Project Management - Earned Value Management
ACTUAL COST (AC) PROJECT Y Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Work Package A $22 $13 $0 $0 $0 $0 Work Package B $0 $10 $25 $18 $24 $8 Work Package C $0 $0 $0 $0 $10 $20 Work Package D $0 $0 $0 $0 $0 $0
Total for Week, or Actual Cost (AC) $22 $23 $25 $18 $34 $28
CUMULATIVE % of ACTUAL WORK COMPLETE PROJECT Y Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Work Package A Hours Worked 160 340 100 0 0 0 Work Package B Hours Worked 0 200 200 240 500 240 Work Package C Hours Worked 0 0 0 0 100 120 Work Package D Hours Worked 0 0 0 0 0 0
Total Hours Worked for Week 160 540 300 240 600 360 Cumulative Total Hours Worked for Week 160 700 1000 1240 1840 2200
Cumulative Percent of Actual Work Completed 4% 17.3% 25% 31% 45% 54%