BSBPMG522

Undertake project work

Learner Workbook

Table of Contents

Table of Contents 2

Candidate Details 3

Assessment – BSBPMG522: Undertake project work. 3

Competency Record to be completed by Assessor 4

Observation/Demonstration 5

Activities 7

Activity 1A 7

Activity 1B 8

Activity 1C 9

Activity 1D 10

Activity 2A 11

Activity 2B 12

Activity 2C 13

Activity 2D 14

Activity 2E 15

Activity 3A 16

Activity 3B 17

Activity 3C 18

Activity 3D 20

Activity 3E 21

Activity 4A 22

Activity 5A 23

Project 24

Major Activity 26

Observation/Demonstration

Throughout this unit, you will be expected to show your competency of the elements through observations or demonstrations. Your instructor will have a list of demonstrations you must complete or tasks to be observed. The observations and demonstrations will be completed as well as the activities found in this workbook. An explanation of demonstrations and observations:

Demonstration is off-the-job

A demonstration will require:

· Performing a skill or task that is asked of you

· Undertaking a simulation exercise

Observation is on-the-job

The observation will usually require:

· Performing a work based skill or task

· Interaction with colleagues and/or customers

Your instructor will inform you of which one of the above they would like you to do. The demonstration/observation will cover one of the unit’s elements.

The observation/demonstration will take place either in the workplace or the training environment, depending on the task to be undertaken and whether it is an observation or demonstration. Your instructor will ensure you are provided with the correct equipment and/or materials to complete the task. They will also inform you of how long you have to complete the task.

You should be able to demonstrate you can:

· Define project

· Develop project plan

· Administer and monitor project

· Finalise project

· Review project.

You should also demonstrate the following skills:

· Reading

· Writing

· Numeracy

· Oral communication

· Navigate the world of work

· Interact with others

· Get the work done

Activities

Activity 1A

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to access project scope and other relevant documentation and define project stakeholders

Activity

The local City Council want to stage a free family fun day at the local city Botanic Gardens to celebrate its 25th Birthday.

Who would you list as the stakeholders?

The Local city council authorities, the event management team and the families of the city who will visit and attend the event will be stakeholders of this event.

Activity 1B

Estimated Time

45 Minutes

Objective

To provide you with an opportunity to seek clarification from delegating authority of issues related to project and project parameters

Activity

Using the examples provided of the types of parameters you may need to consider when seeking clarification from a delegating authority for issues related to the project, detail briefly your thoughts and suggestions on the impact of these:

· Project finances or budget

Project finance or budget direct effect the availability and volume of business resources which are required and critical for completion of a project.

· Procurement requirements associated with project

Through this, the availability of raw material and other business resources can make possible for completion of a business project.

· Scope of project

It defines the limitations of the project.

· Integration of project within organisation

Through highly productive results can achieve with high efficiency level as well.

· Legislative and quality standards

It helps to evaluate or asses the quality of project and the implementation of legal rules as well.

· Physical, human and technical resources available or required for project

Through availability of such resources, the desire level of productivity and efficiency can obtain from the project.

· Reporting requirements

Through this ,the stakeholders can evaluate the performance of the project and the gap present in the outcomes of the project can understand easily.

· Risks associated with project, including WHS

Through this, the business can adopt a pro active behaviour and can make an effective plan in advance to deal with future risk.

· Time lines.

Through this ,the maximum time required for completion of a project can identify. This increase motivation of project team and persuade them to make continuous efforts to complete project within due time.

Activity 1C

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to identify limits of own responsibility and reporting requirements and clarify relationship of project to other projects and to the organisation's objectives

Case Study

Are there other projects that have occurred previously that would help you better understand the strategic objectives?

· If so, what are they?

Yes some other projects related to product development and project expansion has been already taken.

· Are you able to access them?

Yes.

· How do they compare with the current proposed project?

The risk evaluation processes which need to be carried out in this propose project can compare with previous one.

· How can you relate such key items as cost, feasibility, and so forth?

Through cost and feasibility, the propose future of the project can identify and evaluate.

Activity 1D

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to determine and access available resources to undertake project

Activity

Using your workplace as the source of a project, complete the initial details in this suggested example.

The Broad Scope Definition template is a tool that can be used with key stakeholders to clearly define the logical boundaries of the project. Be sure to note any requirements that are out of scope to achieve absolute clarity about what is and is not covered by this project and to avoid the potential for problems later

Name of project

In Scope

Out of Scope (Exclusions)

Assumptions

Constraints

These are items that you are definitely going to deliver / manage

These are items that you are not responsible for – the assumption is that someone else will do them. Exclusions are things that don’t form part of your project, but influence on whether or not you can successfully achieve your objective

Knowledge about the project that is taken as being true or correct for the purposes of project planning. Assumptions are circumstances and events that need to occur for the project to be successful, but are outside the total control of the project team

Known restrictions. These could include any restrictions in start/finish date, time, deliverable or milestone dates, budget limitations, resourcing limits, vendor restraints, etc.

Your project details

The product development process will be carried out by all means.

Effect of any external environmental factor might be able to affect the future direction of success and productivity of the project.

All the project team will work by a high motivation level.

All business resources will remain present in the business throughout the completion of project.

The team project is responsible to give the desire results of the project within given or specify time line.

Activity 2A

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to develop project plan in line with the project parameters and identify and access appropriate project management tools

Activity

Using your workplace as a reference, in groups or as directed by the instructor, develop a project plan outline using a suitable tool, either from the examples provided or using what is provided by your workplace.

You should address:

· Timelines

· Work structure

· Responsibilities

· Parameters

And describe the project management system used:

To writ the project plan for development of a new product , the following points will need to follow:

(i) Scope of Project:

Through this project, a new product development plan will discuss in detail. For this, a complete team will create which will responsible for product development.

(ii) Identify Stakeholders:

The product development team, the financer of project, the customers who will use the product and the business who is going to produce a new product will be the stakeholders of the project.

(iii) Deliverables:

The project will be dividing into various stages and achievement of each stage result will be deliverables of the project. First stage is research and market analysis. Second stage is identification of risk and financial resources, third stage is about development and testing of project and fourth stage is about offering the product to end consumers.

(iv) Create Project Schedule:

The project will complete with in timeline of 40 working days. The project team will responsible to complete the entire project with in stipulated time.

(v) Establishment of Team:

A team of 7 team members with one project leader can establish to achieve the desire results. The entire team will responsible to complete this project as per stated benchmarks.

Activity 2B

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to formulate risk management plan for project, including Work Health and Safety (WHS)

Activity

Conduct a WHS audit.

In groups, or as directed by the instructor, using a project plan example or one from your workplace address the issues below as it relates to your project WHS assessment.

Answers will vary depending on group, so a discussion once complete will help to share ideas and knowledge

Workplace activity

1. Design a simple project WHS reporting and monitoring check list

(i) Identify hazard risk

(ii) Identify the extent of safety level

(iii) Evaluate the safety measures need to implement

(iv) Evaluate the performance of safety system and measures

2. Describe how the project director/manager will investigate serious WHS breaches or incidents

By identifying the actual performance of health and safety system and through comparison of the actual health and safety system with the benchmarks, the WHS base serious incidents can identify in advance.

3. Describe safe work procedures that are specific to you project

(I) Never work under influence of any drug.

(II) Do not reveal the confidential information of project to a unauthorized person.

(III) Work on continuous base instead of speedy work at end of timeline.

4. Describe at least FOUR (4) project KPI's that may have impact on WHS performance parameters

(i) Decrease in chances of accidents

(ii) Decrease the risk of injury

(iii) Improve the quality of environment by decreasing pollution level

(iv) Adoption of recycle activities for waste management

Activity 2C

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to develop and approve project budget

Activity

In groups, or as directed by the instructor and using a project from your workplace, address the issues below as it relates to developing and planning for approval of a project budget. Use as an example the base structure of an existing workplace project but avoid simply duplicating that budget!

1. Demonstrate your budget knowledge:

· Estimate team hours required to complete each task

To complete each deliverables a minimum time of 22 working hours will require.

· Describe applicable overhead costs as a percentage of those direct labour costs

30% of direct cost will be categories as overhead cost.

· Estimate other direct costs (such as consultants, printing etc)

The estimated direct cost will be $5,000.

· Describe appropriate contingency costs and why

Any change in health and safety base laws can persuade the business to change its existing health measures into new one. Application of new laws will increase the cost volume.

1. Detail how much you have to spend

Overall to complete the project a amount of $70,000 is need to spend.

2. Detail what project expenses are mandatory or most important

The direct cost of project is mandatory which include material cost, labour and overhead cost.

3. How would you go about obtaining prices and quotes for expenses

Use of auction, tender and market analysis base strategies can help the business inn this regard.

Activity 2D

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to consult team members and take their views into account in planning the project

Activity

In groups, or as directed by the instructor, conduct this activity by asking the team members questions about project time constraints for an example project.

· Obtain the information from your team based on a project of your choice.

The team is entitled to perform a project for development of business information system. The team is responsible to identify why the need arise to have a new information system, which information system is suitable and why, the process of implementation of new information system and to minimize the extent of risk associated with the development of a new information system in business.

The team state that all scope of project is completed but the limited timeline adversely affect the execution of project.

Issue: time constraints.

Workplace activity

· Meet with the team members who identify their specific roles and who will be working with you to begin to build a preliminary schedule

· Ask the team members what it takes in time and effort to get their respective tasks completed.

· Compare the information you have against the deadline provided.

· Ask your team if it is possible at all to shorten those timeframes

· Gather all the necessary data from your team as to what it takes to complete those tasks.

Activity 2E

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to finalise project plan and gain necessary approvals to commence project according to documented plan

Activity

1. Describe what experiences you have encountered in gaining the necessary approvals to commence a project?

Through this, I learn that practical execution of a project and its start is a complex task. I face several issues to convey the scope of project and its limitations to the other team members and to define and design the responsibilities of each team member before start of project. I face several conflict and understanding base hurdles while guiding and leading the team members in start of project.

2. How did you overcome any approval obstacles?

Through continuous work and open communication, I become able to overcome the obstacles.

3. What were the methods you used in seeking approvals?

Management by Walking Around is the ultimate strategy in this regard. Through this, I become able to walk around with the entire team members while working on their entitled task. Through which, I can monitor and evaluate their performance level and can guide them wherever it become important during development of information system for business.

Answer in relation to an identified project example.

Activity 3A

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to take action to ensure project team members are clear about their responsibilities and the project requirements and provide support for project team members, especially with regard to specific needs, to ensure that the quality of the expected outcomes of the project and documented time lines are met

Activity

Using a workplace example of a recent or current project, detail your findings on how you experienced it as a team member or how you handled it as a project manager using the following examples provided:

1. Take action to ensure project team members are clear about their responsibilities and the project requirements

Presence of effective reward and recognition plan can help to motivate the team members to work hard and perform their responsibilities I an effective manner.

2. Provide support for project team members, especially with regard to specific needs, to ensure that the quality of the expected outcomes of the project and documented time lines are met

· A brief training of 2 to 3 days will be arranged to guide the team members.

· A manual or guiding map will provide to increase the support of team members about how they should perform.

· Presence of continuous performance evaluation techniques will help to identify performance gap among team members and to prepare necessary guideline for them.

Activity 3B

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to establish and maintain required record keeping systems throughout the project

Activity

Using a workplace example of a recent or current project, detail how you experienced maintaining required record keeping systems throughout the project as a team member or how you handled it as a project manager, using the performance criteria just addressed.

Provide examples and suggestions used in your workplace.

To record the entire team progress regarding a project, the help is obtain from the business information system. Beside this ,the project assessment document and blue prints of the project is filled in the business confidential documents to make final report and to use as a reference in future.

Activity 3C

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to implement and monitor plans for managing project finances, resources and quality

Activity

Suggest further comments to these steps for implementing and monitoring plans for managing project finances.

Implement Steps

Monitor Actions

Your Comments

Communicate what needs to be done and by what deadline

Assign the work by breaking down the tasks into smaller and more manageable pieces.

Perform continues monitoring activities to evaluate the work and performance direction of employees.

Consider a variety of expense alternatives

Develop and agree on the project budget plan.

Identify the sources of obtaining external finance and their relevant cost as well.

Choosing suppliers and contracts for goods or services

Base decisions on either company policy or what is best to deliver on project time as well as price.

Can make JIT base contract with suppliers or adopt highly integrated supply chain strategy.

Prepare timeline and sequence of activities

Use a prepared schedule to manage the overall project to ensure its timely completion.

Use Work break down structure and Gantt chart technique to identify maximum time required for completion of each task

Outline clear expectations for the project team and other human resources

Project teams are only temporary so select team members based on their technical skills.

Their individual and collective performance will impact on the financial resources and outcome.

Establish and design clear and simple KPI’s through which one can easily compare the actual performance.

Identify as many potential financial risks as applies

Manage or minimise each one, large or small

· Routinely monitor and re-evaluate significant risks as the project continues

Identify operational risk and external market base risks as well.

Keep all project stakeholders informed and up-to-date

Issue performance reports, status changes, and other project documents

Send weekly email to each shareholder and updated reports through mail on fortnightly.

Forecasting costs

Delivering on time and on budget is the expectation.

Include extra funds in the budget

Adopt rationale use of resources by adoption TQM or any other cost saving technique.

Activity 3D

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to complete and forward project reports as required to stakeholders and undertake risk management as required to ensure project outcomes are met

Activity

In groups, or as directed by the instructor, and using a project from within your workplace conduct a risk assessment using the session notes and discussions just held.

It is required to address the following:

1. External/strategic context

The external market and environment base factors like change I political system and economy factors must take into account while deciding the project strategy and its scope.

2. Internal/organisational context

The capacity of project team members and availability of project resources also take into account.

3. Risk management context

Identify both possible financial ,operational & health and work base risks through a in depth manner.

Activity 3E

Estimated Time

30 Minutes

Objective

To provide you with an opportunity to achieve project deliverables

Activity

Discuss in groups, or as directed by the instructor, your experiences in the workplace on how project deliverables were:

Answers will vary depending on learner, their workplace and their experiences.

Achieved

By coordination, collaboration with open communication, guidelines and efforts the deliverables achieved.

Documented

Keep the detail of deliverables achieved in to business information system

Presented

Present the details through use of electronic means like PDF format, e-mail, power point presentation or through word base printed documents.

WORKPLACE PROJECT:

Development of information system

WORKPLACE PROJECT:

Development of a new product

WORKPLACE PROJECT:

Change in business security system

Activity 4A

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to finalise project

Activity

Complete and comment on the suggested forms reports and tables detailed in this session which are designed to “finalise a project” and make specific references to your experiences with:

· Completing financial record keeping

For this ,following steps are need to implement:

(i) Prepare budget by making estimations

(ii) Identify the actual possible cost volume

(iii) Seek suppliers to get material at best possible low cost

(iv) Compare actual cost with estimated cost

(v) Keep record of each invoice regarding purchase and sale

(vi) Presence of sale contract

(vii) Presence of signature of relevant authority over each cheque issues

(viii) Presence of business valid bank statements

· Assign staff involved in project to other roles etc. And obtain any necessary sign offs

There will be team of 8 team members with one team manager.

The team member will assign various duties as per the experience, skills and education level hold by them.

· Complete project documentation

To complete the project documentation ,presence f below mentioned documents is compulsory:

(i) Project business case

(ii) Project charter

(iii) RACI Matrix

(iv) WBS

(v) Risk log

(vi) Project Communication Plan

(vii) Project Schedule

Activity 5A

Estimated Time

40 Minutes

Objective

To provide you with an opportunity to review the project.

Activity

Give an example of a workplace project and explain the process you would follow to review its effectiveness and success.

List the tools and techniques you would use to do this.

To review the success and effectiveness of the project ,below mentioned tools and techniques can be use:

Through survey ad observations ,the performance can evaluate.

Project

Estimated Time

To be done over a 6-week period. 10-20 hours depending on the project chosen.

Activity

This project is to be done individually outside of class time.

Identify a project that you can realistically undertake over the next 6 weeks. Ideally it will be relevant to your workplace, but if this is not suitable, talk to your trainer about options for projects you can carry out within your family, club or community.

You will need to carry out all the planning for your project, conduct the project and then review and report on your project. Use the templates given in the learner guide and workbook, or research or create templates of your own. You will also need to give a short (5-10 mins) presentation to your class after the completion of the project.

Suitable examples of a project can include:

· Researching, developing and implementing a new policy

· Purchasing a major piece of equipment

· Holding an event, such as a staff function, workshop, information stall or social event

· Implementing new computer software

· Hosting a fundraising event

· Implementing a new procedure

· Introducing a new service or product

· Running a competition

· Carrying out a marketing activity

· Carrying out an office refurbishment

Define this project, by explaining its purpose and intended outcomes. Describe how it aligns with the organisation’s objectives.

Identify the stakeholders.

Develop a project plan.

Explain what resources you will need and why. Include human resources such as staff, volunteers or external subject matter experts.

Describe who you have consulted, how they were involved and how their views were taken into account.

Create and explain the budget. Keep financial records of your project.

Create a risk management plan, identifying potential risks and how they can be overcome.

Seek authority to implement your plan. Who did you ask and why?

Implement the project, taking note of any problems or difficulties that arise.

Explain how you provided support for the members of your project team.

Monitor the project. Explain how you monitored the project and how you ensured it stayed on track and difficulties were overcome.

Finalise the project, explaining what records you kept. Include samples of these records.

Review the project. Was it successful? How did you measure success?

Explain what project management tools you used.

Involve your team members in the review, seek and document their feedback.

Describe things you would do differently next time.

Prepare and present a short (5-10 mins) report to your class.

Major Activity

Estimated Time

60 – 120 Minutes

Objective

To provide you with an opportunity to demonstrate your knowledge of the entire unit.

Activity

This is a major activity – you should let the learners know whether they will complete it during class or in their own time.

They must individually answer the following questions in full to show their competency of each element:

1. Define project

The project is all about development of a new information safety system.

2. Develop project plan

The project is mainly focus to shift from traditional data security measures to ICloud base system. For this, a team of 10 to 12 team members will require which can complete task within 25 working days and can train others about how to use the new system , it benefits and importance as well.

3. Administer and monitor project

To continuously evaluate performance through surveys, observation and use of 360 degree feedback technique can help in this regard.

4. Finalise project

After analysing scope of project and its administration technique, the project will execute by all means.

5. Review project.

Review of project will help to identify the extent of gap present among the outcomes of the project

1) Why is project scope important?

Through this, the context of project, its limitations and possible outcome and its effects can evaluate easily.

2) Why do you need to define project stakeholders?

Through this, it can highlight about who are highly concerned with the outcome of the project.

3) Why is delegating authority important in a project?

Through this, the extent of accountability can highlight and identify easily.

4) Why do you need to recognise the limits of your role?

Through this ,the scope ,duties and restrictions present with a specific job role can understand easily.

5) Why do you need to understand the purpose of this project in the context of the organisation’s objectives?

Through this ,the extent of alignment among project purpose and organization subjective can identify easily. This can provide a basic understanding and guideline about what to do.

6) Why do you need to determine available resources?

Through this ,the extent of input and cost required for a project can identify. This input can compare with output of project to decide either project work successful or not.

7) Why do you need to keep within the project parameters?

To evaluate the project performance easily.

8) Why do you need to use project management tools?

To identify either the project team is going accurately or with in direction or not.

9) Why do you need to be aware of risks?

To adopt a pro active approach or plan to avoid risk ,awareness of risk is important.

10) Why do you need to take your team’s views into account?

To bring innovation, creativity and to increase the involvement of team members ,it is important to take team’s views.

11) Why do team members need to be clear about their roles?

To avoid any future ambiguity .

12) Why do you need to support team members?

To encourage them and motivate them ,it is important to support them.

13) Why is record keeping important?

Such record keeping help to make evidences which can work in future for legal disputes and for guidance as well.

14) Why do you need to monitor project expenditure?

To identify efficiency and activity of project team.

15) Why might project stakeholders require copies of reports?

To make a better understanding

16) Why do you need to achieve project deliverables?

To achieve project goals and objectives.

17) Why do you need to check records for accuracy?

To avoid any mistake and future miss lead.

18) Why is post-project staff transition important?

For learning through a project experience and to give feedback over performance in team ,it is important.

19) Why is involving team members in project reviews important?

To bring more creativity ,to complete task on time and to adopt and practice high efficiency and productivity ,the involvement of entire project team member’s review I important.

20) Why is documenting lessons learned a good practice?

Through this ,a in depth and pro long understanding can be made easily which help in future and improve he knowledge level.

Competency record to be completed by assessor

This should be used by the trainer/assessor to document the learner’s skills, knowledge and performance as relevant to the overall unit. Indicate in the table below if the learner is deemed competent or not yet competent for the unit or if reassessment is required.

Learner’s name

Assessor’s name

Unit of Competence

(Code and Title)

Date(s) of assessment

Has the learner completed all required assessments to a satisfactory standard?

Yes No

(Please circle)

Has sufficient evidence and information been provided by the learner to prove their competency across the entire unit?

Yes No

(Please circle)

The learner has been assessed as competent in the elements and performance criteria and the evidence has been presented as:

Authentic

Yes No

(Please circle)

Valid

Yes No

(Please circle)

Reliable

Yes No

(Please circle)

Current

Yes No

(Please circle)

Sufficient

Yes No

(Please circle)

Learner is deemed:

Not yet competent

Competent

If not yet competent, date for re-assessment:

Comments from trainer/assessor:

Learner’s signature

Assessor’s signature

MSA Training and Professional Development Phone: 03 9905 3180

Room 159, 21 Chancellors Walk Website: monashshortcourses.com

Monash University Clayton, Vic 3800

BSBPMG522 V2 17.01.2019

BSBPMG522

Undertake project work

Lea

rner Workbook

BSBPMG522

Undertake project work

Learner Workbook