Order 1328631: Project Management

profiletutorthammy
Assignment-3.pdf

Multi-Purpose Computer Lab

Facility for Ryerson University

Assignment #3 – Final Report

Team Name: Computing and Communications Team

Course: GMS450-011

Date Submitted: April 2, 2018

Member Name Student ID

Tasfeia Alli 500751520

Yogya Atwal 500747648

Tanvir Sra 500759144

Sama Hussain 500777719

Daniyal Khalid 500641397

Shazaan Amaan 500790600

Cynthia Pathmanathan 500706092

Avani Patel 500693703

Jatin Dhingra 500798777

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 2

Contents 1 Project Charter ................................................................................................................................. 3

1.1 Purpose ............................................................................................................................................ 3

1.2 Objectives ........................................................................................................................................ 4

1.3 Schedule ........................................................................................................................................... 4

1.4 Resource Requirements ................................................................................................................... 5

1.5 Stakeholders .................................................................................................................................... 6

1.6 Risks ................................................................................................................................................. 6

1.7 Evaluation Methods ......................................................................................................................... 6

2 Scope Statement and WBS .............................................................................................................. 7

2.1 Project Scope Statement ................................................................................................................. 7

2.2 Work Breakdown Structure (WBS) .................................................................................................. 8

3 Gantt Chart and Milestone Schedule ............................................................................................... 9

3.1 Gantt Chart ...................................................................................................................................... 9

3.2 Milestone Schedule ........................................................................................................................ 10

4 Project Budget ............................................................................................................................... 11

4.1 S-Curve ........................................................................................................................................... 11

4.2 Supporting estimates ..................................................................................................................... 12

5 Risk Assessment ............................................................................................................................. 14

5.1 Risk Management Plan .................................................................................................................. 14

5.1.1 Risk Threshold ................................................................................................................................ 14

5.1.2 Risk scoring .................................................................................................................................... 14

5.1.3 Risk Prioritization ........................................................................................................................... 14

5.1.4 Resources ....................................................................................................................................... 14

5.1.5 Categories ...................................................................................................................................... 15

5.1.6 Risk Register Template ................................................................................................................... 15

5.2 Risk Assessment ............................................................................................................................. 16

5.2.1 Risk Identification .......................................................................................................................... 16

5.2.2 Qualitative Analysis ........................................................................................................................ 17

5.2.3 Quantitative Analysis ..................................................................................................................... 17

5.2.4 Risk Response ................................................................................................................................. 18

5.2.5 Risk Register ................................................................................................................................... 19

Version Control ........................................................................................................................................... 21

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 3

1 Project Charter

1.1 Purpose

Ryerson University is striving towards providing an excellent infrastructure to students, through which they can promote

innovation and real world application knowledge, therefore students need hands-on experience with many sophisticated

software packages that are used in the workplace. The current computer labs are inefficient and there is a shortage in lab

space with even more demand forecasted in the near future.

We will be building a new multi-purpose computer lab as a first step in solving all the problems, fostering long-term

economic, social and environmental benefits.

 Computers in existing labs remain turned on while idling for extended periods of time, resulting in a waste of

power, associated with a financial cost and adverse impact on the environment. Furthermore, this will depreciate

the machines at a faster rate, reducing overall lifespan and increasing the frequency of replacement contributing to

the disposal of E-Waste. The new lab will consist of a high speed network and computers with high speed

hardware including an additional Solid State Drive (SSD) used to store the operating system, which enables

extremely fast boot time (≤ 20 sec) and login time (≤ 5 sec), which allows to turn off computers after use, as it

takes only a few seconds to start up, saving power and maximizing life span of equipment. This will enable

Ryerson to save on costs and improve the quality of service in a sustainable manner.

 Currently there is a shortage of lab space for conducting lab-based lectures, exams and workshops, for instance

Microsoft Excel training workshops have tight time slots, and exams are split into many batches leading to higher

costs, making control & coordination difficult. The new lab offers ample computing space for a vast range of

needs, including lab-based lectures, appointment based sessions with Teaching Assistants, individual or group

work usage. Some machines will be dedicated for group work during idle time, which will have customizable

hardware that allows to adjust fixtures accordingly to fit a small group.

 Ryerson offers students and faculty members free access to specialized software packages under a general license,

through a virtual platform, however the quality of interface, performance and efficiency are questionable till date,

the new lab will provide students the opportunity to work in groups or individually use software packages such as

SPSS, Auto Desk, SAS, and Ansys etc, with optimal performance. The new sophisticated machine hardware and

software are also focused on catering the needs of high level students specializing in graphic designing,

innovation, statistical applications, research and development for which Ryerson is a known university.

 Ryerson, as any other university has always had a problem on certain days or times when there is extra ordinary

volume of activity, which the servers fail to manage. Examples include, course intention periods and rolling out

results at a specific time. In this case our new lab is capable of transforming certain powerful computers into a

pool of computing power, which can be used to assist the main servers like a virtual server during those times,

which helps to manage the volume of activity effectively and efficiently, preventing bottleneck situations and user

inconvenience.

 The new lab will improve accessibility by approximately 50% compared to the existing labs. About 4

workstations will be dedicated for disabled users, equipped with perfect customizable ergonomics, including

adjustable fixtures, special hardware, peripherals and software features etc, providing a comfortable user

experience and achieving perfect satisfaction, valuing diversity at Ryerson University.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 4

1.2 Objectives

We will be building a compact energy efficient multi-purpose computer lab with ample computing space including cutting

edge technologies and comfortable ergonomics for individuals, groups of students and accessible services.

This project will help Ryerson to minimize financial costs and environmental impacts in the long-run through power-

efficiency and address capacity constraints. Quality of learning & Student satisfaction will be improved sustainably.

The project should be completed by September 3, 2018 to be functional for the fall 2018 semester, therefore we have a

critical schedule with no allowance for delays and minimal slack time. We will meet/exceed all agreed customer

requirements on a maximum budget of $360,000.

We will be clearly communicating the status of the project to our project sponsor after every deliverable is completed,

using a pro-active review approach to complete the lab effectively and successfully on time and budget.

1.3 Schedule

Milestone Schedule

Milestone Due Date

Analysis Complete (Design & Measurements) April 8, 2018

Documentations Complete April 16, 2018

Demolition Complete April 27, 2018

Remodeling Complete August 3, 2018

Fixtures, Fittings & Furniture Received August 6, 2018

Computers & Equipment Received August 13, 2018

Networking & Configurations Complete August 21, 2018

All Installations Complete August 23, 2018

Testing Complete August 30, 2018

Compliance Audit Complete September 3, 2018

Project Completed & Project Sponsor signs off September 4, 2018

Start Date: April 1, 2018

End Date: September 4, 2018

The project will be completed in about 156 days ≈ 5 Months.

Note: We have accounted for concurrent activities and lead times between activities.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 5

1.4 Resource Requirements

Resource Requirements & Summary Budget

Activities &

Resources Labour Required

Labour

($/Hr)

Cost of Material &

Equipment ($) Total Cost

Analysis 5hrs x 2 people x 7 days $15 $150 $1,200

Documentation 5hrs x 2 people x 7 days $15 $150 $1,200

Demolition 8hrs x 4 people x 10 days $14 $5,520 $10,000

Remodeling 8hrs x 5 people x 100 days $14 $94,000 $150,000

Fixtures & Furniture

(50*$300) - - - $15,000

Computers

(50*$2000) - - - $100,000

Assistive Stations

(4*$4000) - - - $16,000

Projectors

(2*$4500) - - - $9,000

Networking 5hrs x 2 people x 3 days $20 $10,000 $10,600

Other Equipment &

Accessories - - - $15,000

Installations 7hrs x 3 people x 17 days $14 $502 $5,500

Testing 6hrs x 2 people x 6 days $15 $120 $1,200

Compliance Audit 3hrs x 2 people x 3 days $15 $30 $300

Fixed Cost - - - $5,000

Total $340,000

We are given a budget of $360,000. Estimated total cost is $340,000, indicating a potential surplus of $20,000, which we

are planning to allocate for risk management in case we need contingency funding in an emergency, to overcome adverse

situations. We are confident that we can complete the project on budget as we have use statistical techniques in

forecasting both opportunities and threats for budgeting and we will be using Earned Value Management (EVM)

techniques in an ongoing basis, to make sure we are always pro-active in detecting and correcting potential problems,

along with regularly communicating the status of the project to the sponsors will help us complete this project

successfully.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 6

1.5 Stakeholders

The key stakeholders are our project team members, facilities director (Sponsor), Ryerson’s senior management including

the Finance director, and our contractors/suppliers such as Bell, Samsung, Epson, Sony, HID, Microsoft, & IBM etc.

The project manager has authority to directly report and get approval from the Facilities director (Sponsor) and Finance

director. The project manager is responsible to lead the team and get the project completed on time, on budget and on

scope, the PM is accountable for any delays or risks to the senior management.

Project team member’s individual roles listed below:

Title Name

Project Manager Tasfeia

Communications Manager Tanvir Sra

Risk Manager Sama Hussain

HR & Scheduling Manager Yogya & Avani

Accounting & Finance Manager Daniyal & Shazaan

Operations Manager Jatin & Cynthia

1.6 Risks

Risk ID Risk

1 Delay in supply of computers & other equipment.

2 Risk of Injury on site

3 Adverse weather conditions can affect duration of renovation.

4 Platform mismatch, problems might arise integrating new technologies with older platforms.

5 Risk of price fluctuations

6 Hardware performance issues/defects

7 Theft of equipment, materials or accessories.

8 Intruders causing damage to property while project is in progress.

9 Minor scope changes requested by the client

10 Minor Software Bugs

The organization is very risk averse. We will be most concerned or give priority to risks that have a PI Score of 0.09 and

higher, we will keep an eye on risks with a score of 0.04 – 0.08 as a second priority and we will accept risks with a score

of 0.03 or less. This is because we have a very critical time line to complete the project and very minimal slack time.

1.7 Evaluation Methods

Project success is measured in terms of satisfying client’s scope requirements, at the pre-specified time and budget.

Project sponsors will be matching and checking off the acceptance criteria with actual performance, and if the scope is

satisfied it is the first criteria for success. Then the planned schedule and actual schedule will be matched, if there is no

any adverse variance, this criterion will be a success too. Finally the budgeted expenditure and actual spending will be

matched, if there is no any adverse variance, this criteria is successful too. Therefore the sponsor will be satisfied and we

consider the overall project to be successful.

The Facilities Management Director and Finance Director of Ryerson University are our sponsors and they will evaluate

the project at the end and sign off, once they are satisfied.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 7

2 Scope Statement and WBS

2.1 Project Scope Statement

Our project is aiming to solve problems power efficiency, computing power and space, accessibility, and capability of

resource pooling to support main servers during bottle neck situations. Increasing student satisfaction, productivity and

minimizing long term costs.

We have selected Samsung as our supplier of computers. The model to be used is Samsung ArtPC PULSE. It is powerful,

compact, durable, modular, stylish and eco-friendly. It has a Silver rating in Electronic Product Environmental

Assessment Tool (EPEAT) and Energy star certified. The modular design make it easier to upgrade hardware components

and expand the lifespan of the equipment.

Quantifiable Criteria include:

1. Cost: The project should be completed with a maximum budget of $360,000 or less.

2. Schedule: Important criterion, project should be completed by September 4th, 2018 to be functional in Fall 2018.

3. Scope and Quality: Equipment and materials should have exact same brands and specifications pre specified in

the acceptance criteria. Floor area should be a minimum of 3000 Square feet etc, actual performance should

adhere to the quantifiable requirements specified in acceptance criteria, for instance certification requirements

such as EPEAT and Energy Star etc. Total of 54 computers including assistive workstations.

Acceptance Criteria

 Floor area should be ≥ 3000 square feet, with one main entrance and 2 fire exits, should have some free space for

students to work on laptops and for future expansion of computers.

 The color scheme of the lab should follow the theme color scheme of Ryerson and be visually pleasant.

 4 Assistive workstations located near front entrance and a fire exit to ensure convenience & safety.

 50 Samsung ArtPC PULSE computers (Customized version)

Specifications:

 Intel Core i7 (8th Gen), 3.4Ghz-4Ghx (Turbo Boost), 8MB Cache, 16GB RAM (DDR4), 512GB

SSD+1TB HDD, NVIDIA 4GB (GTX 1050).

 Screen should be Samsung Quad HD (2560x1440), 24” Curved HDR Quantum Dot Display.

 Operating System: Windows 10 Professional 64 Bit, Boot time ≤ 20 Sec & Login time ≤ 5 Sec.

 Software Versions: All specialized software packages should be upgraded to the latest editions and be

compatible with 64 Bit platforms, to utilize hardware efficiently achieving greater performance.

 2 Sony 4K SXRD HDR projectors (4096x2160), 1500 Lumens, Screen size 60”- 300”.

 Sony speakers should be embedded to the roof, with minimal visibility.

 Epson laser printers and scanners should be used.

 Access Control systems should be from HID Global.

 Network speed should be ≥ 1Gbps from Bell Canada.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 8

Project Deliverables

These are the main requirements to be completed on time and budget for the successful completion of the project, from

Level 2 of WBS.

1. Analysis: Designing includes requirements & layout planning, and measurements taken. 2. Documentation: This includes preparation and submission of all necessary documents for this project. 3. Renovation: Includes demolition and remodeling of the lab, longest activity takes about 110 days critical. 4. Installation: This includes the purchase of all equipment & material, then complete installations. 5. Testing: This deliverable is complete when all components of the lab are tested and a report is prepared. 6. Compliance Audit: This includes an audit being conducted to make sure the lab is perfectly functional before the

project sponsors are invited to evaluate and sign off the project on September 4th, 2018.

All scope requirements stated and agreed will be satisfied to the best extent, in accordance with the acceptance criteria.

Project Exclusions

 We will not be responsible for any damage caused by the administrators due to misuse without reading user manuals and relevant information.

 We will not be responsible for any repair or maintenance.  Once the client approves the project by September 4th, 2018 we will not be responsible for any further changes or

adjustments.

 In case we have a budget surplus, we will not use the surplus fund for any improvements of the lab instead it will be refunded to the project sponsor.

 We are not responsible for exterior designing and appearance, as our scope is only focused on the interior design of the lab.

 We will not be responsible for the performance and reliability of third party software applications used.

2.2 Work Breakdown Structure (WBS)

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 9

3 Gantt Chart and Milestone Schedule

3.1 Gantt Chart

Tasks Start Date End Date Duration (Days) Predecessors

Analysis (1) 1-Apr-18 8-Apr-18 7 -

Designing (1.1) 1-Apr-18 6-Apr-18 5 -

Measurement (1.2) 6-Apr-18 8-Apr-18 2 1.1

Documentation (2) 9-Apr-18 16-Apr-18 7 1

Permits (2.1) 9-Apr-18 11-Apr-18 2 1

Design Documents (2.2) 11-Apr-18 12-Apr-18 1 2.1

Contractor Agreements (2.3) 12-Apr-18 15-Apr-18 3 2.2

Maintenance Documents (2.4) 15-Apr-18 16-Apr-18 1 2.3

Renovation (3) 17-Apr-18 5-Aug-18 110 2

Demolition (3.1) 17-Apr-18 27-Apr-18 10 2

Remodeling (3.2) 27-Apr-18 5-Aug-18 100 3.1

Installation (4) 6-Aug-18 23-Aug-18 17 3

Install - Fixtures & Furniture (4.1) 6-Aug-18 13-Aug-18 7 3

Install - Computers (4.2) 13-Aug-18 18-Aug-18 5 4.1

Networking (4.3) 18-Aug-18 21-Aug-18 3 4.2

Access Control System &Cameras (4.4) 21-Aug-18 23-Aug-18 2 4.3

Install - Other Equipment (4.5) 21-Aug-18 22-Aug-18 1 4.3

Testing (5) 24-Aug-18 30-Aug-18 6 4

Test - Hardware (5.1) 24-Aug-18 26-Aug-18 2 4

Test - Software (5.2) 26-Aug-18 28-Aug-18 2 5.1

Test - Network (5.3) 28-Aug-18 29-Aug-18 1 5.2

Prepare Testing Report (5.4) 29-Aug-18 30-Aug-18 1 5.3

Compliance Audit (6) 31-Aug-18 3-Sep-18 3 5

Conduct Audit (6.1) 31-Aug-18 2-Sep-18 2 5

Prepare Audit Report (6.2) 2-Sep-18 3-Sep-18 1 6.1

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 10

3.2 Milestone Schedule

Milestone Due Date

Analysis Complete (Design & Measurements) April 8, 2018

Documentations Complete April 16, 2018

Demolition Complete April 27, 2018

Remodeling Complete August 3, 2018

Fixtures, Fittings & Furniture Received August 6, 2018

Computers & Equipment Received August 13, 2018

Networking & Configurations Complete August 21, 2018

All Installations Complete August 23, 2018

Testing Complete August 30, 2018

Compliance Audit Complete September 3, 2018

Project Completed & Project Sponsor signs off September 4, 2018

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 11

4 Project Budget

4.1 S-Curve

5.20%

19.24%

32.83%

46.87%

99.90% 100.00%

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

April May June July August September

S-Curve

Period (Months)

C u

m u

la ti

ve P

ro gr

es s

(% )

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 12

4.2 Supporting estimates

Table 1: Work Package Estimates

Work Package Labour Required Labour

($/Hr)

Cost of Material &

Equipment ($) Fixed Cost Total Cost

Analysis 5hrs x 2 people x 7 days $15 $150 $50 $1,250

Documentation 5hrs x 2 people x 7 days $15 $150 $50 $1,250

Demolition 8hrs x 4 people x 10 days $14 $5,520 $550 $10,550

Remodeling 8hrs x 5 people x 100 days $14 $94,000 $4000 $154,000

Installation -

Fixtures &

Furniture

(50*$300)

- - $15,000 - $15,000

Computers

(50*$2000) - - $100,000 - $100,000

Assistive Stations

(4*$4000) - - $16,000 - $16,000

Projectors

(2*$4500) - - $9,000 - $9,000

Networking 5hrs x 2 people x 3 days $20 $10,000 $150 $10,750

Other Equipment &

Accessories - - $15,000 - $15,000

Installation Cost 7hrs x 3 people x 17 days $14 $502 $50 $5,550

Testing 6hrs x 2 people x 6 days $15 $120 $100 $1,300

Compliance Audit 3hrs x 2 people x 3 days $15 $30 $50 $350

Total $340,000

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 13

Table 2: Work Package Time Profile

Work Package April May June July August September Total

Analysis $1,250 - - - - - $1,250

Documentation $1,250 - - - - - $1,250

Demolition $10,550 - - - - - $10,550

Remodeling $4,620 $47,740 $46,200 $47,740 $7,700 - $154,000

Purchase & Installation - - - - $171,300 - $171,300

Testing - - - - $1,300 - $1,300

Compliance Audit - - - - - $350 $350

Cumulative Total $17,670 $65,410 $111,610 $159,350 $339,650 $340,000 $340,000

Monthly (%) 5.20% 14.04% 13.59% 14.04% 53.03% 0.10% 100.00%

Cumulative Progress (%) 5.20% 19.24% 32.83% 46.87% 99.90% 100.00% -

Note: Expenses incurring across multiple periods have been prorated based on number of days consumed each month.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 14

5 Risk Assessment

5.1 Risk Management Plan

5.1.1 Risk Threshold

In our project the risk threshold will be a risk score 0.09, after which it is high priority and of concern to us. Once the

score is 0.09 or higher we will take immediate action. We will also consider risks with a score 0.04 and higher as a second

priority (Risk Averse).

5.1.2 Risk scoring

 Qualitative Analysis: Probability-Impact (PI) Matrix will be used.

1. 0.01 ≥ Score ≤ 0.03 – Low Risk (Accept)

2. 0.04 ≥ Score ≤ 0.08 – Moderate Risk (Avoid/Transfer)

3. 0.09 ≥ Score ≤ 0.72 – High risk (Mitigate/Transfer/Avoid)

 Quantitative Analysis: We will be using Expected Monetary Value (EMV) to determine an accurate value for a

high risk event, which is beyond the risk threshold.

5.1.3 Risk Prioritization

The Probability-Impact (PI) Matrix will be used to determine the risk score, which shows if risk is high, moderate or low,

then Risk response actions will be decided based on the category. Main impact will be on schedule, followed by budget.

 Risk Score 0.09 – 0.72 is high risk (Mitigate/Transfer/Avoid)

 Risk Score 0.04 – 0.08 is moderate risk (Avoid/Transfer)

 Risk Score 0.01 – 0.03 is low risk (Accept)

Probability Risk Score = Probability x Impact

0.9 0.05 0.09 0.18 0.36 0.72

0.7 0.04 0.07 0.14 0.28 0.56

0.5 0.03 0.05 0.1 0.2 0.4

0.3 0.02 0.03 0.06 0.12 0.24

0.1 0.01 0.01 0.02 0.04 0.08

0.05 0.10 0.20 0.40 0.80

5.1.4 Resources

The risk management team will comprise of internal project team members only. The Project Manager (Tasfeia), Risk

Managers (Sama & Tanvir), HR & Scheduling Managers (Yogya & Avani), Finance Managers (Daniyal & Shazaan), will

be involved in assessment and management of risk effectively, field of experience and relevance are considered for the

choice.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 15

5.1.5 Categories

Risk categories involved in our project are as follows:

 Schedule

 External Weather

 Technical

 Health & Safety

 Cost

 Sponsor Related

 External – Other (Unpredictable & Very Unlikely)

5.1.6 Risk Register Template

Id Risk Description Prob. Impact Score Response Revised

Prob. Revised Impact

Revised Score

Status

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 16

5.2 Risk Assessment

5.2.1 Risk Identification

ID # Risk Description Type Category Probability Impact

1

Delay in

supply of

computers

Delivery dates may not be

met, as we changed supplier

from HP (Existing supplier

of Ryerson) to Samsung,

past records not available.

Threat Schedule Very Likely Adversely affects overall

schedule & budget

2

Adverse

weather

condition

May cause delay in building

walls, affecting project

completion time.

Threat External Likely

If remodelling is delayed,

then overall project is

delayed.

(Budget &Schedule)

3

Inferior Network

Performance

Performance not meeting

acceptance criteria. Threat Technical Likely

Affects quality, if scope

requirements not met.

4 Platform

mismatch

Problems might arise

integrating new technologies

with older platforms.

Threat Technical Likely Impacts budget, scope &

schedule

5

Risk of

Injury on

site

Workers might get hurt by

defective equipment and/or

unsafe wiring.

Threat Health &

Safety Likely

Impacts budget and

schedule.

6 Risk of price fluctuations

Possible variability in price

of equipment and/or

materials.

Threat Cost Unlikely Negatively affect budget.

7 Theft of

items Risk of items being stolen. Threat

External -

Other Likely

Third party contractors or

workers stealing, has a

budget impact & quality.

8 Intruders May cause damage to

property while project is in

progress

Threat External -

Other Unlikely Insignificant financial cost.

9 Minor scope

change

Project sponsor may request

for minor scope

changes/adjustments.

Threat Sponsor Unlikely

Small changes requested

do not compromise our

schedule and budget

objectives.

10

Minor Software

Bugs

Minor issues with add-on

features Threat Technical Very Unlikely

Performance lag barely

noticeable.

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 17

5.2.2 Qualitative Analysis

5.2.3 Quantitative Analysis

Method used to find the risk value: Expected Monetary Value (EMV)

In this case we selected Delay in supply of computers as a high priority risk, with estimated values and probabilities, the

expected value is 5.2 days and $5200. This risk will cause a delay in following activities such as Networking, Testing etc.

There is no allowance for a delay in schedule, however we have a contingency funding, hence we will shift to an earlier

delivery time of 6 days before installations, and the extra cost will only be about $3000, mainly for inventory management

costs. This way we will be able to complete the project on time and $3000 higher than the estimated $340,000 budget,

however we are still below the maximum budget of $360,000. We have a net advantage in mitigating this risk.

Delay in supply of computers

Pessimistic

(0.3)

Likely

(0.5)

Optimistic

(0.2) EV Working (P*I)

Expected Value

Schedule Impact (Days) 7 5 3 (0.3x7)+(0.5x5)+(0.2x3) 5.2 days

Budget Impact ($) 5000 3000 1000 (0.3x5000)+(0.5x3000)+(0.2x1000) $3,200

ID # Risk Probability Impact Score (PxI)

1 Delay in supply of computers 0.7 0.8 0.56

2 Adverse weather condition 0.5 0.8 0.4

3 Inferior Network Performance 0.3 0.8 0.4

4 Platform mismatch 0.3 0.8 0.24

5 Risk of Injury on site 0.3 0.4 0.12

6 Risk of price fluctuations 0.1 0.8 0.08

7 Theft of items 0.5 0.1 0.05

8 Intruders 0.3 0.2 0.06

9 Minor scope change 0.3 0.1 0.03

10 Minor Software Bugs 0.1 0.05 0.01

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 18

5.2.4 Risk Response

ID # Risk Response Revised

Probability

Revised

Impact

Revised

Score

1 Delay in supply

of computers Mitigate 0.10 0.05 0.01

2 Adverse weather

condition Mitigate 0.30 0.10 0.03

3 Inferior Network

Performance Transfer 0.10 0.05 0.01

4 Platform

mismatch Mitigate 0.30 0.10 0.03

5 Risk of Injury on

site Avoid 0.10 0.05 0.01

6 Risk of price

fluctuations Transfer 0.10 0.05 0.01

7 Theft of items Avoid 0.10 0.05 0.01

8 Intruders Avoid 0.10 0.05 0.01

9 Minor scope

change Accept 0.30 0.10 0.03

10 Minor Software

Bugs Accept 0.10 0.05 0.01

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 19

5.2.5 Risk Register

ID #

Risk Description Pro

bab

ility

Impact Score

(PxI) Response

Revised Probability

Revised Impact

Revised Score

Status

1

Delay in

supply of

computers

Delivery dates may

not be met, as we

changed supplier

from HP (Existing

supplier of Ryerson)

to Samsung, past

records not

available.

0.7 0.8 0.56 Mitigate 0.10 0.05 0.01 Closed

2

Adverse

weather

condition

May cause delay in

building walls,

affecting project

completion time.

0.5 0.8 0.4 Mitigate 0.30 0.10 0.03 In- Progress

3

Inferior

Network

Performance

Performance not

meeting acceptance

criteria.

0.3 0.8 0.4 Transfer 0.10 0.05 0.01 Closed

4 Platform

mismatch

Problems might

arise integrating new

technologies with

older platforms.

0.3 0.8 0.24 Mitigate 0.30 0.10 0.03 In- Progress

5 Risk of Injury

on site

Workers might get

hurt by defective

equipment and/or

unsafe wiring.

0.3 0.4 0.12 Avoid 0.10 0.05 0.01 In- Progress

6 Risk of price

fluctuations

Possible variability

in price of

equipment and/or

materials.

0.1 0.8 0.08 Transfer 0.10 0.05 0.01 Closed

7 Theft of

items

Risk of items being

stolen. 0.5 0.1 0.05 Avoid 0.10 0.05 0.01 Closed

8 Intruders

May cause damage

to property while

project is in progress

0.3 0.2 0.06 Avoid 0.10 0.05 0.01 Closed

9 Minor scope

change

Project sponsor may

request for minor

scope

changes/adjustments

0.3 0.1 0.03 Accept 0.30 0.10 0.03 Closed

10

Minor

Software

Bugs

Minor issues with

add-on features 0.1 0.05

0.01 Accept 0.10 0.05 0.01 Closed

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 20

Extra Information on Risk Responses

We have zero allowance for schedule but we have a budget surplus of $20,000, which can be used for risk

management and contingency funding, therefore we will try to address as many risks as we can with available

resources to make sure the deadline is met. Some risk responses are explained below with an estimated cost.

Delay in supply of computers (Mitigate)

 We will be shifting the required delivery date 6 days before installation, which has an extra cost of only

$3000 associated with inventory management costs for that 6 day period.

Adverse weather condition (Mitigate)

 We will be re-scheduling vulnerable/critical activities later when the weather forecast information is

available for the period, and we will be using overtime hours in order to cover up lost time. Estimated

additional cost is about $2500.

Inferior Network Performance (Transfer)

 We will be eliminating this risk by outsourcing the networking activities to Bell Canada, as they have

specialized experts in the field of Network engineering, they will satisfy the scope requirements without

any compromise. Estimated additional cost is about $4000.

Platform mismatch (Mitigate)

 There is a risk that new technologies may not integrate properly with older platforms. Therefore we will

be using tuning/conversion/bridging hardware & software solutions, to achieve successful integration for

resource pooling etc. This will have an estimated additional cost of about $3000.

Risk of Injury on site (Avoid)

 We will ensure defective equipment are replaced as soon as it is detected. Our workers will be strictly

advised to thoroughly check the status of equipment before using, to see if it is in perfect working order,

if not it needs to be immediately reported to the on site manager. Unsafe wiring should be eliminated,

throughout the project our contractors will be advised to safely cover and keep electrical wires out of the

way. This process and actions will cost an estimated $2000.

Risk of price fluctuations (Transfer)

 We will be using Fixed-price contracts transferring liability to seller, this has no additional costs.

Theft of items (Avoid) & Intruders (Avoid)

 We will be installing temporary surveillance and use clear notices to display that the site is monitored

24/7 until the actual camera system is ready to be installed, which will cost an additional $2500.

Minor scope change (Accept) & Minor Software Bugs (Accept)

 We will encourage our sponsor to request for any changes they wish in the beginning stages, therefore it

will be better to plan ahead. Minor software bugs will have a barely noticeable impact on performance,

therefore we will accept it but we are expecting the problems to be solved via an update within 30 days

from installation. These activities have no extra costs.

Total Risk Management costs: 3000+2500+4000+3000+2000+2500= $17000

Budget surplus remaining: 20000-17000= $3000

Multi-Purpose Computer Lab Facility for Ryerson University

Computing and Communications Team 21

Version Control

Version Date Author Change

1 03/19/2018 All Group Members All major decisions were made about the overall project,

WBS was made after brainstorming. Project charter and

scope statement was completed, with minor changes

made later in the week.

2 03/26/2018 All Group Members We discussed and completed Gant chart, Milestone

schedule and Budget sections with the S Curve.

3 03/30/2018 All Group Members We started working on Risk section virtually through

social media and phone.

4 04/01/2018 All Group members We completed the project, every member reviewed and

approved, signing off the document digital.

5 04/02/2018 - We printed and submitted the project in class.

Digital Signatures approving equal contribution and participation in completing the team project.

Tasfeia Alli Yogya Atwal

Tanvir Sra Sama Hussain

Daniyal Khalid Shazaan Amaan

Cynthia Pathmanathan Avani Patel

Jatin Dhingra