Project Management - Earned Value Management

profileSuperhero
Actuals-Project-Z.pdf

ACTUAL COST (AC) PROJECT Z Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

Work Package A $15 $15 $5 $0 $0 $0 Work Package B $0 $2 $12 $13 $18 $12 Work Package C $0 $0 $0 $0 $8 $9 Work Package D $0 $0 $0 $0 $0 $0

Total for Week, or Actual Cost (AC) $15 $17 $17 $13 $26 $21

CUMULATIVE % of ACTUAL WORK COMPLETE PROJECT Z Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

Work Package A Hours Worked 160 340 100 0 0 0 Work Package B Hours Worked 0 200 200 240 500 240 Work Package C Hours Worked 0 0 0 0 100 120 Work Package D Hours Worked 0 0 0 0 0 0

Total Hours Worked for Week 160 540 300 240 600 360 Cumulative Total Hours Worked for Week 160 700 1000 1240 1840 2200

Cumulative Percent of Actual Work Completed 4% 17.3% 25% 31% 45% 54%