Project Management 1
Plan for delivery schedule & cost of a Project:
For a company engaged in design and delivery of a Audio Visual installation system at University of Maryland, the following tasks (that are Not in a proper order), with corresponding duration and cost for each task are envisaged for the plan. Please fill the attached table by listing all the necessary tasks involved in proper sequence , showing start & finish of each task and associated costs, then find the total project proposed cost/value/price to client by including 12% for overhead, and 15% for profits:
Locate and survey the location 1 weeks $3,000
Approvals 1 week ------
Select Your Sub-contractors 1 week $3000
System Design details and develop plan 16 weeks $48,000
Install all necessary wiring lines 4 weeks $25,000
Install Security System 1 week scattered $18,000
Build Control/head Room 4 weeks $60,000
Install Furniture & Mics 2 weeks $10,000
Install Airconditiong System 3 weeks $35,000
Order all necessary equipment & Furniture 1 weeks $45,000
Install All Equipment in Control Room 2 weeks $12,000
Flooring 1 week $15,000
Carpeting & Clean up 1 week $14,000
Painting 1 week $15,000