Assignment for Class
MPS -Approved
| BA 357 Work Assignment 2 - Worksheet 1: MPS Approved plan | ||||||||||||||
| Item: A | Clodhopper (Fall2010) | Lot Size Rule: | FOQ 2500 | |||||||||||
| Lead Time: | 1 week | |||||||||||||
| Safety Stock Level: | 1500 | |||||||||||||
| Current Inventory: | 5500 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Forecast | 450 | 450 | 450 | 450 | 600 | 600 | 600 | 600 | 2233 | 2232 | 2233 | 2232 | ||
| Customer Orders Booked | 150 | 350 | 500 | 600 | 200 | 1000 | 2500 | 2000 | ||||||
| Projected On-Hand Inventory | 5050 | 4600 | 4100 | 3500 | 2900 | 2300 | 3800 | 3200 | 3467 | 3467 | 3734 | 4002 | ||
| MPS Scheduled Receipts | ||||||||||||||
| MPS Quantity | 2500 | 2500 | 2500 | 2500 | 2500 | |||||||||
| MPS Start | 2500 | 2500 | 2500 | 2500 | 2500 | |||||||||
| Available to Promise | 3700 | 1500 | 2500 | 0 | 500 | 2500 | ||||||||
| Item: B | Clodbuster (Fall2010) | Lot Size Rule: | FOQ 1000 | |||||||||||
| Lead Time: | 1 week | |||||||||||||
| Safety Stock Level: | 750 | |||||||||||||
| Current Inventory: | 4000 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Forecast | 300 | 300 | 300 | 300 | 400 | 400 | 400 | 400 | 943 | 942 | 943 | 942 | ||
| Customer Orders Booked | 200 | 450 | 50 | 900 | 3000 | |||||||||
| Projected On-Hand Inventory | 3700 | 3400 | 2950 | 2650 | 2250 | 1350 | 950 | 1550 | 1550 | 1608 | 1665 | 1723 | ||
| MPS Scheduled Receipts | ||||||||||||||
| MPS Quantity | 1000 | 3000 | 1000 | 1000 | 1000 | |||||||||
| MPS Start | 1000 | 3000 | 1000 | 1000 | 1000 | |||||||||
| Available to Promise | 2400 | 1000 | 0 | 1000 | 1000 | 1000 |
BOMs
| BA 357 Work Assignment 2 - Worksheet 2: Bill of Materials Data | |||||||
| ClodHopper BOM (Product A) | |||||||
| Name | Quantity | Assembly Time | Lead Time | ||||
| A | ClodHopper | 1 | 1 week | ||||
| C | Handle Bar Assembly | 1 | 2 weeks | ||||
| D | Steel Tubing 1" dia | 10 feet | 3 weeks | ||||
| E | Control cable | 5 feet | 2 weeks | ||||
| F | Control lever assembly | 1 | 1 week | ||||
| G | Grips | 2 | 1 week | ||||
| H | Powerhead assembly | 1 | 1 week | ||||
| I | Gearbox assembly | 1 | 1 week | ||||
| J | Engine (Standard) | 1 | 2 weeks | ||||
| K | Tiller blade unit | 1 | 1 week | ||||
| M | Instruction Manual | 1 | 4 weeks | ||||
| ClodBuster BOM (Product B) | |||||||
| Name | Quantity | Assembly Time | Lead Time | ||||
| B | ClodBuster | 1 | 1 week | ||||
| C | Handle Bar Assembly | 1 | 2 weeks | ||||
| D | Steel Tubing 1" dia | 10 feet | 3 weeks | ||||
| E | Control cable | 5 feet | 2 weeks | ||||
| F | Control lever assembly | 1 | 1 week | ||||
| G | Grips | 2 | 1 week | ||||
| P | HD Powerhead assembly | 1 | 1 week | ||||
| I | Gearbox assembly | 1 | 1 week | ||||
| L | Engine (Heavy Duty) | 1 | 3 weeks | ||||
| N | HD Tiller Unit | 1 | 2 weeks | ||||
| M | Instruction Manual | 1 | 4 weeks |
Inventory Records
| BA 357 Work Assignment 2 - Worksheet 3: Inventory Records and Lot-Sizing Rules | |||||||||
| Record Date: | 31-Dec-09 | ||||||||
| Item | Name | Current Inventory On-Hand | Lot-Size Rule | Lot Size | Lead or Assembly Time | Desired Safety Stock Level | Units | ||
| A | ClodHopper | 5500 | FOQ | 2500 | 1 week | 1500 | |||
| B | ClodBuster | 4000 | FOQ | 1000 | 1 week | 750 | |||
| C | Handle Bar Assembly | 3100 | L4L | 2 weeks | 1000 | ||||
| D | Steel Tubing 1" dia | 50,000 | POQ Period = 4 weeks | 3 weeks | 20,000 | feet | |||
| E | Control cable | 5,000 | FOQ | 20,000 | 2 weeks | 10,000 | feet | ||
| F | Control lever assembly | 2500 | L4L | 1 week | |||||
| G | Grips | 4000 | L4L | 1 week | |||||
| H | Powerhead assembly | 700 | FOQ | 4000 | 1 week | ||||
| I | Gearbox assembly | 650 | FOQ | 5000 | 1 week | 750 | |||
| J | Engine (Standard) | 500 | FOQ | 2500 | 2 weeks | 750 | |||
| K | Tiller blade unit | 850 | POQ Period = 2 weeks | 1 week | 750 | ||||
| L | Engine (Heavy Duty) | 450 | FOQ | 1000 | 3 weeks | 500 | |||
| M | Instruction Manual | 6000 | FOQ | 10,000 | 4 weeks | 2500 | |||
| N | HD Tiller Unit | 1250 | POQ Period = 3 weeks | 2 weeks | 500 | ||||
| P | HD Powerhead assembly | 900 | FOQ | 2000 | 1 week |
Scheduled Receipts
| BA 357 Work Assignment 2 - Worksheet 4: Scheduled Receipts | |||||||||||||
| Note: These are purchase order and production commitments scheduled in 2009 that are already scheduled for completion in 2010. The sizes of the orders or production lots are listed by week of scheduled delivery. Include these quantities in "Projected on-hand inventory" - do not include them in "Planned order releases." | |||||||||||||
| Item | Name | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 |
| A | ClodHopper | ||||||||||||
| B | ClodBuster | ||||||||||||
| C | Handle Bar Assembly | ||||||||||||
| D | Steel Tubing 1" dia (feet) | 100,000 | |||||||||||
| E | Control cable (feet) | 20,000 | 20,000 | ||||||||||
| F | Control lever assembly | ||||||||||||
| G | Grips | ||||||||||||
| H | Powerhead assembly | 4000 | |||||||||||
| I | Gearbox assembly | 5000 | |||||||||||
| J | Engine (Standard) | 2500 | 2500 | 2500 | 2500 | ||||||||
| K | Tiller blade unit | ||||||||||||
| L | Engine (Heavy Duty) | 1000 | 1000 | 1000 | 1000 | 1000 | 1000 | ||||||
| M | Instruction Manual | 10,000 | |||||||||||
| N | HD Tiller Unit | ||||||||||||
| P | HD Powerhead assembly | 2000 |
MRP Form - Results
| BA 357 Work Assignment 2 - Worksheet 5: MRP Form | ||||||||||||||
| Item: C | Handle Bar Assembly | Lot Size Rule: | L4L | |||||||||||
| Lead Time: | 2 weeks | |||||||||||||
| Safety Stock Level: | 1000 | |||||||||||||
| Current Inventory: | 3100 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases | ||||||||||||||
| Item: E | Control Cable | Lot Size Rule: | FOQ 20,000 | |||||||||||
| Lead Time: | 2 weeks | |||||||||||||
| Safety Stock Level: | 10,000 | |||||||||||||
| Current Inventory: | 5,000 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases | ||||||||||||||
| Item: H | Powerhead Assembly | Lot Size Rule: | FOQ 4,000 | |||||||||||
| Lead Time: | 1 week | |||||||||||||
| Safety Stock Level: | 0 | |||||||||||||
| Current Inventory: | 700 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases | ||||||||||||||
| Item: K | Tiller Blade Unit | Lot Size Rule: | POQ 2 weeks | |||||||||||
| Lead Time: | 1 week | |||||||||||||
| Safety Stock Level: | 750 | |||||||||||||
| Current Inventory: | 850 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases | ||||||||||||||
| Item: P | HD Powerhead Assembly | Lot Size Rule: | FOQ 2,000 | |||||||||||
| Lead Time: | 1 week | |||||||||||||
| Safety Stock Level: | 0 | |||||||||||||
| Current Inventory: | 900 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases | ||||||||||||||
| Item: L | Engine (Heavy Duty) | Lot Size Rule: | FOQ 1,000 | |||||||||||
| Lead Time: | 3 weeks | |||||||||||||
| Safety Stock Level: | 500 | |||||||||||||
| Current Inventory: | 450 | |||||||||||||
| Jan 2010 | Feb 2010 | Mar 2010 | ||||||||||||
| Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | |||
| Gross Requirements | ||||||||||||||
| Scheduled Receipts | ||||||||||||||
| Projected On-Hand Inventory | ||||||||||||||
| Planned Receipts | ||||||||||||||
| Planned Order Releases |