Project Management Plan

profileiamgroot_1992
Assignment3.docx

Chapter 4 – Section 3 of PMP Template Plan

3. Change Management (Chapter 4)

3.1 Change Management Process

Change management entails thoughtful planning and sensitive implementation, and above all, consultation with, and involvement of, the people affected by the changes. Changes made to the project at any timeline are raised using a request for change is requested before change is initiated and the change request is handled by the implementation team to determine if the change impacts the project risking the timeline, resource, structure or any kind of impact. Any change requires a Quality Assurance decision to approve the change or reject. If the change request is denied the change request is rejected.

3.2 Change Control Process Flowchart

3.3 Change Request Form

Change Request Form

Change Request Number

01

Initiator

Bosch

Brief Description of Request

Editing Workflow configuration change

Submission Request Date

02/04/2017

Request Approve Date

02/05/2017

Reason for Change

The document check-out option is not open and as per the initial configuration request the feature is added for employee using a document at remote locations or exporting to other electronic document managmenet system

Approval Signature

Signed

Date Signed

02/05/2017

Change Request Form

Change Request Number

02

Initiator

Stephen

Brief Description of Request

Security Access change

Submission Request Date

02/04/2017

Request Approve Date

02/05/2017

Reason for Change

System access for Business administrator is requested for creating users in the system and remove access for system owner

Approval Signature

Signed

Date Signed

02/05/2017

3.4 Change Log

Change No.

Type

Description

Initiator

Submission Request Date

Status

Submission Approved Date

Comments

01

Configuration

Editing Workflow configuration change

Bosch

02/04/2017

Approved

02/05/2017

None

02

Configuration

Security Access change

Stephen

02/04/2017

Approved

02/05/2017

None

References:

http://www.businessballs.com/changemanagement.htm