BUILDING CONSTRUCTION MANAGEMENT And CONTROL

profileSadeen Alharbi
Assignment1.docx

University of Business and Technology

College of Engineering

Fall Semester 2021

Arch 462 – BUILDING CONSTRUCTION MANAGEMENT

And CONTROL

Assignment (1)

(20 Marks)

Dr. Jawad Alsuliman

Student Name: ----------------------------------------------

Student ID: ---------------

Question 1: (4 Marks)

· Draw the following network using Precedence Diagram Method and determine the critical path(s); PDMin; Total Float for each activity considering the following data:

Activity

Depends on

Duration (days)

A

--

6

B

--

5

C

--

6

D

A

5

E

A,B

8

F

B

3

G

E

6

H

G

8

I

F

9

J

C,E

7

K

J,H

6

Question 2: (4 Marks)

· Draw the following network using Precedence Diagram Method and determine the PDMin; Total Float; and draw the Bar-chart considering the contract duration = 30 days with the following data:

Activity

Depends on

Duration (days)

A

--

3

B

--

4

C

A

3

D

A

4

E

B

8

F

A, B

3

G

B

6

H

D, G

7

I

F

2

J

H, I

10

Question 3: (4 Marks)

The following table illustrates the activities of a small project:

Activity

Duration

(Days)

Depends On

A

10

---

B

3

A & F

C

7

G

E

5

A & G

F

11

---

G

10

J

H

9

E & I & B

I

4

C

J

6

---

K

5

B

It is required to:

· Draw Activity On Node “AON” Network;

· Calculate ES, EF, LS, LF for each activity;

· Highlight and Write the Critical Path;

· Find activity total float;

· Find activity free float.

Question 4: (4 Marks)

Activity

Depend On

Duration

C

--

6

A

--

7

B

--

8

D

A & B

9

G

C

6

E

C

5

H

B & C

7

F

E & H

10

Given a small project as shown in table:

It is required to:

· Draw (PDM) network;

· Calculate activity times;

· Find project duration;

· Locate critical path;

· Find total float of each activity;

· Find free float of each activity;

· Convert to (ADM) network.

Question 5: (4 Marks)

Given a list of activities for a small project as shown in the following table:

Activity

Duration (days)

Early Start

Early Finish

Late Start

Late Finish

Total Float

Free Float

A

0

5

0

B

5

11

0

C

11

13

6

D

0

4

1

E

4

7

4

F

11

19

0

G

19

20

0

It is required to:

· Complete the missing data in the table; and

· Draw The Activity-On-Node network, assuming that any relationship you need is FS=0.