A) Draw the network diagram? B) How many paths are in the network, and what are they? C) What is the critical path and its duration? D) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS,
Using the information in next Table to answer the below questions:
A) Draw the network diagram?
B) How many paths are in the network, and what are they?
C) What is the critical path and its duration?
D) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF ?
|
Task |
Duration (Days) |
Predecessor/s |
|
A |
5 |
- |
|
B |
6 |
- |
|
C |
7 |
- |
|
D |
8 |
- |
|
F |
1 |
A |
|
G |
2 |
B |
|
H |
3 |
C |
|
I |
4 |
D |
|
J |
5 |
F,G,H |
|
K |
1 |
I |
|
L |
2 |
J |
|
M |
1 |
K |
|
N |
10 |
L,M |