Activity- 10 Exe Project

profileAmeychekka
Activity10ExeProject.docx

Given the following information, answer the questions about this project:

 

Activity

Expected Duration

Predecessors

A

4 days

B

9 days

A

C

11 days

A

D

5 days

B

E

3 days

B

F

7 days

C

G

3 days

D, F

H

2 days

E, G

I

1 day

H

1. Draw the network as a Gantt chart.

2. What is the critical path?  Which activities have slack time?

3. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration?  How would the critical path change?