operations management

profilejenny2000000
9_ProjectManagementII.pptx

Class 9: Project Management II

Instructor: Mani Lakshmanan

P300 Introduction to Operations Management

Review: Project Management

Project Planning

List Detailed Project Activities

Budgeting for Time and Cost

Detailed Scheduling Using the Critical Path Method (CPM)

Network diagram

Duration of a project

Critical path

Slack

2

A,0

3

B,3

I,3

D,5

C,5

E,6

F,4

J,14

K,2

L,1

G,3

H,1

0 0
0 0
0 5
1 6
0 3
0 3
3 6
3 6
6 11
6 11
11 17
11 17
17 21
17 21
21 24
21 24
3 17
7 21
3 5
18 20
5 6
20 21
24 25
24 25
ES EF
LS LF

Critical Path: The longest path from the beginning node to the end node in the project.

Outline

Project crashing: making time-cost trade-offs

Project Execution

Project progression measures

4

Project Crashing

Crashing a project

Need to accelerate the project due to time constraint

Need to speed up projects that are behind schedule

Deadlines have been changed

How best to spend more money (resources) to speed up a project

Project

Deliverables

Scope/Quality

(Better)

Schedule

(Faster)

Budget

(Cheaper)

5

Accelerate a Project with Minimal Costs

Q: Determine a cost-effective way to reduce the project completion time to 175 days.

A precedence table for designing and building a township playground:

6

Crash Time: the total time needed for the task after being accelerated!

Minimal-Cost Scheduling with Expediting

Step 1: Get the critical path diagram

A, 20

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 20

I, 30

7

A, 20

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 20

I, 30

150 170

80

80 110

120 140

140 150

150 160

170 200

120

0 20

0 20

30 90

90 120

120 140

20 120

140 150

150 170

160 170

170 200

Early Start/Finish and Late Start/Finish Times

8

10 days Slack

10 days Slack

Minimal-Cost Scheduling with Expediting

Step 1: Get the critical path diagram

Step 2: Determine which activities to accelerate

Step 3: Determine how long to accelerate

9

Acceleration vs. Cost

$20/day

$4/day

$15/day

$30/day

A, 20

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 20

I, 30

10 days Slack

10 days Slack

10

Duration: 200

Objective: 175 days

A, 20

B, 60

D, 30

C,90

E, 20

F, 10

H, 10

G, 20

I, 30

$20/day

$4/day

$15/day

$30/day

10 Days Reduced by Accelerating C

11

10 days Slack

Duration: 190

Objective: 175 days

10 days Slack

Optimal Acceleration Strategy

Step 1: Get the critical path diagram

Step 2: Determine which activities to accelerate

With only one critical path

The activities on critical path

The activity with the lowest accelerate cost

Accelerate only one activity one time

Step 3: Determine how long to accelerate. Stop when:

New critical path appears

Or the task reaches its shortest duration possible

12

A, 20

B, 60

D, 30

C,90

E, 20

F, 10

H, 10

G, 20

I, 30

$20/day

$4/day

$15/day

$30/day

Duration: 190

10 Days Reduced by Accelerating C

Objective: 175 days

13

10 days Slack

10 Days Reduced by Accelerating C & B Together

A, 20

B, 50

D, 30

C,80

E, 20

F, 10

H, 10

G, 20

I, 30

$20/day

$4/day

$15/day

$30/day

Duration: 180

Objective: 175 days

14

Minimal-Cost Scheduling with Expediting

Step 1: Use Single-Time-Estimate to get the critical path diagram

Step 2: Determine which activities to accelerate

With only one critical path (discussed before)

With more than one critical path. E.g. 2 critical paths:

One or two activities that can reduce both critical paths simultaneously

The combination of activities with lowest combined accelerate costs

Step 3: Determine how long to accelerate. Stop when:

New critical path appears

Or the task reaches its shortest duration possible

15

10 Days Reduced by Accelerating C & B Together

A, 20

B, 50

D, 30

C,80

E, 20

F, 10

H, 10

G, 20

I, 30

$20/day

$15/day

$30/day

Duration: 180

Objective: 175 days

16

5 Days Reduced by Accelerating A

A,15

B, 50

D, 30

C,80

E, 20

F, 10

H, 10

G, 20

I, 30

$20/day

$4/day

$15/day

$30/day

Duration: 175

17

Objective: 175 days

Exercise: What if We Change the Crash Cost:

Q: Determine a cost-effective way to reduce the project completion time to 155 days.

A precedence table for designing and building a township playground:

18

Crash Time: the total time needed for the task after being accelerated!

Acceleration vs. Cost

$30/day

$15/day

$4/day

$20/day

$25/day

$10/day

A, 20

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 20

I, 30

10 days Slack

10 days Slack

Duration: 200

19

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 20

I, 30

10 days Slack

10 days Slack

Duration: 195

$30/day

$15/day

$4/day

$20/day

$25/day

$10/day

20

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 60

D, 30

C,100

E, 20

F, 10

H, 10

G, 10

I, 30

10 days Slack

Duration: 185

$30/day

$15/day

$4/day

$25/day

$10/day

21

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 60

D, 30

C, 90

E, 20

F, 10

H, 10

G, 10

I, 30

Duration: 175

$30/day

$15/day

$4/day

$25/day

$10/day

22

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 60

D, 20

C, 80

E, 20

F, 10

H, 10

G, 10

I, 30

Duration: 165

$30/day

$15/day

$4/day

$25/day

$10/day

23

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 60

D, 20

C, 80

E, 20

F, 10

H, 5

G, 5

I, 30

Duration: 160

$30/day

$15/day

$25/day

$10/day

24

Objective: 155 days

Acceleration vs. Cost

A, 15

B, 55

D, 20

C, 75

E, 20

F, 10

H, 5

G, 5

I, 30

Duration: 155

$15/day

25

Objective: 155 days

Outline

Project Planning

4. Project crashing: making time-cost trade-offs

Project Execution

Project progression measures

26

Progression Measures

ACWP: actual cost (“value”) of work performed to date, also called Actual

BCWS: budgeted cost (“value”) of work scheduled (planned) to date

BCWP: budgeted cost (“value”) of work performed to date

27

Progression Measures

Example 1

BCWS = $100, BCWP = $105, ACWP = $95

Example 2

BCWS = $100, BCWP = $80, ACWP = $95

28

Project is $5 worth of work ahead schedule (BCWP – BCWS)

and $10 under budget (BCWP – ACWP).

Project is $20 worth of work behind schedule ($80-$100= -$20)

and $15 over budget ($80 - $95 =-$15).

32

Progression Measures

Time: Schedule Variance (SV) = BCWP-BCWS

In term of bucks

Compare between:

How much of work should be performed to date? (BCWS)

How much of work has been performed to date? (BCWP)

Cost: Cost Variance (CV) = BCWP-ACWP

Focus on the performed work

Compare between:

The actual cost (ACWP)

The budget cost (BCWP)

29

Activity Budget $ Scheduled % Performed % Actual (ACWP) BCWS BCWP
A $3,000 50% 30% $1,100
B $10,000 20% 40% $4,700
C $2,000 100% 100% $1,700
Total $7,500

Progression Measures

30

32

Activity Budget $ Scheduled % Performed % Actual (ACWP) BCWS BCWP
A $3,000 50% 30% $1,100 $900
B $10,000 20% 40% $4,700 $4,000
C $2,000 100% 100% $1,700 $2,000
Total $7,500 $6,900

Time: $_____ ahead of or behind schedule

Cost: $__________ above or below the budget.

$1,500
$2,000
$2,000
$5,500

Progression Measures

31

Activity Budget $ Scheduled % Performed % Actual (ACWP) BCWS BCWP
A $3,000 50% 30% $1,100 $900
B $10,000 20% 40% $4,700 $4,000
C $2,000 100% 100% $1,700 $2,000
Total $7,500 $6,900

Time: $1,400, or ($6,900 - $5,500) / $5,500 = 25.5% ahead of schedule

Cost: $600, or ($7,500 - $6,900) / $6,900 = 8.70% above the budget.

$1,500
$2,000
$2,000
$5,500

Progression Measures

32

Code Activity Time

(days)

Immediate

Predecessors

Cost Shortest

time

Possible

Accelration

Cost/day

A Planning 20 None $300 15 days $30

B Purchasing 60 A $2100 50 days $4

C Excavation 100 A $4000 75 days $20

D Sawing 30 B $2850 20 days $15

E Placement 20 C,D $500

F Assembly 10 E $200

G Infill 20 F $400

H Outfill 10 F $600

I Decoration 30 G,H $1350

Code

Activity

Time (days)

Immediate

Predecessors

Cost

Shortest time Possible

Accelration Cost/day

A

Planning

20

None

$300

15 days

$30

B

Purchasing

60

A

$2100

50 days

$4

C

Excavation

100

A

$4000

75 days

$20

D

Sawing

30

B

$2850

20 days

$15

E

Placement

20

C,D

$500

F

Assembly

10

E

$200

G

Infill

20

F

$400

H

Outfill

10

F

$600

I

Decoration

30

G,H

$1350

Code Activity Time

(days)

Immediate

Predecessors

Cost Shortest

time

possible

Crash

Cost/day

A Planning 20 None $300 15 days $20

B Purchasing 60 A $2100 50 days $15

C Excavation 100 A $4000 75 days $30

D Sawing 30 B $2850 20 days $4

E Placement 20 C,D $500

F Assembly 10 E $200

G Infill 20 F $400 5 days $25

H Outfill 10 F $600 5 days $10

I Decoration 30 G,H $1350

Code

Activity

Time (days)

Immediate

Predecessors

Cost

Shortest time possible

Crash Cost/day

A

Planning

20

None

$300

15 days

$20

B

Purchasing

60

A

$2100

50 days

$15

C

Excavation

100

A

$4000

75 days

$30

D

Sawing

30

B

$2850

20 days

$4

E

Placement

20

C,D

$500

F

Assembly

10

E

$200

G

Infill

20

F

$400

5 days

$25

H

Outfill

10

F

$600

5 days

$10

I

Decoration

30

G,H

$1350