TPP 5 - Consolidated Project Management Plan (Group)

profilejarfra
AppendixD-TeamBusinessProjectRiskAssessment.xlsx

Risk Register

WBS Task Name Task Level Risk Description Risk Category (Risk Type) Risk Probability Risk Consequence (Impact) Initial Risk Score (Probability * Impact) Risk Handling Category Risk Handling/Control Plan Risk Owner (Risk Manager) Cost
1 Mamma's Sandwich Shoppe & Bakery 0 $51,966.99
1.1 Project Start 1 $0.00
1.2 Project Management 1 $5,932.97
1.2.1 Initiation 2 $2,925.81
1.2.1.1 Initial Project Meeting 3 Customer non-responsive or schedule conflicts People 10% $784.68 $78.47 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Project Manager $784.68
1.2.1.2 Inputs 3 $189.35
1.2.1.2.1 Business Case 4 Business case becomes obsolete or is undermined by external or internal changes Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Complete a business case if not already provided Ensure purpose is well defined within the Project Charter Project Sponsor $0.00
1.2.1.2.2 Environmental Factors 4 Acts of God and lead to loss of resources, materials, and premises Environmental 10% $113.61 $11.36 Accept Ensure insurance for resource materials are in place Provide project team with emergency procedures Project Manager $113.61
1.2.1.2.3 Organizational Processes 4 Organizational processes are not clearly defined or understood Client 25% $75.74 $18.94 Mitigate Analyze organizational processes and document within process workflows Ensure processes are well defined within the Project Charter Project Sponsor $75.74
1.2.1.3 Outputs 3 $1,951.78
1.2.1.3.1 Project Charter 4 Project design and deliverable definition is incomplete Technical, Cost, Schedule 25% $1,072.00 $268.00 Mitigate Define the scope in detail using input from subject matter experts Project Manager $1,072.00
1.2.1.3.2 Kickoff Meeting 4 Customer non-responsive or schedule conflicts Schedule 10% $209.78 $20.98 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Project Manager $209.78
1.2.1.3.3 Progress Review Meeting 4 $670.00
1.2.1.3.3.1 Project Status Meeting 1 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.2 Project Status Meeting 2 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.3 Project Status Meeting 3 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.4 Project Status Meeting 4 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.5 Project Status Meeting 5 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.6 Project Status Meeting 6 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.7 Project Status Meeting 7 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.8 Project Status Meeting 8 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.9 Project Status Meeting 9 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.10 Project Status Meeting 10 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.2 Initiation COMPLETE 2 $0.00
1.2.3 Planning 2 $3,007.16
1.2.3.1 Activity Planning 3 $134.00
1.2.3.1.1 Activity Definitions 4 Project activity definitions are incomplete Technical 25% $33.50 $8.38 Mitigate Identify all logical relationships to generate full network activity Ensure schedules remain flexible and dynamic so that durations can be immediately transmitted to remaining project activities for accurate scheduling Project Manager $33.50
1.2.3.1.2 Activity Sequences 4 Unplanned work must be accomodated Schedule 15% $33.50 $5.03 Accept Assess and prioritize unplanned work based on weighted score (value versus complexity) Communicate with Project Sponsor and Project team on the impact and determine if priorities must be shifted to address issues Project Manager $33.50
1.2.3.1.3 Activity Resources 4 Lack of resources pose risk at meeting project goals Contractual 10% $33.50 $3.35 Mitigate Track and analyze resources using resource leveling techniques Adjust project resource's workloads in accordance with estimated risks and availability Project Manager $33.50
1.2.3.1.4 Activity Durations 4 Pressure to reduce activity durations increase risk of errors Schedule 15% $33.50 $5.03 Mitigate Share the schedule with key stakeholders to reduce the risk of scope creep and errors Project Manager $33.50
1.2.3.2 Scope Management 3 $268.00
1.2.3.2.1 Project WBS 4 Unplanned work must be accommodated Schedule 15% $268.00 $40.20 Accept Assess and prioritize unplanned work based on weighted score (value versus complexity) Communicate with Project Sponsor and Project team on the impact and determine if priorities must be shifted to address issues Project Manager $268.00
1.2.3.3 Project Cost Planning 3 $1,364.04
1.2.3.3.1 Cost Estimates 4 Cost estimate exceeds project budget Financial 5% $1,212.48 $60.62 Mitigate Build in 10% contingency on costs and scheduling Use two methods of cost estimation (parametric and engineering estimate) to cross refence and provide accuracy Project Manager $1,212.48
1.2.3.3.2 Project Budget 4 Cost estimate exceeds project budget Financial 5% $151.56 $7.58 Mitigate Build in 10% contingency on costs and scheduling Cross reference cost estimates to Work Breakdown Structure (WBS) to determine of resources are appropriately aligned Project Manager $151.56
1.2.3.4 Procurement Management 3 $303.12
1.2.3.4.1 IT System Purchases/Acquisitions 4 Project funding is reduced Financial 5% $151.56 $7.58 Mitigate Closely monitor all costs in real-time to ensure activites stay aligned with approved budget Consult with Project Sponsor and Finance to plan for budget reductions based on the tolerance for risk Project Sponsor $151.56
1.2.3.4.2 IT System Contracting 4 Ineffective workflows delay in contract approvals Contractual 5% $151.56 $7.58 Mitigate Specify deadlines for performance of all stages of the agreement Consult with Project Sponsor to suspend or delay contractual work Project Sponsor $151.56
1.2.3.5 Risk Management 3 $402.00
1.2.3.5.1 Project Risks 4 Errors with estimating risks Technical 10% $201.00 $20.10 Mitigate Continuously monitor and improve upon risks Mitigate most probable and threatening risks first Consult with Project Sponsor on decision-making process Project Manager $201.00
1.2.3.5.2 Risk Responses 4 Risk responses are not clearly defined or understood Technical 10% $201.00 $20.10 Mitigate Ensure risk responses are accurate and clearly defined Consult with Project Sponsor and key stakeholders to gain acceptance Project Manager $201.00
1.2.3.6 Communication Plan 3 Lack of clarity increases number of impromptu meetings and decreases productivity Cost, Schedule, Client 25% $0.00 $0.00 Mitigate Incorporate communication frequency, goals, and key stakeholders (audience) for each communication event Use the most appropriate channel of communication for target audience such as email, face-to-face, or phone calls Project Manager $0.00
1.2.3.7 Project Schedule 3 Delay in earlier project phases jeopardizes ability to meet fixed date Schedule 25% $536.00 $134.00 Mitigate Ensure the project plan is accurate using the work breakdown structure as reference Use tracking Gantt to preemptively identify schedule slippage Project Manager $536.00
1.2.4 Planning COMPLETE 2 $0.00
1.3 IT System Design 1 $2,021.70
1.3.1 IT Contractors 2 $268.00
1.3.1.1 Interviews 3 Lack of participation from qualified candidates People 25% $268.00 $67.00 Mitigate Identify alternative sources to market job requisitions such as the employment of technical recruiters or staffing agencies Project Manager $268.00
1.3.1.2 Hiring 3 Delays in onboarding consultant and/or contractor resources Contractual 25% $0.00 $0.00 Mitigate Build in and protect lead times within the schedule to allow for onboarding of consultant and/or contractor resources Escalate to Project Sponsor and incorporate late penalties within the contract Project Sponsor $0.00
1.3.2 Initial Design Specification 2 Project design and deliverable definition is incomplete Technical 20% $1,326.26 $265.25 Mitigate Define the scope in detail using input from subject matter experts Systems Engineer $1,326.26
1.3.3 Review Design Specification 2 Participants non-responsive or schedule conflicts Schedule 5% $427.44 $21.37 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Consulting Architect $427.44
1.3.4 Deliver Design Specification 2 Project sponsor refuses to approve deliverables or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Manager $0.00
1.4 System Networking 1 $750.85
1.4.1 Networking Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Consulting Architect $282.11
1.4.2 Networking Procurement 2 Networking equipment delayed in shipment Contractual, Cost, Schedule 15% $34.75 $5.21 Transfer Insure the shipment/parcel Contact Verizon (vendor) and request expedited shipment Project Sponsor $34.75
1.4.3 Networking Installation 2 Technical difficulties building and installing network components Technical, Schedule 5% $433.99 $21.70 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assit in the deployment of network services Delay project if necessary Systems Engineer $433.99
1.5 System Hardware 1 $3,598.90
1.5.1 Hardware Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Consulting Architect $282.11
1.5.2 Hardware Procurement 2 Hardware is delayed in shipment Contractual, Cost, Schedule 15% $2,432.80 $364.92 Transfer Insure the shipment/parcel Contact Toast (vendor) and request expedited shipment Project Sponsor $2,432.80
1.5.3 Hardware Installation 2 Technical difficulties building and installing hardware components Technical, Schedule 30% $883.99 $265.20 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $883.99
1.6 System Software 1 $5,361.15
1.6.1 Software Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Project Manager $282.11
1.6.2 Software Procurement 2 Unable to download software from online portal Financial, Contractual, Technical 15% $18.95 $2.84 Transfer Contact Oracle (vendor) support and open up support request Access mirror portal and download software packages/binaries from alternate location Project Sponsor $18.95
1.6.3 Software Installation 2 $5,060.10
1.6.3.1 Point of Sales Software 3 $1,817.32
1.6.3.1.1 Install Software 4 Technical difficulties in installing POS software Technical 25% $1,401.24 $350.31 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $1,401.24
1.6.3.1.2 Test POS Software 4 Project sponsor does not accept the system due to lack of functionality or capabilities Cost, Schedule, Technical 5% $416.08 $20.80 Mitigate Depending on severity, either send back to engineer for correction or identify new resource with skillsets that aligns with customer requirements Delay project if necessary Project Manager $416.08
1.6.3.2 ERP Software 3 $1,945.87
1.6.3.2.1 Install Software 4 Technical difficulties in installing ERP software Technical 25% $652.83 $163.21 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $652.83
1.6.3.2.2 Test Software 4 Project sponsor does not accept the system due to lack of functionality or capabilities Cost, Schedule, Technical 5% $1,293.04 $64.65 Mitigate Consult with stakeholders on requirements in accordance with business case Identify gaps in software and incorporate revisions to correct missing features and capabilities Project Manager $1,293.04
1.6.3.3 Website 3 $1,296.91
1.6.3.3.1 Code Webpage 4 Incomplete/Incorrect requirements result in need to restart development of webpage Technical, Schedule 25% $696.75 $174.19 Mitigate Open discussion with Project Sponsor and key stakeholders to identify issues and prepare change requests Web Developer $696.75
1.6.3.3.2 Test Webpage 4 Project sponsor does not accept webpage, requires rework Cost, Schedule, Technical 5% $600.16 $30.01 Mitigate Depending on severity, either send back to developer for correction or identify new developer with skillsets that aligns with customer requirements Delay project if necessary Project Manager $600.16
1.7 System Test 1 $21,537.20
1.7.1 Integrate System Components 2 Problems of integration with internal and external systems Cost, Schedule, Technical 25% $4,217.60 $1,054.40 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Consult with external (vendor) technical experts to identify remediation steps to properly integrate with external systems Consulting Architect $4,217.60
1.7.2 Test Integrated Components 2 Difficulty in integrating modules/components due to lack of functionality Technical 15% $17,319.60 $2,597.94 Mitigate Identify gaps in software and hardware components Incorporate revisions to correct missing features and capabilities Implement agile method to break down modules into smaller iterations and tackle integration issues piece by piece Project Manager $17,319.60
1.7.3 Deliver IT System 2 Project sponsor refuses to approve deliverable or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $0.00
1.8 System Transition 1 $9,232.56
1.8.1 Prepare System Documentation 2 System documentation design is incomplete Technical 20% $4,746.24 $949.25 Mitigate Define the scope in detail using input from subject matter experts Project Manager $4,746.24
1.8.2 Review System Documentation 2 Participants non-responsive or schedule conflicts People, Schedule 5% $481.72 $24.09 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $481.72
1.8.3 Deliver System Documentation 2 Project sponsor refuses to approve deliverables or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $0.00
1.8.4 Provide Staff Training 2 Sheduling issues with customer personnel Schedule 15% $4,004.60 $600.69 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Delay training until full-participation can be provided Project Manager $4,004.60
1.9 Project Closure 1 $3,531.66
1.9.1 Document Lessons Learned 2 Participants non-responsive or schedule conflicts People, Schedule 5% $2,997.28 $149.86 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $2,997.28
1.9.2 Update Project Files 2 Participants non-responsive or schedule conflicts People, Schedule 5% $134.00 $6.70 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $134.00
1.9.3 Project Closure Meeting 2 $134.00
1.9.3.1 Gain Formal Acceptance 3 Project sponsor refuses to approve deliverable or delays approval Client, Cost, Schedule 10% $134.00 $13.40 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $134.00
1.9.4 Archive Project Files 2 Project files are misplaced, deleted/erased, or incomplete Client, Schedule 5% $134.00 $6.70 Mitigate Provide shared storage capability that allows for version control, recovery, and team collaboration Provide private Uniformed Resource Locator (URL) hyperlink to Project Sponsor for information dissemination Project Manager $134.00
1.9.5 Release Resources 2 Resources are prematurely released Cost, Contractual, Schedule 5% $132.38 $6.62 Mitigate Ensure the project plan and schedule are accurately followed Project Manager $132.38
1.1 Project Close 1 $0.00
Total $51,967.00 $8,052.90
15% of cost at risk

Dropdown Lists

Low Accept Technical
Medium Mitigate Cost
High Transfer Schedule
Client
Contractual
Weather
Financial
Political
Environmental
People