388 173.53 48,068 62,456
May 13,813 124.12 34,381 48,193
June 12,532 80.00 22,160 34,692
July 12,366 64.12 17,761 30,127
August 12,135 74.71 20,694 32,829
September 12,599 107.65 29,818 42,417
October 13,851 167.06 46,275 60,126
November 14,674 223.53 61,918 76,591
December 16,630 282.94 78,375 95,005
Overall: 170,016 1,864.12 516,361 686,377
January 15,390 242.11 67,063 82,453
February 13,891 197.89 54,817 68,708
March 14,006 188.42 52,193 66,199
April 13,056 138.95 38,488 51,544
May 13,021 106.84 29,595 42,616
June 12,266 90.53 25,076 37,342
July 12,356 76.84 21,285 33,641
August 12,406 71.05 19,682 32,088
September 12,659 101.58 28,137 40,797
October 13,627 143.16 39,655 53,282
November 14,080 187.37 51,901 65,981
December 15,596 266.32 73,769 89,366
Overall: 162,356 1,811.05 501,662 664,017
January 14,200 208.80 57,838 72,038
February 14,800 204.70 56,702 71,502
March 13,200 189.80 52,575 65,775
April 13,100 176.20 48,807 61,907
May 13,700 137.00 37,949 51,649
June 13,600 101.90 28,226 41,826
July 14,000 85.30 23,628 37,628
August 15,700 87.80 24,321 40,021
September 13,800 95.60 26,481 40,281
October 13,900 139.60 38,669 52,569
November 15,600 196.80 54,514 70,114
December 16,500 218.60 60,552 77,052
Overall: 172,100 1,842.10 510,262 682,362
January 15,840 227.50 63,018 78,857
February 13,991 206.50 57,201 71,192
March 14,615 215.50 59,694 74,309
April 13,495 164.00 45,428 58,923
May 13,419 120.00 33,240 46,659
June 12,408 87.00 24,099 36,507
July 12,587 70.00 19,390 31,977
August 12,453 49.00 13,573 26,026
September 12,559 53.50 14,820 27,378
October 13,660 158.50 43,905 57,565
November 13,700 217.00 60,109 73,809
December 16,400 220.00 60,940 77,340
Overall: 165,127 1,788.50 495,415 660,541
Energy Total
Consumption
2018
Year Month
Electrical
2015
2016
2017
Fuel Total