Customer Success Story

profilepurpletowel17
Agile-Watefall-Milestones.xlsx

Agile Approach

WeLoveVideo, Inc. CRM project
AGILE APPROACH
PHASES ITERATIVE SUB PHASES DAYS START FINISH PREDICESSOR
1 Iteration 1 5 days 4/5/19 8:00 4/11/19 17:00
2 Planning 1 day 4/5/19 8:00 4/5/19 17:00
3 Requirements Analaysis 1 day 4/8/19 8:00 4/8/19 17:00 2
4 Design 1 day 4/9/19 8:00 4/9/19 17:00 3
5 Building 1 day 4/10/19 8:00 4/10/19 17:00 4
6 Acceptance Testing 1 day 4/11/19 8:00 4/11/19 17:00 5
7 Iteration 2 5 days 4/5/19 8:00 4/11/19 17:00
8 Planning 1 day 4/5/19 8:00 4/5/19 17:00
9 Requirements Analaysis 1 day 4/8/19 8:00 4/8/19 17:00 8
10 Design 1 day 4/9/19 8:00 4/9/19 17:00 9
11 Building 1 day 4/10/19 8:00 4/10/19 17:00 10
12 Acceptance Testing 1 day 4/11/19 8:00 4/11/19 17:00 11
13 Iteration 3 5 days 4/12/19 8:00 4/18/19 17:00
14 Planning 1 day 4/12/19 8:00 4/12/19 17:00 12
15 Requirements Analaysis 1 day 4/15/19 8:00 4/15/19 17:00 14
16 Design 1 day 4/16/19 8:00 4/16/19 17:00 15
17 Building 1 day 4/17/19 8:00 4/17/19 17:00 16
18 Acceptance Testing 1 day 4/18/19 8:00 4/18/19 17:00 17
19 Iteration 4 5 days 4/19/19 8:00 4/25/19 17:00
20 Planning 1 day 4/19/19 8:00 4/19/19 17:00 18
21 Requirements Analaysis 1 day 4/22/19 8:00 4/22/19 17:00 20
22 Design 1 day 4/23/19 8:00 4/23/19 17:00 21
23 Building 1 day 4/24/19 8:00 4/24/19 17:00 22
24 Acceptance Testing 1 day 4/25/19 8:00 4/25/19 17:00 23
25 Iteration 5 5 days 4/26/19 8:00 5/2/19 17:00
26 Planning 1 day 4/26/19 8:00 4/26/19 17:00 24
27 Requirements Analaysis 1 day 4/29/19 8:00 4/29/19 17:00 26
28 Design 1 day 4/30/19 8:00 4/30/19 17:00 27
29 Building 1 day 5/1/19 8:00 5/1/19 17:00 28
30 Acceptance Testing 1 day 5/2/19 8:00 5/2/19 17:00 29
31 Deployment 1 day 5/3/19 8:00 5/3/19 17:00 30
32 Maintainance 5 days 5/6/19 8:00 5/10/19 17:00
33 Planning 1 day 5/6/19 8:00 5/6/19 17:00 31
34 Requirements Analaysis 1 day 5/7/19 8:00 5/7/19 17:00 33
35 Design 1 day 5/8/19 8:00 5/8/19 17:00 34
36 Building 1 day 5/9/19 8:00 5/9/19 17:00 35
37 Acceptance Testing 1 day 5/10/19 8:00 5/10/19 17:00 36

Waterfall Model

WeLoveVideo, Inc. CRM project
WATERFALL APPROACH
PHASES ITERATIVE SUB PHASES DAYS START FINISH PREDICESSOR
1 Planning 15 days 4/5/19 8:00 4/25/19 17:00
2 Project Scope Analysis 5 days 4/5/19 8:00 4/11/19 17:00
3 Feasibility Analysis 5 days 4/12/19 8:00 4/18/19 17:00 2
4 Quality Assurance 5 days 4/19/19 8:00 4/25/19 17:00 3
5 Requirement Analaysis 20 days 4/26/19 8:00 5/23/19 17:00
6 Functional Requirements 5 days 4/26/19 8:00 5/2/19 17:00 4
7 Non-functional requiremetns 5 days 5/3/19 8:00 5/9/19 17:00 6
8 Hardware Requirements 5 days 5/10/19 8:00 5/16/19 17:00 7
9 Software Requirements 5 days 5/17/19 8:00 5/23/19 17:00 8
10 System Design 70 days 5/24/19 8:00 8/29/19 17:00
11 Conceptual Design 10 days 5/24/19 8:00 6/6/19 17:00 9
12 Logical Design 10 days 6/7/19 8:00 6/20/19 17:00 11
13 Physical Design 20 days 6/21/19 8:00 7/18/19 17:00 12
14 Coding 30 days 7/19/19 8:00 8/29/19 17:00 13
15 Implementation 3 days 8/30/19 8:00 9/3/19 17:00 14
16 Testing 11 days 9/4/19 8:00 9/18/19 17:00
17 Unit testing 3 days 9/4/19 8:00 9/6/19 17:00 15
18 Integratopm testing 3 days 9/9/19 8:00 9/11/19 17:00 17
19 Acceptance testing 5 days 9/12/19 8:00 9/18/19 17:00 18
20 Deployment 2 days 9/19/19 8:00 9/20/19 17:00 19
21 Maintenance 5 days 9/23/19 8:00 9/27/19 17:00 20