Construction Management W 1
Week 1 Assignment 1
Construction Management
Assignment 1
Suggested format: Times New Roman 12 points, single spaced, 1” margin all around, APA style
for references
Note: All assignments will be checked for plagiarism using SafeAssign. The similarity index
should not be greater than 35% on the report. You should always provide references at the end.
LEARNING OBJECTIVE:
After successfully completing this assignment, students will be able to:
• Define various schedule activities and assign reasonable durations to the
activities
• Differentiate between planning and scheduling processes
Q1: Please arrange the following activities for a residential project in order which the
activities should be completed. Some of the activities can be started simultaneously, if
needed. 40 Points
Install concrete stairway
Frame interior walls
Install gas lines
Install electrical outlets and switches
Install shingles
Install roofing trusses
Install electrical fixtures
Install roof vents
Painting interiors
Carpeting
Final inspections
Project completion
Q2. Please identify various construction activities in the following project and prepare a
bar chart manually or using excel/or MS Project. 60 Points
You have been asked by your boss to create a first draft bar chart that will be used in a
presentation for a negotiated contract for the construction of a warehouse. The owner has
Week 1 Assignment 1
furnished the following brief scope of work. Fill in other details as needed by making
assumptions. The detailed plans will be developed later. The project must be finished within two
months (calendar days) or less.
The warehouse is 40 ×120 feet, with a concrete footing and floor slab. It is a steel structure with
the sections between the structural posts filled in with metal studs. It has exterior insulation
finish system (EIFS) exterior wall coverings. The roofing material is a single-ply roof mem-
brane. The roof is insulated with fiberglass insulation on the inside, with a heavy plastic
protection on the bottom side of the insulation. The exterior walls will be insulated with
fiberglass batts. The only interior partitions are for a small office and restrooms. The inside wall
coverings are drywall that will be finished and painted. The heating system consists of natural
gas unit heaters suspended from the ceiling. There is no cooling system. There are two large
overhead doors and two man doors for access to the building. There are also some landscaping
and paved parking areas around the building.