Project Management - Earned Value Management
ACTUAL COST (AC) PROJECT X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Work Package A $22 $13 $0 $0 $0 $0 Work Package B $0 $10 $25 $18 $24 $8 Work Package C $0 $0 $0 $0 $10 $20 Work Package D $0 $0 $0 $0 $0 $0
Total for Week, or Actual Cost (AC) $22 $23 $25 $18 $34 $28
CUMULATIVE % of ACTUAL WORK COMPLETE PROJECT X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
Work Package A Hours Worked 320 440 140 0 0 0 Work Package B Hours Worked 0 200 200 200 540 300 Work Package C Hours Worked 0 0 0 0 120 40 Work Package D Hours Worked 0 0 0 0 0 0
Total Hours Worked for Week 320 640 340 200 660 340 Cumulative Total Hours Worked for Week 320 960 1300 1500 2160 2500
Cumulative Percent of Actual Work Completed 8% 24% 32.1% 37.0% 53% 61.7%