| WeLoveVideo, Inc. CRM project | ||||||
| AGILE APPROACH | ||||||
| PHASES | ITERATIVE SUB PHASES | DAYS | START | FINISH | PREDICESSOR | |
| 1 | Iteration 1 | 5 days | 4/5/19 8:00 | 4/11/19 17:00 | ||
| 2 | Planning | 1 day | 4/5/19 8:00 | 4/5/19 17:00 | ||
| 3 | Requirements Analaysis | 1 day | 4/8/19 8:00 | 4/8/19 17:00 | 2 | |
| 4 | Design | 1 day | 4/9/19 8:00 | 4/9/19 17:00 | 3 | |
| 5 | Building | 1 day | 4/10/19 8:00 | 4/10/19 17:00 | 4 | |
| 6 | Acceptance Testing | 1 day | 4/11/19 8:00 | 4/11/19 17:00 | 5 | |
| 7 | Iteration 2 | 5 days | 4/5/19 8:00 | 4/11/19 17:00 | ||
| 8 | Planning | 1 day | 4/5/19 8:00 | 4/5/19 17:00 | ||
| 9 | Requirements Analaysis | 1 day | 4/8/19 8:00 | 4/8/19 17:00 | 8 | |
| 10 | Design | 1 day | 4/9/19 8:00 | 4/9/19 17:00 | 9 | |
| 11 | Building | 1 day | 4/10/19 8:00 | 4/10/19 17:00 | 10 | |
| 12 | Acceptance Testing | 1 day | 4/11/19 8:00 | 4/11/19 17:00 | 11 | |
| 13 | Iteration 3 | 5 days | 4/12/19 8:00 | 4/18/19 17:00 | ||
| 14 | Planning | 1 day | 4/12/19 8:00 | 4/12/19 17:00 | 12 | |
| 15 | Requirements Analaysis | 1 day | 4/15/19 8:00 | 4/15/19 17:00 | 14 | |
| 16 | Design | 1 day | 4/16/19 8:00 | 4/16/19 17:00 | 15 | |
| 17 | Building | 1 day | 4/17/19 8:00 | 4/17/19 17:00 | 16 | |
| 18 | Acceptance Testing | 1 day | 4/18/19 8:00 | 4/18/19 17:00 | 17 | |
| 19 | Iteration 4 | 5 days | 4/19/19 8:00 | 4/25/19 17:00 | ||
| 20 | Planning | 1 day | 4/19/19 8:00 | 4/19/19 17:00 | 18 | |
| 21 | Requirements Analaysis | 1 day | 4/22/19 8:00 | 4/22/19 17:00 | 20 | |
| 22 | Design | 1 day | 4/23/19 8:00 | 4/23/19 17:00 | 21 | |
| 23 | Building | 1 day | 4/24/19 8:00 | 4/24/19 17:00 | 22 | |
| 24 | Acceptance Testing | 1 day | 4/25/19 8:00 | 4/25/19 17:00 | 23 | |
| 25 | Iteration 5 | 5 days | 4/26/19 8:00 | 5/2/19 17:00 | ||
| 26 | Planning | 1 day | 4/26/19 8:00 | 4/26/19 17:00 | 24 | |
| 27 | Requirements Analaysis | 1 day | 4/29/19 8:00 | 4/29/19 17:00 | 26 | |
| 28 | Design | 1 day | 4/30/19 8:00 | 4/30/19 17:00 | 27 | |
| 29 | Building | 1 day | 5/1/19 8:00 | 5/1/19 17:00 | 28 | |
| 30 | Acceptance Testing | 1 day | 5/2/19 8:00 | 5/2/19 17:00 | 29 | |
| 31 | Deployment | 1 day | 5/3/19 8:00 | 5/3/19 17:00 | 30 | |
| 32 | Maintainance | 5 days | 5/6/19 8:00 | 5/10/19 17:00 | ||
| 33 | Planning | 1 day | 5/6/19 8:00 | 5/6/19 17:00 | 31 | |
| 34 | Requirements Analaysis | 1 day | 5/7/19 8:00 | 5/7/19 17:00 | 33 | |
| 35 | Design | 1 day | 5/8/19 8:00 | 5/8/19 17:00 | 34 | |
| 36 | Building | 1 day | 5/9/19 8:00 | 5/9/19 17:00 | 35 | |
| 37 | Acceptance Testing | 1 day | 5/10/19 8:00 | 5/10/19 17:00 | 36 |
Waterfall Model
| WeLoveVideo, Inc. CRM project | ||||||
| WATERFALL APPROACH | ||||||
| PHASES | ITERATIVE SUB PHASES | DAYS | START | FINISH | PREDICESSOR | |
| 1 | Planning | 15 days | 4/5/19 8:00 | 4/25/19 17:00 | ||
| 2 | Project Scope Analysis | 5 days | 4/5/19 8:00 | 4/11/19 17:00 | ||
| 3 | Feasibility Analysis | 5 days | 4/12/19 8:00 | 4/18/19 17:00 | 2 | |
| 4 | Quality Assurance | 5 days | 4/19/19 8:00 | 4/25/19 17:00 | 3 | |
| 5 | Requirement Analaysis | 20 days | 4/26/19 8:00 | 5/23/19 17:00 | ||
| 6 | Functional Requirements | 5 days | 4/26/19 8:00 | 5/2/19 17:00 | 4 | |
| 7 | Non-functional requiremetns | 5 days | 5/3/19 8:00 | 5/9/19 17:00 | 6 | |
| 8 | Hardware Requirements | 5 days | 5/10/19 8:00 | 5/16/19 17:00 | 7 | |
| 9 | Software Requirements | 5 days | 5/17/19 8:00 | 5/23/19 17:00 | 8 | |
| 10 | System Design | 70 days | 5/24/19 8:00 | 8/29/19 17:00 | ||
| 11 | Conceptual Design | 10 days | 5/24/19 8:00 | 6/6/19 17:00 | 9 | |
| 12 | Logical Design | 10 days | 6/7/19 8:00 | 6/20/19 17:00 | 11 | |
| 13 | Physical Design | 20 days | 6/21/19 8:00 | 7/18/19 17:00 | 12 | |
| 14 | Coding | 30 days | 7/19/19 8:00 | 8/29/19 17:00 | 13 | |
| 15 | Implementation | 3 days | 8/30/19 8:00 | 9/3/19 17:00 | 14 | |
| 16 | Testing | 11 days | 9/4/19 8:00 | 9/18/19 17:00 | ||
| 17 | Unit testing | 3 days | 9/4/19 8:00 | 9/6/19 17:00 | 15 | |
| 18 | Integratopm testing | 3 days | 9/9/19 8:00 | 9/11/19 17:00 | 17 | |
| 19 | Acceptance testing | 5 days | 9/12/19 8:00 | 9/18/19 17:00 | 18 | |
| 20 | Deployment | 2 days | 9/19/19 8:00 | 9/20/19 17:00 | 19 | |
| 21 | Maintenance | 5 days | 9/23/19 8:00 | 9/27/19 17:00 | 20 |