Individual assignment 3

profilePeterok
Assignment203.xlsx

Planned Value

May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16
Activity A $4,000
Activity B $2,000
Activity C $5,000 $5,000
Activity D $4,000
Activity E $8,000
Activity F $4,000
Activity G $2,000 $4,000
Activity H $8,000
Activity I $2,000
Activity J $12,000
Activity K $6,000
Activity L $5,000
Activity M $7,000
Activity N $9,000
Activity O $7,000 $6,000
PV $4,000 $7,000
Cumulative PV $4,000 $11,000

Actual Cost

May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16
Activity A $4,000
Activity B $3,000
Activity C $6,000 $4,000 $2,000
Activity D $3,000 $2,000
Activity E $6,000 $3,000
Activity F $1,000 $3,000
Activity G $3,000 $3,000
Activity H $7,000
Activity I $2,000
Activity J $2,000
Activity K
Activity L
Activity M
Activity N
Activity O
AC $4,000 $9,000
Cumulative AC $4,000 $13,000

Completion

May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16
Activity A 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Activity B 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Activity C 50% 75% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Activity D 75% 100% 100% 100% 100% 100% 100% 100% 100%
Activity E 50% 100% 100% 100% 100% 100% 100%
Activity F 25% 100% 100% 100% 100% 100%
Activity G 50% 100% 100% 100% 100% 100%
Activity H 100% 100% 100% 100%
Activity I 100% 100% 100% 100%
Activity J 25%
Activity K
Activity L
Activity M
Activity N
Activity O
EV $4,000 $7,000
Cumulative EV $4,000 $11,000