Final Project Report

profileMKE2018
ARush_RiskMatrixWeek4_10292017.xlsx

Sheet1

L M H
100
90 H
80 M
70 L
60
50
40
30
20
10
Number Risk Name Full Risk Cost Risk Probability Factored Risk cost Risk Impact to Project Risk Mitigation Plan Point of Contact Expected Risk Retire date
1 Lack of top management commitment to the project $20,000 20% $4,000 L Proper communication plan, Regular contact with stakeholders. Management 09/01/16
2 Misunderstanding of the requirements $30,000 12% $3,600 H Clear documentation of the requirements,, Involving all users in requirement gathering Management 09/01/16
3 Not managing change properly $12,000 10% $1,200 M Avoid risk by Proper change management Change Management 09/01/16
4 Failure to gain user commitment $23,000 20% $4,600 M Good communication and reporting Communication Officer 09/01/16
5 Lack of effective project management skill $1,600 10% $160 M Employing expert project manager, outsourcing the project management or outsourcing the recruitment process. Management 09/01/16
6 Insufficient Finance $34,000 20% $6,800 L Dealing with the project by modifying the scope creep Management 03/01/17
7 Insufficient communication $13,000 10% $1,300 L Improved communication and stakeholder involvement Project Officer 03/01/17
8 Poor Stakeholder engagement $12,000 10% $1,200 M Improved communication and stakeholder involvement Project Officer 03/01/17
9 Failure to understand the customer value $11,000 8% $880 H Risk avoidance Project Officer 03/01/17
10 Sticking to old ways and refusing change $10,000 6% $600 H Training and understanding of the importance of the project. Project Officer 09/01/16

10

1

2

3

4

5

6

8

9

7