Activity I
Activity Description Predecessors Duration (Days)
A Site selection None 4
B Buy concessions A 4
C Rent facilities A 2
D Build stands A 5
E Generator & wiring installation C 2
F Security B 4
G Lighting installation E 2
H Sound system installation E, F 2
I Stage construction D 3
J Tear down G, H, I 4
Activity II
Activity Expected Duration Predecessors
A 4 days
B 9 days A
C 11 days A
D 5 days B
E 3 days B
F 7 days C
G 3 days D, F
H 2 days E, G
I 1 day H