| Building Bear Workshop Project Schedule |
| Activity | Start Date | Finish Date | Number of Days |
| Defining Contents | 1-Mar-20 | 1-May-20 | 61 |
| Store Identification | 1-Mar-20 | 6-Mar-20 | 5 |
| Re-funishing the Identified Stores | 7-Mar-20 | 10-Mar-20 | 3 |
| Streamlining the Stores Management | 11-Mar-20 | 16-Mar-20 | 5 |
| Selection of New Branch Managers | 17-Mar-20 | 24-Mar-20 | 7 |
| Identification of Products in @ Store | 25-Mar-20 | 30-Mar-20 | 5 |
| Re-arranging the existing products | 31-Mar-20 | 5-Apr-20 | 5 |
| Product Listing | 6-Apr-20 | 11-Apr-20 | 5 |
| Product Search | 12-Apr-20 | 18-Apr-20 | 6 |
| Collection of product data | 18-Apr-20 | 22-Apr-20 | 4 |
| Advertising | 23-Apr-20 | 26-Apr-20 | 3 |
| Discounts Formulation | 27-Apr-20 | 1-May-20 | 4 |
| Programming | 2-May-20 | 15-Jun-20 | 44 |
| Prepairing Layout | 2-May-20 | 9-May-20 | 7 |
| Preparing Links | 10-May-20 | 18-May-20 | 8 |
| Shopping Carts | 19-May-20 | 25-May-20 | 6 |
| Adding Carts | 26-May-20 | 30-May-20 | 4 |
| Customer Purchasing the Bears | 31-May-20 | 5-Jun-20 | 5 |
| Customers Making Payments for the Bears | 6-Jun-20 | 9-Jun-20 | 3 |
| Thanking the Customers | 10-Jun-20 | 15-Jun-20 | 5 |
| System Testing | 16-Jun-20 | 16-Jul-20 | 30 |
| Test Plan Development | 16-Jun-20 | 20-Jun-20 | 4 |
| Unit Testing | 21-Jun-20 | 27-Jun-20 | 6 |
| System and Integration Testing | 28-Jun-20 | 3-Jul-20 | 5 |
| Functional Testing | 4-Jul-20 | 6-Jul-20 | 2 |
| Employees Trainng | 7-Jul-20 | 10-Jul-20 | 3 |
| System Launching | 11-Jul-20 | 16-Jul-20 | 5 |
| Documentation | 17-Jul-20 | 1-Aug-20 | 15 |
| F.A.Q | 17-Jul-20 | 20-Jul-20 | 3 |
| Internal Documentation | 21-Jul-20 | 25-Jul-20 | 4 |
| External Documentation | 26-Jul-20 | 1-Aug-20 | 6 |