Bloom Décor Company Project Requirements
Anthony Bahlman
Bloom Decor Company Project Requirements
Requirements
|
REQUIREMENTS |
PHASE OF THE PROJECT |
RESPONSIBLE PARTY |
DURATION |
|
Planning the requirements of the new facility considering the location, spacing, and the company's short-term and long-term goals (Müller, Drouin, & Sankaran, 2019). |
planning |
Project managers |
One week |
|
Determining the requirements of each department (Müller, Drouin, & Sankaran, 2019). |
planning |
Human resource department |
One week |
|
Communicating the planned move to employees and seeking their suggestions (Müller, Drouin, & Sankaran, 2019). |
planning |
Human resource |
Two weeks |
|
Assessing operational costs associated with relocating to the new location (Müller, Drouin, & Sankaran, 2019). |
planning |
Project leader |
One week |
|
Determining modification cost, logistic cost, the cost of branding the new location, the cost of furnishing the new location, and effecting the refurbishment (Müller, Drouin, & Sankaran, 2019). |
Initiating |
Project manager, directors & head of finance |
One month |
|
Communicating the planned move to the current landlord (Müller, Drouin, & Sankaran, 2019). |
initiating |
Administration department |
Two months |
|
Scheduling relocation with vendors such as IT support company, the telecommunication company, power back up company, signage, and branding company (Müller, Drouin, & Sankaran, 2019). |
initiating |
Administration department |
One month |
|
Moving out |
Completion |
Project manager |
One week |
|
Communicating to customers (Müller, Drouin, & Sankaran, 2019). |
completion |
Customer service department |
Two days |
|
Grand opening |
completion |
Project manager, company directors |
One day |
|
Hiring new staff, purchasing additional inventory, and continuing with operations |
Completion |
Human resource department |
One week |
Risk Assessment
|
Risk |
Potential of the risk occurring |
Level of Impact |
How the risk can be mitigated |
|
Customer service failure |
high |
High may result in loss of business |
Choosing an ideal location accessible to the available clients and potential market. Adequately training the newly recruited staff (Ou-Yang & Chen, 2017). |
|
Damages to the company equipment or loss of equipment |
high |
High – may result to slow customer service and slow other business operation processes. |
Hiring the services of a reputable moving company. Labeling all the fragile company equipment. Tagging assets to prevent stealing Ensuring company assets during the transfer (Ou-Yang & Chen, 2017). |
|
Destruction of customer assets |
high |
high |
Delivering all the décor materials already bought by customers before moving out (Ou-Yang & Chen, 2017). |
|
Communication and IT infrastructures not functioning properly on the first-day |
medium |
High- paralyzed operations |
Having all the communication and IT equipment tested a week before commissioning the new location. The vending companies should a checklist to ensure everything has been properly installed (Ou-Yang & Chen, 2017). |
|
Important files and records missing on the first day of the relocation |
Medium |
medium |
Moving the cabinets as a whole with the files inside without separating them. Labeling everything before relocating for proper unpackaging (Ou-Yang & Chen, 2017). |
|
Stress for employees |
low |
Low. Stress for employees planning the movements, stress of adapting to a new environment |
Ensuring that every employee is involved in reducing the pressure on few employees. Creating a conducive atmosphere to reduces work pressure with the fast two weeks (Ou-Yang & Chen, 2017). |
Project cost breakdown sheet
|
Requirement |
particular |
cost |
|
Modification and partitioning cost |
labor |
$ 4,250 |
|
Modification material cost |
materials |
$ 24,000 |
|
Branding cost |
Materials & labor |
$ 1,200 |
|
vendor charges for relocating outsourced services |
Service charge |
$ 2,200 |
|
Local government operation license |
License fee |
$ 800 |
|
Logistic cost |
Logistic cost |
$3,500 |
|
Opening ceremony cost |
Food & beverages |
$ 900 |
|
Inventory cost |
Cost of purchasing new inventory |
$12,000 |
|
Furniture |
Purchasing new furniture |
$ 1,400 |
|
Hiring new staff (Ou-Yang & Chen, 2017). |
Hiring staff |
$ 1, 200 |
|
Total |
|
$ 51,450 |
References
Müller, R., Drouin, N., & Sankaran, S. (2019). Modeling organizational project
management. Project Management Journal, 50(4), 499-513.
Ou-Yang, C., & Chen, W. L. (2017). Applying a risk assessment approach for cost analysis and
decision-making: a case study for a basic design engineering project. Journal of the Chinese Institute of Engineers, 40(5), 378-390.