cost forecasting
KSCE Journal of Civil Engineering (2018) 22(5):1626-1633
Copyright ⓒ2018 Korean Society of Civil Engineers
DOI 10.1007/s12205-017-0452-x
− 1626 −
pISSN 1226-7988, eISSN 1976-3808
www.springer.com/12205
Construction Management
Forecasting Construction Cost Index Using Interrupted Time-Series
Taenam Moon* and Do Hyoung Shin**
Received April 5, 2017/Accepted June 19, 2017/Published Online August 9, 2017
··································································································································································································································
Abstract
The Construction Cost Index (CCI) provided by the Engineering News-Record (ENR) is frequently used in predicting the cost of construction projects because it reflects a comprehensive trend in the construction costs. In previous studies, the CCI was forecasted using the time-series analysis methods. However, the effects of specific intervening factors such as economic recession and policy changes on the CCI data were neglected, thus compromising the reliability and accuracy of the forecast models. In this study, an interrupted time-series forecasting model was developed wherein the economic recession of 2008 was reflected in the forecasting model, which is an outlier identified to have significant impact on the CCI. The forecast result obtained using the interrupted time- series forecasting model was better than that using the conventional forecast models such as the ARIMA and Holt–Winters exponential-smoothing models. The accurately forecasted CCI using the presented model will help in budget and bid planning as well as assessing the risk of future businesses.
Keywords: Construction Cost Index (CCI), interrupted time-series, forecast, outlier detection, intervention analysis
··································································································································································································································
1. Introduction
The cost associated with a construction project is an important
parameter that needs to be analyzed by all parties, including the
project owner, contractor, and subcontractor. An increase in the
construction costs during the project period can have a negative
impact on the overall project such as delay or termination of the
project, high project costs, and quantitative and qualitative
degradation of bid competition. Predicting the trend in construction
costs is crucial in estimating the cost of construction projects as
well as assessing the risks associated with budget planning and
coordination and costs (Xu and Moon, 2013). However, since
the past few decades, many construction companies and project
owners have suffered huge losses because the final construction
costs were considerably higher than those initially anticipated at
the planning phase despite having made significant efforts to
accurately predict the construction costs (Touran and Lopez, 2006).
This problem exists largely because it is not easy to accurately
predict the construction costs because of the volatility and
uncertainty in the factors such as transportation and construction
material costs, which directly influence the construction market,
and socioeconomic factors such as macroeconomic environments.
In addition, there is considerable difficulty in predicting the
actual construction costs of a few months or several years into
the future during the planning process because the time gap
between the project planning process and the actual construction
period is considerable (Shane et al., 2009).
The Construction Cost Index (CCI) can be effectively used to
estimate the construction costs of a construction project by
employing it to the temporal correction of cost data, cost planning,
price fluctuation, comparison with relevant costs, and evaluation
of market trend (Seeley, 1972; Fleming and Tysoe, 1991). In
particular, the US construction industry widely employs the CCI,
provided by the Engineering News-Record (ENR), because the
trend in the construction costs can be studied comprehensively
(Lewis and Grogan, 2013). The ENR conducts various surveys
and studies on construction economics, including US construction
materials and labor costs, to provide statistical information based
on their findings. The CCI is published in the first week of every
month with 1913 as the reference year. The ENR discloses the
individual CCIs, as well as the average of the CCIs, of 20 cities
in the United States. However, the CCIs are often predicted
because the published CCI does not reflect the actual time
required for project completion. Thus, the CCI cannot be employed
satisfactorily to estimate the cost, prepare the bids, and plan the
investments required for a project. In particular, for construction
projects where millions of dollars are invested, it is very important to
increase the accuracy of forecasting the CCI because a mere 1%
error in the construction cost forecast translates to considerable
losses (Shahandashti and Ashuri, 2013).
Many studies have suggested CCI-forecasting methods largely
based on causality analysis or time-series analysis. In recent years, in
most of the studies, the time-series-analysis-based methods were
preferred because the independent variables must be precisely
selected and such variables must be accurately predicted for
causality analysis. The data used in the time-series analysis have
TECHNICAL NOTE
*Graduate Student, Dept. of Civil Engineering, Inha University, Incheon 22212, Korea (E-mail: [email protected])
**Member, Associate Professor, Dept. of Civil Engineering, Inha University, Incheon 22212, Korea (Corresponding Author, E-mail: [email protected])
Forecasting Construction Cost Index Using Interrupted Time-Series
Vol. 22, No. 5 / May 2018 − 1627 −
been observed over a relatively long period. These data are used
to develop the model and calculate the predicted values under an
assumption that the system based on this time-series data will be
maintained in the future. In the event of uncontrollable factors
such as policy changes, strikes, or wars, there is a possibility that
the time-series data over a long period may have different
patterns at different times because of the time-specific nature of
such factors. Hence, it is difficult to have confidence in the
analysis results if the data are affected by any event in the time-
series analysis, particularly when such effects are not reflected in
the model. Moreover, in most of the CCI-forecasting methods
based on the time-series analysis, necessary adjustments were
never made to consider these factors.
This study proposes an interrupted time-series model to
forecast the CCI, which helps in overcoming such limitations by
reflecting the intervening factors that influence the CCI to
improve the reliability and accuracy of the forecasting model.
The time-series data used in developing the forecasting model
are the CCI data obtained from the ENR, dating from January
1990 to February 2016. The analysis was performed using R
programming language.
2. Related Studies
Generally, the causality and time-series analyses have been
widely used in forecasting the construction costs (Touran and
Lopez, 2006). The CCI-based forecasting methods can be broadly
divided into the aforementioned methods.
2.1 Causality Analysis
The previous causality analysis methods used for forecasting
the CCI involved selecting independent variables that could best
explain the CCI and developing the model using these variables
with the help of linear-regression analyses. For example, Williams
(1994) predicted the CCI using the prime lending rate, housing
starts, and months of the year as the independent variables.
Hwang (2009) developed a model using prime-interest rate,
housing starts, and consumer price index. Ashuri et al. (2012)
predicted the CCI by determining the money supply and crude
oil prices as the significant variables having a long term correlation
with the CCI, among various variables. In these studies, the
causality analysis method was used to improve the predictability
of the model by using variables that were neglected in previous
studies or by using variables that coincided with the economic
conditions of the time. However, the causality analysis method
has disadvantages in that the independent variables associated
with the CCI must be identified and the predicted values of these
independent variables must be calculated. In particular, it is
difficult to select appropriate independent variables because
there are various factors affecting the construction costs in the
construction industry. Moreover, the degrees of such effects vary
with respect to time. In addition, predicting the future value of
the selected independent variables becomes a factor, as it
increases the error in the forecasted value of the CCI. Hence, the
causality analysis method has not been widely used in forecasting
the CCI in recent years (Joukar and Nahmens, 2015; Xu and
Moon, 2013).
2.2 Time-series Analysis
In many studies, the time-series analysis was used to overcome
the disadvantages of the causality analysis method in which the
CCI is explained with external factors. The time-series analysis
can be divided into two categories: a univariate time-series
analysis and a multivariate time-series analysis. The univariate
time-series analysis is used to predict the values of a dependent
variable by using its past values as an explanatory variable.
Unlike the causality analysis method, which helps in determining
the relationship between the various variables, the time-series
analysis method requires only the statistical information and
structure of the past values under an assumption that the past
time-series pattern continues to this day. As one of the most
representative CCI- forecasting studies using a univariate time-
series, Ashuri and Lu (2010) showed that seasonal Autoregressive
Integrated Moving Average (ARIMA) and Holt–Winters
exponential-smoothing models provided the most accurate
predictability by comparing the predictability of various univariate
time-series analyses. Additionally, Joukar and Nahmen (2015)
concluded that the variation values were not constant as the CCI
varies over time; moreover, in most of the previous CCI studies,
such variations over time were neglected. They forecasted the
CCI wherein they reflected the volatility of variance using
Autoregressive Conditional Heteroskedasticity (ARCH) and
Generalized Autoregressive Conditional Heteroskedasticity
(GARCH) with better results than the existing ARIMA model in
a one-step ahead forecast.
A multivariate time-series analysis is a time-series analysis
performed using multiple independent variables, which follows
the vector autoregression (VAR) approach. In recent years, the
multivariate time-series analysis of the CCI has been frequently
studied in comparison with the univariate analysis. For example,
Hwang (2011) developed a VAR model considering the CCI and
Consumer Price Index (CPI) as variables to forecast the CCI and
showed that this predictive model yielded more accurate predictions
than the univariate time-series models. Xu and Moon (2013)
predicted the CCI using the co-integrated vector autoregression
(C-VAR), considering not only the long-term effects of the two
variables but also the short-term interactions, with the CCI and
CPI as variables. In addition, they showed that this model
exhibited better results than a univariate time-series model such
as the ARIMA model. However, the VAR models have some
disadvantages in that the number of parameters to be estimated is
high compared to the dependent variable data. The results are
largely influenced by the method whereby the analyst chooses
the variable selection, lag length, and order of variables in the
model.
To date, the time-series analysis of the CCI has been performed
under an assumption that the time-series patterns of the past
continue to exist in both univariate and multivariate analyses.
Taenam Moon and Do Hyoung Shin
− 1628 − KSCE Journal of Civil Engineering
However, a considerable amount of real-world data, particularly
the time-series data observed over a long period, contains
outliers that influence such data with the change in the trend. In
previous CCI studies, because the time-series data were modeled
without considering the outliers, there are possibilities that
significant biases have occurred in the autocorrelations, partial
autocorrelations, and ARIMA parameters. As such, the biases
could have significantly influenced the predicted values by
distorting the results of statistical tests because they tend to
increase the confidence intervals of the model parameter (Guttman
and Tiao, 1978; Chang, 1982; Galeano and Peña, 2013). Hence,
in this study, the outliers that have influenced the CCI data were
identified and a CCI-forecasting model is proposed wherein such
outliers are accounted for as interventions. For the intervention
analysis, the multivariate time-series analysis is not generally
used because the multivariate time-series analysis is used to
estimate parameters using the cross-correlation of the variables,
making it difficult to apply various interventions to each variable.
Thus, the multivariate analysis was ruled out in this study. The
intervention model proposed in this study was developed based
on the interrupted ARIMA model (Box and Tiao, 1975), which
was a univariate model.
3. Development of CCI-Forecasting Model
To construct and validate the CCI-forecasting model, the CCI
data from January 1990 to January 2015 and from February 2015
to February 2016 were classified as training and test sets,
respectively. In the modeling process, the training set was first
used to test whether the CCI satisfied the stationarity condition,
which is the fundamental assumption of the time-series analysis,
and estimate the basic ARIMA model. The outliers were then
identified using this basic ARIMA model as the reference by
employing the outlier-detection method proposed by Tsay
(1988), breakpoint-estimation method proposed by Bai (1994),
and generalized Extreme Studentized Deviate (ESD) test suggested
by Rosner (1983). Among the identified outliers, appropriate
intervention points were selected and a predictive model was
developed by performing the intervention analysis. Additionally,
the CCI-forecast values, estimated through the intervention
analysis using the test set, were compared with the actual CCI
and forecast values to validate the model; these values were
derived from the ARIMA and Holt–Winters methods, which
were commonly used time-series models for forecasting the CCI.
3.1 Stationary Test
The CCI data used in this study are the monthly data dated
from January 1990 to February 2016 (a total of 314 months). In
the time-series analyses, a unit-root test such as the augmented
Dickey–Fuller test (Dickey and Fuller, 1979) is a commonly
used method for checking the stationarity condition. However,
Perron (1989) stated that if a structural break such as a sudden
increase or a trend change exists in the time-series data, it could
have an impact on the validity of the unit root. Fig. 1 shows the
lagged first difference of the CCI (∆CCIt = CCIt−CCIt-1, ∆: the
first difference operator). The figure shows that there are changes
in the CCI trend and variance in 1993, 2001, 2008, and 2013.
These changes can cause errors in the validation of the unit root
as well as influence the parameter estimation. In this case, it is
necessary to perform a unit root test wherein the structural breaks
are considered endogenously, thus reducing the bias in the unit-
root test (Zivot and Andrews, 1992; Perron and Vogelsang, 1992;
Perron, 1997). Table 1 lists the results of the Zivot–Andrews unit
root test for the CCI data, which is one of the most commonly
used unit-root tests. In a unit root test, the trends or the average
values must be considered depending on the types of data. Thus,
in this study, the trend term was considered in the unit-root test
for CCIt, and the intercept (the average value of the data) in the
unit-root test for ΔCCt. As listed in Table 1, the t-value of CCIt is
-3.838, and the null hypothesis could not be rejected at the 5%
significance level. However, when the t-value of ΔCCIt is
-15.3791, the null hypothesis was rejected at the 5% significance
level. Through this result, it was confirmed that the lagged first
difference of the CCI satisfied the stationarity condition.
Accordingly, further analysis in the study was conducted using
the lagged first difference of the CCI.
3.2 ARIMA Modeling
To confirm the degree of the ARIMA model for the CCI, the
autocorrelation between the time differences was checked by
investigating the Auto-Correlation Function (ACF) and Partial
Auto-Correlation Function (PACF) of the first lagged difference
Fig. 1. Lagged First Difference of CCI
Table 1. Results of Zivot–Andrews Unit-Root Test
Series Critical Value of t
(at 5% level of significance) t-Value
CCIt -4.42 -3.838
ΔCCIt -4.8 -15.3791
Forecasting Construction Cost Index Using Interrupted Time-Series
Vol. 22, No. 5 / May 2018 − 1629 −
of the CCI (ΔCCIt). The ACF plot, shown in Fig. 2, exhibits a
significant shape in Lag 1 and a trend that gradually reduces into
a sine shape. In addition, the PACF plot presents a significant
shape in Lag 1. The first lagged difference of the CCI was
regarded at first place to have seasonality in Lag 5 because of the
weak significance in Lag 5 in its ACF and PACF. However, no
significant ACF or PACF patterns were observed in Lags 10 and
15, and no seasonality was observed when the ACF and PACF of
the CCI were examined. Thus, it was decided not to consider the
seasonality for the first lagged difference of the CCI in the
ARIMA modeling. The ACF shape in Lag 5 was considered an
error that could be accepted within a level of significance of 5%.
It was tentatively reasoned thorough this that it is appropriate to
forecast the CCI based on the lagged first-differenced Auto-
Regression (AR) model, i.e., ARIMA(1,1,0). Eq. (1) represents
the forecasting model of the CCI derived as ARIMA (1,1,0)
shape using the training set. Using the first lagged difference, this
model is used to forecast ΔCCIt+1, which is the change in the CCI
from the previous month to the next month. Hence, the forecast
value of the CCI, CCIt+1, can be calculated as CCIt + ΔCCIt+1 by
adding the CCI change compared to the previous month to the
CCI value of the previous month.
∆CCIt+1 = 17.6447 + 0.2127∆CCIt + εt+1 ~ WN(0,1) (1)
where ΔCCIt+1 is first lagged difference (CCIt+1 − CCIt), εt+1 ~
WN(0,1) is white noise (average 0, variance 1) error term.
To better determine the fitness of the ARIMA(1,1,0) model,
the model was compared to other models wherein overfitting
was employed by adding one degree at a time. Table 2 lists the
results obtained by comparing the ARIMA(1,1,0) derived from
the training set with the ARIMA(2,1,0) and ARIMA(1,1,1)
models, wherein the parameters were added to the ARIMA(1,1,0)
model. The Akaike Information Criterion (AIC), which is
generally used as the ARIMA-model selection criterion, reflects
the degree of fit of the model. The smaller the value, the better is
the degree of fit. By comparing of AIC for the fit of the ΔCCIt values, it was shown that the ARIMA(1,1,0) model is more
suitable for the CCI forecasting than the ARIMA(2,1,0) and
ARIMA(1,1,1) models. Moreover, the ARIMA(1,1,0) model
was determined to be most suitable in terms of the parameter
significance and principle of parsimony. Thus, the ARIMA(1,1,0)
model, which was derived using Eq. (1), was selected as the
basic ARIMA model for forecasting the CCI. However, the
intervention effects have not been considered in this basic model.
The outlier must be first detected to incorporate the intervention
effect into the forecasting model.
3.3 Outlier Detection
In this study, the outliers were detected to check whether there
is any intervention of specific factors in the CCI and determine
the timing of such intervention effect, if any. The following three
different outlier-detection methods were applied on the training
set to determine the outliers of the CCI in the study: 1) the
likelihood-ratio test, which is a probabilistic method proposed by
Tsay (1988); 2) the breakpoint-estimation method, which is a
robust method proposed by Bai (1994); and 3) the ESD test
proposed by Rosner (1983). These outlier-detection methods are
used to detect the outliers through different mechanisms. The
likelihood-ratio test is used to probabilistically detect the outliers
using the initially assumed ARIMA model. The breakpoint-
detection method is used to detect the outliers through the shift
and slope changes by dividing the time-series data into segments.
The ESD test is used to determine the outliers by setting the
normal distribution of the time-series data as the reference.
Because using both the detection method, through a probabilistic
model such as ARIMA, and the robust-detection method is
mutually supplementary (Martin, 1980), the likelihood of detecting
the outliers that are not identified using a specific method
increases. In this study, any outlier detected using one of the
aforementioned methods was treated as an outlier.
Table 3 and Figs. 3-5 present the results of the three outlier-
detection methods. A total of 15 outliers were detected. First, the
outliers of the CCI were detected by applying the likelihood-ratio
Fig. 2. ACF and PACF of Lagged First Difference of the CCI
Table 2. Comparison of ARIMA Model for CCI Forecast
ARIMA (1,1,0)
ARIMA (2,1,0),
ARIMA (1,1,1)
AR(1) Coefficient
0.2127*** (0.0564)
0.2096*** (0.0577)
0.2475 (0.1947)
AR(2) Coefficient
0.0147 (0.0576)
MA(1) Coefficient
-0.0364 (0.1969)
Drift 17.6447 ***
(1.9610) 17.6452***
(1.9897) 17.6452***
(1.9769)
AIC 2829.68 2831.61 2831.64
Note: *** represents the P-values, which satisfy the significance level of 0.1% or lower.
Taenam Moon and Do Hyoung Shin
− 1630 − KSCE Journal of Civil Engineering
test to the differences between the actual values and the
corresponding predicted values using ARIMA(1,1,0) model. The
outliers detected using the likelihood-ratio test are classified into
four types: Additive Outlier (AO), Innovational Outlier (IO),
Level Shift (LS), and Temporary Change (TC). Among these,
only the TC and LS were considered for the interrupted time-
series modeling in this study. The TC affects the time-series for a
short period; nevertheless, it comprehensively changes the time-
series, though the effect decreases after the occurrence point. The
LS constantly affects the time-series even after the occurrence
point. The IO was excluded because it does not lead to a
comprehensive change in the time-series, with the effect on the
time-series gradually diminishing after the occurrence point. It is
usually considered inappropriate to consider the IO in the
interrupted time-series modeling. The AO was excluded because
it affects the time-series only at the occurrence point, generally
resulting from exogenous factors such as measurement and
recording errors. The likelihood-ratio test helped in identifying
Table 3. Results of Outlier Detection
Method of Outlier Detection
Likelihood Ratio Test
Breakpoint-Estimation Method
ESD Test Cause of Outlier
Detection Point
1993.05 Jump in Steel Cost
1993.11
1999.06 Jump in Common Labor Cost
2004.03
Jump in Steel Cost2004.05
2004.09
2006.10 Jump in Steel Cost
2008.06
Recession2008.07 2008.07
2008.09
2012.06 Jump in Steel Cost
2013.10 2013.10 Jump in Common Labor Cost
2013.11
Fig. 3. Detection of CCI Outliers (using likelihood-ratio test)
Fig. 4. Detection of CCI Outliers (using breakpoint-estimation method)
Fig. 5. Detection of CCI Outliers (using ESD test)
Forecasting Construction Cost Index Using Interrupted Time-Series
Vol. 22, No. 5 / May 2018 − 1631 −
four outliers. The four outliers were TCs.
The outliers of the CCI were also detected using the breakpoint-
estimation method and ESD test. The number of outliers identified
using the breakpoint-estimation method and ESD test were five
and six, respectively. Because the slope of each segment is
compared in the breakpoint-estimation method, the outliers of
the CCI were effectively detected. In the ESD test, the lagged
first difference of the CCI (i.e., ΔCCI) was employed. The
normality of the data is required in the ESD test. The CCI was
not found to satisfy the normality whereas the normality was
satisfied by the lagged first difference of the CCI. Hence, in the
study, the ESD test was conducted on the lagged first difference
of the CCI instead of the CCI.
Even when the same outlier is detected using the three
detection methods, the occurrence points can be slightly different
depending on the detection method. For example, the three
detection methods were used to identify the outliers between
June 2008 and September 2008. The precise occurrence points
are slightly different; however, the outliers actually occurred at
the same point in time. In other words, the outliers between June
2008 and September 2008 are the same. However, slightly
different occurrence points were detected because of the differences
in the mechanisms of the outlier-detection methods. This issue is
dealt with in the interrupted time-series modeling. The approach
to address the issue is explained in section 3.4.
3.4 Interrupted Time-series Model
An intervention analysis was conducted using the detected
outliers to develop an interrupted time-series model wherein the
intervention effects are reflected. Through this analysis, an
interrupted time-series model was derived by adding the outlier
effects to the ARIMA(1,1,0) model shown in Eq. (1).
It is necessary to determine the intervention timing (occurrence
timing) of the outliers that have actually occurred at the same
point in time to validate the significance of the outlier effects in
the intervention analysis. Otherwise, it is possible to consider the
significance of the outlier effects by unnecessarily reflecting
outliers that are essentially the same. Accordingly, in this study,
identical outliers are indicated via the shaded boxes of similar
colors in Table 3, which were detected to have occurred at
similar time points obtained from the three detection methods.
Here, the intervention-timing points of the outliers occurring at
similar points detected using the different detection methods
were defined at the earliest of the occurrence points of the
outliers. This was done because latter points could have resulted
from the influences of a trend change or a jump in a short period.
Hence, when the intervention point is based on the latter points,
the model can be estimated without considering the outlier
effects between the earlier and latter points. By using this
approach, the following seven intervention timing points were
derived from the 15 outliers listed in Table 3: 1993.05, 1999.06,
2004.03, 2006.10, 2008.06, 2012.06, and 2013.10 (in YYYY.MM).
An interrupted time-series model was developed by adding the
effects of the seven intervention points to the ARIMA(1,1,0)
model, which was selected as the basic model in section 3.2.
Table 4 lists the results of the modeling performed by individually
adding the seven intervention points in the training set to
ARIMA(1,1,0). It can be seen that only model (1), obtained by
adding the intervention of March 2004, and model (2), obtained
by adding the intervention of June 2008, satisfy the significance
of the variable and exhibit a statistical fit. In March 2004, the
steel prices increased sharply to a point where the ENR had to
revise the CCI index after it had been released for the first and
last time in history. In June 2008, the subprime mortgage crisis
occurred, thus sharply increasing the labor and materials costs.
Hence, it is safe to say that the effects and causes of both the
intervention points are explicit. However, the model, which was
obtained by adding both March 2004 and June 2008 as the
interventions, failed to satisfy the significance of the variables.
Thus, the final interrupted time- series model was selected by
choosing the one having better predictability, between models
(1) and (2), wherein March 2004 and June 2008 were added as
the interventions, respectively. To compare the theoretical
predictability of the models, this study examined the AIC through
the change (ΔCCIt+1) in the CCI from the previous month to the
next month. The AIC values of models (1) and (2) were 2820.98
and 2810.42, respectively. Both the models provided better AICs
than the AIC value of ARIMA(1,1,0), which was 2829.68 (refer
to Table 2), where the outlier effects were not reflected. Additionally,
model (2) had a lower AIC value than model (1), showing that it
had better predictability. Moreover, no autocorrelation was
observed in the ACF of the residual nor was there any abnormality
of the residual in the post-hoc test of model (2). Thus, model (2)
was selected as the final interrupted time-series model to forecast
the CCI. Model (2) is represented in Eq. (2), which is obtained
by adding a dummy variable term Pt(T) to Eq. (1). This dummy
variable reflects the effect of the intervention that occurred at the
time point of June 2008. This intervention effect reduces the
statistical distortion due to the outlier that has existed in June
2008, enabling more accurate forecasting. Similar to the case in
Table 4. Statistical Results of Interrupted Time-series Models
AR(1) Coefficient
AR(1) (2004.03)
Coefficient-
MA(1) (2004.03)
Coefficient-
AR(1) (2008.07)- Coefficient
MA(1) (2008.07)
Coefficient Drift AIC
Model (1) 0.1857** (0.0568)
0.6111*** (0.1075)
17.0556*** (1.8841)
2820.98
Model (2) 0.1364* (0.0583)
0.5810*** (0.0521)
112.6052*** (24.1589)
16.3939*** (1.7400)
2810.42
Note : *, **, and *** show the p-values that satisfy the significance level of 5% or lower, 1% or lower, and 0.1% or lower, respectively.
Taenam Moon and Do Hyoung Shin
− 1632 − KSCE Journal of Civil Engineering
Eq. (1), the CCI forecast value CCIt+1 is calculated as CCIt +
DCCIt+1 by adding the changes in the CCI compared to the previous
month, calculated using Eq. (2), to the CCI value of the previous
month.
(2)
where ΔCCIt+1 is lagged first difference of CCIt+1 (CCIt − CCIt),
Pt(T) is dummy variable applied only for T point ( , T =
2008.06), B is Backshift operator (BΔCCIt+1 = ΔCCIt), εt+1 ~
WN(0,1) is white noise (average 0, dispersion 1) error term.
4. Model Validation
So far, the ARIMA and intervention analyses were performed
by setting the monthly time-series of the CCI dated from 1990.01
to 2015.01 as the training set. To validate the predictability of the
model, the test set (2015.02–2016.01) data were employed,
which were monthly time-series of the CCI obtained after the
training set. The interrupted time-series model (as in Eq. (2)),
ARIMA, and Holt–Winters exponential smoothing model were
tested on the test set to compare their predictability over a period
of 12 months (2015.02–2016.01). As the ARIMA and Holt–
Winters exponential smoothing models were frequently used in
previous CCI-forecasting studies, and showed relatively good
predictability for the CCI (Ashuri and Lu, 2010), they have been
included in the models to be compared. Each model helped in
forecasting the CCI value as of February 2015, which was the
first forecasting point, using the CCI value as of January 2015.
The forecasted values were then used to forecast the value as of
March 2015. The CCIs over a period of 12 months, until January
2016, which was the last point of the test set, were determined
similarly.
The forecasted values of the test set obtained using each model
were compared to the actual values. Table 5 lists the test results.
The error rate of each month is the ratio of the absolute value of
the error (the difference between the actual and forecasted
values) to the actual value in the percentage form. In addition,
Mean Absolute Error (MAE), Mean Absolute Percentage Error
(MAPE), and Root Mean Square Error (RMSE) were calculated
to evaluate the forecast error over the entire 12 months of each
model. The comparison-test results show that the MAE, MAPE,
and RMSE were lower in the interrupted time-series model
(interrupted ARIMA model) than those in the ARIMA and Holt–
Winters models. This implies that the interrupted time-series
model has better predictability than the other two models.
5. Conclusions
Forecasting the CCI can be very helpful in predicting the
trends in the future US construction market and determining the
direction of project budget planning. Because a small difference
in the prediction can translate into a significant amount of losses,
a forecast of index such as the CCI can play a crucial role in the
construction project market. When forecasting the CCI using a
time-series analysis, it is necessary to consider the intervention
effects due to events such as policy changes, sudden increase in
construction materials, and economic recessions. These factors
affect the construction market, because they can cause
comprehensive changes in the time-series of the CCI. To
develop a better forecasting model for the CCI, in this study,
stationarity validation and outlier detections were performed,
and necessary considerations were made for the identified
outliers. Finally, an interrupted time-series (interrupted ARIMA)
model was developed wherein the 2008 recession crisis was
incorporated as an intervention.
CCIt 1+Δ 16.3939 112.6052
1 0.5810B– ----------------------------P
t T( ) 0.1364 CCIt εt 1+ WN 0 1,( )∼+Δ+ +=
0 t T≠,
1 t, T=⎩ ⎨ ⎧
Table 5. Comparing the Predictability between CCI-forecasting Models
Month Actual Value
Interrupted ARIMA ARIMA Holt-Winters
Forecasted Value
Error (%) Forecasted
Value Error (%)
Forecasted Value
Error (%)
2015.02 9962 9991.068 0.2907 9993.549 0.3155 9978.792 0.1679
2015.03 9972 10007.826 0.3583 10012.024 0.4002 9988.709 0.1671
2015.04 9992 10024.270 0.3227 10029.845 0.3785 9994.417 0.0242
2015.05 9979 10040.670 0.6167 10047.527 0.6853 10041.459 0.6246
2015.06 10039 10057.065 0.1807 10065.180 0.2618 10070.876 0.3188
2015.07 10037 10073.459 0.3646 10082.826 0.4583 10102.959 0.6596
2015.08 10039 10089.853 0.5085 10100.471 0.6147 10134.876 0.9588
2015.09 10065 10106.247 0.4125 10118.116 0.5312 10171.459 1.0646
2015.1 10128 10122.641 0.0536 10135.761 0.0776 10183.668 0.5567
2015.11 10092 10139.035 0.4704 10153.406 0.6141 10214.335 1.2234
2015.12 10135 10155.429 0.2043 10171.050 0.3605 10218.460 0.8346
2016.01 10132 10171.823 0.3982 10188.695 0.5670 10231.502 0.9950
MAE 34.8420 43.8709 63.2956
MAPE (%) 0.3457 0.4346 0.6231
RMSE 37.8155 46.9538 54.73.7628
Forecasting Construction Cost Index Using Interrupted Time-Series
Vol. 22, No. 5 / May 2018 − 1633 −
The predictability between CCI-forecasting models over 12
months (2015.02–2016.01) in the test set was compared. The
results showed that the interrupted time-series model (MAPE =
0.3457%) provided better predictability than the ARIMA (MAPE
0.4346%) and Holt–Winters exponential-smoothing (MAPE =
0.6231%) models. The results indicate the need to consider the
interventions when developing a CCI-forecasting model to obtain
accurate forecasts. Additionally, it was possible to improve the
convincibility for the CCI forecast values because they were
explained by considering the intervention effects due to events
such as policy changes and economic recessions, which affect the
CCI, instead of explaining merely through characteristics of the
time-series structures. The intervention effects in the CCI not
only affect the future forecast but also have influences on the
normality as well as the autocorrelation, which are the basic
assumptions of the time-series analysis. Thus, it is necessary to
consider such influences to obtain forecasts with solid statistical
reasoning. As suggested in this study, the interrupted time-series
model, along with the interventions, will enable more accurate
forecasting of the construction costs and will be helpful in budget
planning as well as risk assessment for future projects.
Acknowledgements
This work was supported by an Inha University Research
Grant.
References
Ashuri, B. and Lu, J. (2010). “Forecasting ENR construction cost index:
A time series analysis approach.” Construction Research Congress
2010, DOI: 10.1061/41109(373)135.
Ashuri, B., Shahandashti, S. M., and Lu, J. (2012). “Empirical tests for
identifying leading indicators of ENR Construction Cost Index.”
Construction Management and Economics, Vol. 30, No. 11, pp. 917-
927, DOI: 10.1080/01446193.2012.728709.
Bai, J. (1994). “Least squares estimation of a shift in linear processes.”
Journal of Time Series Analysis, Vol. 15, No. 5, pp. 453-472, DOI:
10.1111/j.1467-9892.1994.tb00204.x.
Box, G. E. P. and Tiao, G. C. (1975). “Intervention Analysis with
Applications to Economic and Environmental Problems.” Journal of
the American Statistical Association, Vol. 70, No. 349, pp. 70, DOI:
10.2307/2285379.
Chang, I. (1982). Outliers in time series, Technical Report. University of
Wisconsin.
Dickey, D. A. and Fuller, W. A. (1979). “Distribution of the estimators for
autoregressive time series with a unit root.” Journal of the American
Statistical Association, Vol.74, No. 366, pp. 427, DOI: 10.2307/2286348.
Fleming, M. C. and Tysoe, B. A. (1991). Spon's Construction Cost and
Price Indices Handbook, CRC Press.
Galeano, P. and Peña, D. (2013). “Finding outliers in linear and
nonlinear time series.” Robustness and Complex Data Structures,
pp. 243-260, DOI: 10.1007/978-3-642-35494-6_15.
Guttman, I. and Tiao, G. C. (1978). “Effect of correlation on the
estimation of a mean in the presence of spurious observations.”
Canadian Journal of Statistics, Vol. 6, No. 2, pp. 229-247, DOI:
10.2307/3315050.
Hwang, S. (2009). “Dynamic regression models for prediction of
construction costs.” Journal of Construction Engineering and
Management, Vol. 135, No. 5, pp. 360-367, DOI: 10.1061/(asce)
co.1943-7862.0000006.
Hwang, S. (2011). “Time series models for forecasting construction
costs using time series Indexes.” Journal of Construction Engineering
and Management, Vol. 137, No. 9, pp. 656-662, DOI: 10.1061/
(asce)co.1943-7862.0000350.
Joukar, A. and Nahmens, I. (2015). “Volatility forecast of construction
cost index using general autoregressive conditional heteroskedastic
method.” Journal of Construction Engineering and Management,
Vol. 142, No. 1, pp. 04015051, DOI: 10.1061/(asce)co.1943-
7862.0001020.
Lewis, S. and Grogan, T. (2013). A hundred year of ENR cost indexes,
Engineering News Record, New York.
Martin, R. D. (1980). Robust estimation of autoregressive models. In:
Billinger, D.R., Tiao, G.C., Eds., Direction in Time Series. Haywood,
CA: Institute of Mathematical Statistics, pp. 228-254.
Perron, P. (1989). “The great crash, the oil price shock, and the unit root
hypothesis.” Econometrica, Vol. 57, No. 6, pp. 1361, DOI: 10.2307/
1913712.
Perron, P. (1997). “Further evidence on breaking trend functions in
macroeconomic variables.” Journal of Econometrics, Vol. 80, No. 2,
pp. 355-385, DOI: 10.1016/s0304-4076(97)00049-3.
Perron, P. and Vogelsang, T. J. (1992). “Nonstationarity and level shifts
with an application to purchasing power parity.” Journal of Business
& Economic Statistics, Vol. 10, No. 3, pp. 301, DOI: 10.2307/1391544.
Rosner, B. (1983). “Percentage points for a generalized ESD many-
outlier procedure.” Technometrics, Vol. 25, No. 2, pp. 165, DOI:
10.2307/1268549.
Seeley, I. H. (1972). Building economics: Appraisal and control of building
design cost and efficiency, Macmillan, London, United Kingdom.
Shahandashti, S. M. and Ashuri, B. (2013). “Forecasting engineering
news-record construction cost index using multivariate time series
models.” Journal of Construction Engineering and Management,
Vol. 139, No. 9, pp. 1237-1243, DOI: 10.1061/(asce)co.1943-
7862.0000689.
Shane, J. S., Molenaar, K. R., Anderson, S., and Schexnayder, C. (2009).
“Construction project cost escalation factors.” Journal of Management
in Engineering, Vol. 25, No. 4, pp. 221-229, DOI: 10.1201/
9780849390388.ch7.
Touran, A. and Lopez, R. (2006). “Modeling cost escalation in large
infrastructure projects.” Journal of Construction Engineering and
Management, Vol. 132, No. 1, pp. 853-860, DOI: 10.1061/(asce)
0733-9364(2006)132:8(853).
Tsay, R. S. (1988). “Outliers, level shifts, and variance changes in time
series.” Journal of Forecasting, Vol. 7, No. 1, pp. 1-20, DOI:
10.1002/for.3980070102.
Williams, T. P. (1994). “Predicting changes in construction cost indexes
using Neural Networks.” Journal of Construction Engineering and
Management, Vol. 120, No. 2, pp. 306-320, DOI: 10.1061/(asce)
0733-9364(1994)120:2(306).
Xu, J. W. and Moon, S. (2013). “Stochastic forecast of construction cost
index using a cointegrated vector autoregression model.” Journal of
Management in Engineering, Vol. 29, No. 1, pp. 10-18, DOI:
10.1061/(asce)me.1943-5479.0000112.
Zivot, E. and Andrews, D. W. K. (1992). “Further evidence on the great
crash, the oil-price shock, and the Unit-Root Hypothesis.” Journal of
Business & Economic Statistics, Vol. 10, No. 3, pp. 251-270, DOI:
10.1080/07350015.1992.10509904.
<< /ASCII85EncodePages false /AllowTransparency false /AutoPositionEPSFiles true /AutoRotatePages /None /Binding /Left /CalGrayProfile (Gray Gamma 2.2) /CalRGBProfile (sRGB IEC61966-2.1) /CalCMYKProfile (U.S. Web Coated \050SWOP\051 v2) /sRGBProfile (sRGB IEC61966-2.1) /CannotEmbedFontPolicy /Error /CompatibilityLevel 1.3 /CompressObjects /Off /CompressPages true /ConvertImagesToIndexed true /PassThroughJPEGImages false /CreateJobTicket false /DefaultRenderingIntent /Default /DetectBlends true /DetectCurves 0.0000 /ColorConversionStrategy /LeaveColorUnchanged /DoThumbnails false /EmbedAllFonts true /EmbedOpenType false /ParseICCProfilesInComments true /EmbedJobOptions true /DSCReportingLevel 0 /EmitDSCWarnings false /EndPage -1 /ImageMemory 1048576 /LockDistillerParams true /MaxSubsetPct 100 /Optimize true /OPM 1 /ParseDSCComments true /ParseDSCCommentsForDocInfo true /PreserveCopyPage true /PreserveDICMYKValues true /PreserveEPSInfo true /PreserveFlatness true /PreserveHalftoneInfo false /PreserveOPIComments false /PreserveOverprintSettings true /StartPage 1 /SubsetFonts false /TransferFunctionInfo /Apply /UCRandBGInfo /Remove /UsePrologue false /ColorSettingsFile () /AlwaysEmbed [ true ] /NeverEmbed [ true ] /AntiAliasColorImages false /CropColorImages true /ColorImageMinResolution 290 /ColorImageMinResolutionPolicy /Warning /DownsampleColorImages true /ColorImageDownsampleType /Bicubic /ColorImageResolution 150 /ColorImageDepth 8 /ColorImageMinDownsampleDepth 1 /ColorImageDownsampleThreshold 1.33333 /EncodeColorImages true /ColorImageFilter /FlateEncode /AutoFilterColorImages false /ColorImageAutoFilterStrategy /JPEG /ColorACSImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /ColorImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /JPEG2000ColorACSImageDict << /TileWidth 256 /TileHeight 256 /Quality 30 >> /JPEG2000ColorImageDict << /TileWidth 256 /TileHeight 256 /Quality 30 >> /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 290 /GrayImageMinResolutionPolicy /Warning /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 150 /GrayImageDepth 8 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.33333 /EncodeGrayImages true /GrayImageFilter /FlateEncode /AutoFilterGrayImages false /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /GrayImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /JPEG2000GrayACSImageDict << /TileWidth 256 /TileHeight 256 /Quality 30 >> /JPEG2000GrayImageDict << /TileWidth 256 /TileHeight 256 /Quality 30 >> /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 800 /MonoImageMinResolutionPolicy /Warning /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 150 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.33333 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict << /K -1 >> /AllowPSXObjects false /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile (None) /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False /CreateJDFFile false /Description << /CHS <FEFF4f7f75288fd94e9b8bbe5b9a521b5efa7684002000410064006f006200650020005000440046002065876863900275284e8e9ad88d2891cf76845370524d53705237300260a853ef4ee54f7f75280020004100630072006f0062006100740020548c002000410064006f00620065002000520065006100640065007200200035002e003000204ee553ca66f49ad87248672c676562535f00521b5efa768400200050004400460020658768633002> /CHT <FEFF4f7f752890194e9b8a2d7f6e5efa7acb7684002000410064006f006200650020005000440046002065874ef69069752865bc9ad854c18cea76845370524d5370523786557406300260a853ef4ee54f7f75280020004100630072006f0062006100740020548c002000410064006f00620065002000520065006100640065007200200035002e003000204ee553ca66f49ad87248672c4f86958b555f5df25efa7acb76840020005000440046002065874ef63002> /DAN <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> /DEU <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> /ESP <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> /FRA <FEFF005500740069006c006900730065007a00200063006500730020006f007000740069006f006e00730020006100660069006e00200064006500200063007200e900650072002000640065007300200064006f00630075006d0065006e00740073002000410064006f00620065002000500044004600200070006f0075007200200075006e00650020007100750061006c0069007400e90020006400270069006d007000720065007300730069006f006e00200070007200e9007000720065007300730065002e0020004c0065007300200064006f00630075006d0065006e00740073002000500044004600200063007200e900e90073002000700065007500760065006e0074002000ea0074007200650020006f007500760065007200740073002000640061006e00730020004100630072006f006200610074002c002000610069006e00730069002000710075002700410064006f00620065002000520065006100640065007200200035002e0030002000650074002000760065007200730069006f006e007300200075006c007400e90072006900650075007200650073002e> /ITA <FEFF005500740069006c0069007a007a006100720065002000710075006500730074006500200069006d0070006f007300740061007a0069006f006e00690020007000650072002000630072006500610072006500200064006f00630075006d0065006e00740069002000410064006f00620065002000500044004600200070006900f900200061006400610074007400690020006100200075006e00610020007000720065007300740061006d0070006100200064006900200061006c007400610020007100750061006c0069007400e0002e0020004900200064006f00630075006d0065006e007400690020005000440046002000630072006500610074006900200070006f00730073006f006e006f0020006500730073006500720065002000610070006500720074006900200063006f006e0020004100630072006f00620061007400200065002000410064006f00620065002000520065006100640065007200200035002e003000200065002000760065007200730069006f006e006900200073007500630063006500730073006900760065002e> /JPN <FEFF9ad854c18cea306a30d730ea30d730ec30b951fa529b7528002000410064006f0062006500200050004400460020658766f8306e4f5c6210306b4f7f75283057307e305930023053306e8a2d5b9a30674f5c62103055308c305f0020005000440046002030d530a130a430eb306f3001004100630072006f0062006100740020304a30883073002000410064006f00620065002000520065006100640065007200200035002e003000204ee5964d3067958b304f30533068304c3067304d307e305930023053306e8a2d5b9a306b306f30d530a930f330c8306e57cb30818fbc307f304c5fc59808306730593002> /NLD (Gebruik deze instellingen om Adobe PDF-documenten te maken die zijn geoptimaliseerd voor prepress-afdrukken van hoge kwaliteit. De gemaakte PDF-documenten kunnen worden geopend met Acrobat en Adobe Reader 5.0 en hoger.) /NOR <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> /PTB <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> /SUO <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> /SVE <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> /ENU (Use these settings to create Adobe PDF documents best suited for high-quality prepress printing. Created PDF documents can be opened with Acrobat and Adobe Reader 5.0 and later.) /KOR <FEFFc7740020c124c815c7440020c0acc6a9d558c5ec0020ace0d488c9c80020c2dcd5d80020c778c1c4c5d00020ac00c7a50020c801d569d55c002000410064006f0062006500200050004400460020bb38c11cb97c0020c791c131d569b2c8b2e4002e0020c774b807ac8c0020c791c131b41c00200050004400460020bb38c11cb2940020004100630072006f0062006100740020bc0f002000410064006f00620065002000520065006100640065007200200035002e00300020c774c0c1c5d0c11c0020c5f40020c2180020c788c2b5b2c8b2e4002e> >> /Namespace [ (Adobe) (Common) (1.0) ] /OtherNamespaces [ << /AsReaderSpreads false /CropImagesToFrames true /ErrorControl /WarnAndContinue /FlattenerIgnoreSpreadOverrides false /IncludeGuidesGrids false /IncludeNonPrinting false /IncludeSlug false /Namespace [ (Adobe) (InDesign) (4.0) ] /OmitPlacedBitmaps false /OmitPlacedEPS false /OmitPlacedPDF false /SimulateOverprint /Legacy >> << /AddBleedMarks false /AddColorBars false /AddCropMarks false /AddPageInfo false /AddRegMarks false /ConvertColors /ConvertToCMYK /DestinationProfileName () /DestinationProfileSelector /DocumentCMYK /Downsample16BitImages true /FlattenerPreset << /PresetSelector /MediumResolution >> /FormElements false /GenerateStructure false /IncludeBookmarks false /IncludeHyperlinks false /IncludeInteractive false /IncludeLayers false /IncludeProfiles false /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe) (CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector /DocumentCMYK /PreserveEditing true /UntaggedCMYKHandling /LeaveUntagged /UntaggedRGBHandling /UseDocumentProfile /UseDocumentBleed false >> ] >> setdistillerparams << /HWResolution [2400 2400] /PageSize [2834.646 2834.646] >> setpagedevice