BUILDING CONSTRUCTION MANAGEMENT And CONTROL
|
University of Business and Technology College of Engineering
Fall Semester 2021 Arch 462 – BUILDING CONSTRUCTION MANAGEMENT And CONTROL
Assignment (1) (20 Marks)
|
Dr. Jawad Alsuliman
Student Name: ----------------------------------------------
Student ID: ---------------
Question 1: (4 Marks)
· Draw the following network using Precedence Diagram Method and determine the critical path(s); PDMin; Total Float for each activity considering the following data:
|
Activity |
Depends on |
Duration (days) |
|
A |
-- |
6 |
|
B |
-- |
5 |
|
C |
-- |
6 |
|
D |
A |
5 |
|
E |
A,B |
8 |
|
F |
B |
3 |
|
G |
E |
6 |
|
H |
G |
8 |
|
I |
F |
9 |
|
J |
C,E |
7 |
|
K |
J,H |
6 |
Question 2: (4 Marks)
· Draw the following network using Precedence Diagram Method and determine the PDMin; Total Float; and draw the Bar-chart considering the contract duration = 30 days with the following data:
|
Activity |
Depends on |
Duration (days) |
|
A |
-- |
3 |
|
B |
-- |
4 |
|
C |
A |
3 |
|
D |
A |
4 |
|
E |
B |
8 |
|
F |
A, B |
3 |
|
G |
B |
6 |
|
H |
D, G |
7 |
|
I |
F |
2 |
|
J |
H, I |
10 |
Question 3: (4 Marks)
The following table illustrates the activities of a small project:
|
Activity |
Duration (Days) |
Depends On |
|
A |
10 |
--- |
|
B |
3 |
A & F |
|
C |
7 |
G |
|
E |
5 |
A & G |
|
F |
11 |
--- |
|
G |
10 |
J |
|
H |
9 |
E & I & B |
|
I |
4 |
C |
|
J |
6 |
--- |
|
K |
5 |
B |
It is required to:
· Draw Activity On Node “AON” Network;
· Calculate ES, EF, LS, LF for each activity;
· Highlight and Write the Critical Path;
· Find activity total float;
· Find activity free float.
Question 4: (4 Marks)
|
Activity |
Depend On |
Duration |
|
C |
-- |
6 |
|
A |
-- |
7 |
|
B |
-- |
8 |
|
D |
A & B |
9 |
|
G |
C |
6 |
|
E |
C |
5 |
|
H |
B & C |
7 |
|
F |
E & H |
10 |
Given a small project as shown in table:
It is required to:
· Draw (PDM) network;
· Calculate activity times;
· Find project duration;
· Locate critical path;
· Find total float of each activity;
· Find free float of each activity;
· Convert to (ADM) network.
Question 5: (4 Marks)
Given a list of activities for a small project as shown in the following table:
|
Activity |
Duration (days) |
Early Start |
Early Finish |
Late Start |
Late Finish |
Total Float |
Free Float |
|
A |
|
0 |
5 |
|
|
0 |
|
|
B |
|
5 |
11 |
|
|
0 |
|
|
C |
|
11 |
13 |
|
|
6 |
|
|
D |
|
0 |
4 |
|
|
1 |
|
|
E |
|
4 |
7 |
|
|
4 |
|
|
F |
|
11 |
19 |
|
|
0 |
|
|
G |
|
19 |
20 |
|
|
0 |
|
It is required to:
· Complete the missing data in the table; and
· Draw The Activity-On-Node network, assuming that any relationship you need is FS=0.