WBS Title Description Start Date End Date Total estimated days Point of Contact (POC)
1.0 Develop Work Breakdown Structure (WBS) Description of work to be completed / milestone 1/5/16 1/5/16 1
1.1 Review customer statement of work (SOW) Read and review the statement of work 1/6/16 1/9/16 3 Project Manager
1.1.1 Identify all project deliverables and milestones Highlight and identify all project deliverables and milestones associtated with the project 1/6/16 1/9/16 0 Project Manager
1.2 Forward a copy of the customer statement of work to the project team Forward a copy of the customer statement of work to all project team members 1/10/16 1/10/16 1 Project Manager
1.2.1 Begin development of the WBS Develop the WBS 1/10/16 1/10/16 1 Project team
1.3 Project team review Set up a SOW team review with the project team 1/13/16 1/13/16 1 Project team
1.3.1 Identify all top level work packages Highlight and identify all top level milestones / deliverables 1/14/16 1/15/16 1 S. Johnson
1.4 Identify all lower level work packages identify all work associated with the top level milestones 1/14/16 1/15/16 1 M. Jones
1.4.1 Project team approval Set up a project team meeting for WBS review / approval 1/17/16 1/17/16 1 Project team

Proj. Work Breakdown Structure

WBS Title Description Start Date End Date Total estimated days Point of Contact (POC)
1.0 Backpack with refrigerator and radio module Project The name of the project is Backpack with refrigerator and radio module Project 9/1/2015 3/1/2017 540 days Project manager
1.1 Project Planning and Initialization The phase involving the project initialization 9/1/15 9/20/15 19 days Project manager
1.1.1 Developing project charter Developing project charter 9/1/15 9/8/15 7 days Project manager
1.2 Program Evaluation Program Evaluation 9/8/15 9/13/15 5 days Project manager
1.2.1 Evaluating and recommending the program integrating the feedback into the backpack design 9/8/15 9/13/15 5 days Project owner
1.3 Program Approval Program Approval 9/20/15 10/20/15 30 Days Project owner
1.3.1 Approving the program charter Approving the program charter 9/20/15 9/30/15 10 Days Project owner
1.4 Signoffs Signoffs 10/20/15 10/22/15 2 Days Project ownver, contract manager
1.4.1 Signing off the contract Signing off the contract 10/20/15 10/21/15 1 day contract manager
2.0 Contract budgeting and procurement Contract budgeting and procurement 10/20/15 10/25/15 5 days procurement team
2.1 Contract budgeting Contract budgeting 10/25/15 11/5/15 10 days Project manager
2.1.1 Developing the contract budget Developing the contract budget 10/25/15 11/5/15 10 days Project manager
2.2 Procurement Procurement 11/5/15 12/5/15 30 Days procurement team
2.2.1 Acquring the backpacks Acquring the backpacks 11/5/15 12/5/15 30 Days procurement team
2.3 Delivery of backpacks to manufacturer Delivery of backpacks to manufacturer 11/5/15 12/5/15 30 Days transportation team
2.3.1 Transporting the backpacks to the manufacturer Transporting the backpacks to the manufacturer 12/5/15 1/5/16 30 Days transportation team
3.1 Backpack re-inspection Backpack re-inspection 1/5/16 2/5/16 30 days project owner
3.1.1 re-inspecting the received backpacks re-inspecting the received backpacks 1/5/16 2/5/16 30 days Operations team
4.1 Design of the refrigerator Design of the refrigerator 2/5/16 2/10/16 5 Days Operations team
4.1.1 Developing the refrigerator design for the backpack Developing the refrigerator design for the backpack 2/5/16 2/10/16 5 days Operations team
4.2 Development of the refrigerator Development of the refrigerator 2/10/16 5/10/16 90 Days Operations team
4.2.1 Developing and integrating the refrigerator Developing and integrating the refrigerator 2/10/16 5/10/16 90 days Operations team
5.1 Radio module design Radio module design 5/10/16 7/10/16 60 Days IT experts
5.1.1 Designing the radio module Designing the radio module 5/10/16 7/10/16 60 Days IT experts
5.2 Development of the radio module Development of the radio module 7/10/16 9/10/16 60 Days IT experts
5.2.1 Develop and integrate the radio module Develop and integrate the radio module 7/10/16 9/10/16 60 Days IT experts
6.1 Refrigerator module tests Refrigerator module tests 9/10/16 10/10/16 30 Days testing team
6.2.1 Conducting tests on refrigerator module Conducting tests on refrigerator module 9/10/16 10/10/16 30 Days testing team
6.2 Radio module testing Radio module testing 10/10/16 11/20/16 40 Days testing team
6.2.1 Conducting tests on the radio module Conducting tests on the radio module 10/10/16 11/20/16 40 Days testing team
7.1 Feedback collection Feedback collection 11/20/16 12/20/16 30 days data analysts
7.1.1 Collecting user feedback on the backpack Collecting user feedback on the backpack 11/20/16 12/20/16 30 days data analysts
7.2 Re-designing Re-designing 12/20/16 1/30/16 30 Days Operations team
7.2.1 Integrating the feedback into the backpack design Integrating the feedback into the backpack design 12/20/16 1/30/17 30 Days Operations team
8.1 Transportation to the special operations officers Transportation to the special operations officers 1/30/17 2/20/17 20 days transportation team
8.1.1 Transporting the backpacks to the special operations officer Transporting the backpacks to the special operations officer 2/20/17 3/1/17 10 days transportation team
8.2 Transportation to the grounds operations Transportation to the grounds operations 2/20/17 3/1/17 10 days transportation team
8.2.1 Transporting the backpacks to the grounds operations camp Transporting the backpacks to the grounds operations camp 2/20/17 3/1/17 10 days transportation team