Article Review
Personality and the Prediction of Team Performance
THOMAS A. O’NEILL* and NATALIE J. ALLEN
Department of Psychology, The University of Western Ontario, London, Ontario, Canada
Abstract: Although much is known about personality and individuals’ job performance, only a few studies have
considered the effects of team-level personality on team performance. Existing research examining the effects of
personality on team performance has found that, of the Big Five factors of personality, Conscientiousness is often themost
important predictor. Accordingly, we investigated the criterion validity of lower-level Conscientiousness traits to
determine whether any one trait is particularly predictive of team performance. In addition to Conscientiousness, we
examined the criterion validity of the other Big Five personality factors. We found that Conscientiousness and its facets
predicted team performance. Agreeableness, Extraversion and Neuroticism were not predictive of team performance,
whereas Openness had a modest negative relation with team performance. Copyright # 2010 John Wiley & Sons, Ltd.
Key words: team performance; team composition; personality; Big Five; narrow traits; personality facets
INTRODUCTION
The composition of a work team is defined by the individual
characteristics of its members. One implicit rationale
underlying the research on team composition is that
individual characteristics of team members (i.e. their
personalities, demographic characteristics, attitudes and so
on) serve as inputs that indirectly influence team perform-
ance through group processes (e.g. collaboration) and
emergent states (e.g. team cohesion). In other words, the
characteristics of team members affect the way in which a
team operates and its subsequent performance.
Personality, as a class of team composition variables, is
the focus of the present study. Over the past several years,
research on personality has received considerable attention
in the teams literature (e.g. Bell, 2007; Humphrey,
Hollenbeck, Meyer, & Ilgen, 2007; Peeters, van Tuijl, Rutte,
& Reymen, 2006). Interest in this topic continues for at least
two reasons. First, there is an intuitive appeal to the argument
that personality will influence team-related variables.
Conceptually, personality should be related to (a) team
knowledge, skills and abilities, (b) processes and emergent
states and (c) general dimensions of teamwork (e.g.
collaboration, supportive behaviour, team trust). Most of
these variables appear to be natural outgrowths of personality
and, therefore, one would expect personality to be a valid
predictor in many cases (see Halfhill, Sundstrom, Lahner,
Calderone, & Nielsen, 2005; Kichuk & Wiesner, 1998).
A second reason that personality continues to be
investigated in team settings is that it is a consistent and
important predictor of individuals’ job performance (e.g.
Barrick &Mount, 1991; Tett, Jackson, Rothstein, & Reddon,
1999). Extending these findings to the team level is needed as
organizations are increasingly turning to teamwork in an
effort to stay competitive in the global marketplace (Allen &
West, 2005; Kozlowski & Ilgen, 2006). Thus, research on
personality and team performance is an ongoing priority.
In this study, we collected personality data frommembers
of project design teams, operationalized those data at the
group level (e.g. using the group mean on each trait), and
correlated the resulting team-level personality scores with
team performance. Our purpose in this research was
threefold. First, we examined the extent to which any
content-relevant personality facets of Conscientiousness
could demonstrate superior prediction of team performance
relative to a broad Conscientiousness composite. An
investigation of this type is needed given that Conscien-
tiousness has been shown to be one of the most consistent Big
Five predictors of job performance and team performance,
but the criterion validity of its facets have rarely been
examined at the team level (but see LePine, 2003). Second,
we investigated whether any personality factors besides
Conscientiousness could be valid predictors of team
performance in the present context. Specifically, we assessed
the criterion validity of the other Big Five factors:
Agreeableneness, Extraversion, Neuroticism and Openness.
Third, when considered as a team-level construct, personality
has historically been operationalized in several ways. In this
study we provide new evidence regarding the criterion
validity of the four most common team-level personality
operationalizations.
TEAM-LEVEL PERSONALITY
Typically, the operationalization of personality variables at
the team level is accomplished by aggregating individual-
level personality scores using one of four group-level
European Journal of Personality, Eur. J. Pers. 25: 31–42 (2011)
Published online 4 April 2010 (wileyonlinelibrary.com) DOI: 10.1002/per.769
*Correspondence to: Thomas A. O’Neill, Department of Psychology, Social Science Centre, The University of Western Ontario, London, Ontario N6A 5C2, Canada. E-mail: [email protected]
Copyright # 2010 John Wiley & Sons, Ltd.
Received 29 July 2009
Revised 16 February 2010, Accepted 16 February 2010
indices: Mean, variance, minimum and maximum scores
(see Barrick, Stewart, Neubert, & Mount, 1998; Halfhill
et al., 2005; Williams & Allen, 2008). The particular
operationalization is usually chosen through a consideration
of the personality variable, the nature of the task, and how the
two are expected to interact (e.g. Allen & West, 2005; Hecht
& Allen, 1999; LePine, Hollenbeck, Ilgen, & Hedlund,
1997).
The mean approach involves computing the arithmetic
average of each team member’s score on the personality
variable. This approach is appropriate when the trait is
theorized to work additively—that is, when it is suspected
that the more (or less) team members possess the trait, the
better the team will perform. The variance approach indexes
the dispersion, or heterogeneity, of the trait across team
members. This operationalization is used when the
researcher believes a greater (or lesser) amount of variation
in the trait will be related to the criterion. Finally, sometimes
it is appropriate to consider only the team member with the
highest, or lowest, score on a trait (referred to as the
maximum or minimum approach, respectively), and refer to
that value as the team-level score. As an analogy, on an
assembly line, the number of units produced will often depend
on the slowest working team member, and, accordingly, the
minimum score on a trait such as Achievement could be most
predictive of team performance. Conversely, on a creativity
task, the teammember with the highest score on a trait such as
Innovation could be most responsible for the level of team
performance achieved (because a novel idea has only to
come from one team member). Theorizing about the most
appropriate operationalization for team personality is critical
as these may substantially affect the magnitude of person-
ality’s criterion validity (Moynihan & Peterson, 2004;
Williams & Allen, 2008).
In the most recent and comprehensive meta-analysis
examining relations between team-level personality and
performance, Bell (2007) found that, overall, team-level
personality does predict team performance. The findings for
lab studies were generally weak, likely because team
performance measurement in those studies tended to be
too coarse to detect small variations in behaviour related to
expressions of personality. Field studies in Bell’s meta-
analysis, however, demonstrated the strongest and most
consistent findings for Conscientiousness. Teams with high
means, high team member maximum and minimum scores
and low variance had the greatest performance levels
(Emotional Stability was coded in the socially desirable
direction). Other Big Five factors were predictive of team
performance, but not with the same magnitude and
consistency across operationalizations.
Given that Conscientiousness was the most consist-
ently predictive trait of team performance in Bell’s (2007)
meta-analysis, it is reasonable to consider that facets of
Conscientiousness might even be more predictive (see
Dudley, Orvis, Lebiecki, & Cortina, 2006). For example,
the factor of Conscientiousness encompasses several
more specific facets of personality, such as Industrious-
ness, Order, Self-Control, Responsibility, Traditionalism
and Virtue (see Roberts, Chernyshenko, Stark, & Gold-
berg, 2005). Arguably, some of these lower-level
personality variables belonging to the same higher-level
personality factor may correlate differently, in magnitude
or direction, from the others in the prediction of a
criterion (see Ashton, 1998; Ashton, Jackson, Paunonen,
Helmes, & Rothstein, 1995; Hough, 1992; LePine, 2003;
Paunonen, 1998, 2003). Reflecting on Bell’s meta-
analytic findings, as well as the literature demonstrating
the validity of narrow traits, we suggest that, in order to
maximize the predictive power of Conscientiousness as it
relates to team performance, criterion-relevant facets
ought to be considered.
The fact that personality variables other than Conscien-
tiousness (e.g. Agreeableness) were predictive of team
performance in Bell’s meta-analysis suggests that they, too,
may be relevant in the present study. As we will argue later,
our criterion, project team performance, could be associated
with certain team-level operationalizations of Agreeable-
ness, Extraversion, Neuroticism and Openness. Finally, the
method of operationalizing team personality (e.g. mean,
minimum) that will be most predictive of team performance
must also be considered in maximizing criterion validity. In
the section that follows we develop our predictions regarding
the operationalization that is, in the context of our study,
most theoretically appropriate for each personality factor and
facet included in this study.
THE PRESENT STUDY
Our sample consisted of concept design teams, composed of
engineering students, who worked interdependently for 6.5
months. The teams were engaged in an intensive, complex
engineering design task. The team members had shared
outcomes of significant value, and coordinated most work
dynamically and reciprocally (rather than through pooled or
sequential processes). These were classic ‘project teams’ as
they were created for a specific purpose and time frame, after
which they would disband (see Chiocchio & Essiembre,
2009). Knowledge of these contextual details was important
in generating predictions, outlined below.
The Big Five
In the present research we assessed the Big Five factors of
personality. In order to optimize their prediction of team
performance, we judged it most appropriate to operationalize
the Big Five factors, at the team-level, as follows:
Conscientiousness (mean), Agreeableness (mean), Neuroti-
cism (mean), Extraversion (variance) and Openness (maxi-
mum). Important theoretical rationales underlie the choice of
team personality operationalizations. Beginning with Con-
scientiousness, we contend that this factor captures a class of
attributes that manifest themselves as valuable resources,
such as achievement-striving, organization, planning and
task focus. The team may draw upon resources of this type to
accomplish its work (see LePine et al., 1997; Stewart, 2003).
An additive team-level conceptualization, using the mean
approach, is most appropriate in the present research because
32 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
the more team members are conscientious, the better the
team should perform (see also Barrick et al., 1998).
Similarly, Agreeableness represents a factor of personality
that can be expected to foster effective team interactions
because members are trusting, altruistic and cooperative.
Such teams could perform well because of their smooth
conflict resolution, and inclination towards open communi-
cation and information seeking (Peeters et al., 2006). We also
see Agreeableness as accumulating additively, as the more
members are characterized as agreeable, the more they
should have positive interactions, and in turn, create a higher
performing team. Regarding the personality factor Neuroti-
cism, most previous studies have found important relations
with team performance for the mean only (see Bell, 2007).
As Neuman, Wagner and Christiansen (1999) pointed out,
teams that are higher on Neuroticism will have difficulty
coordinating one another’s tasks and may experience
disruption from tempermental and/or impulsive team
members (see also Driskell, Hogan, & Salas, 1987). Thus,
we predicted that the mean operationalization of Neuroti-
cism would be most predictive of team performance relative
to other operationalizations.
Turning to Extraversion, we expected that the variance
operationalization would be the strongest predictor of team
performance for that trait. A team comprising all extraverts
could be expected to have high conflict as its members will
all be assertive and leadership oriented, and therefore, power
struggles are likely to emerge (see Barry & Stewart, 1997).
Conversely, a team composed of all introverts would likely
not perform well because members may not converse enough
to generate a compelling design idea and stay coordinated
during project work. A mix of introverts and extraverts (i.e.
heterogeneity) may characterize effective teams because
there will likely be fewer leadership battles, but enough
communication to keep the team coordinated and on track
towards effective task completion (see Mohammad &
Angell, 2003). Thus, we operationalized Extraversion using
the variance approach.
Finally, Openness was operationalized as the maximum
score. Given that the engineering projects in the present
study required that teams generate novel solutions to design
problems of their choosing, generating a creative solution or
approach to the project was critical. However, only one team
member is likely needed to generate an idea that other group
members can subsequently develop (see Valente, 1995).
Original and innovative ideas might be expected to come
from the member highest on Openness, which calls for the
maximum operationalization.
Conscientiousness facets
Recall that one purpose of this research was to investigate
whether any lower level personality facets, within the
Conscientiousness domain, would be especially predictive of
team performance. Regarding the selection of these narrow,
facet-level traits, we chose a subset that we expected, on an
a priori basis, to predict team performance on the project
teams’ tasks. To select the traits, we considered three sources
of content-relevant information that have been shown to lead
to effective a priori selection of criterion-relevant person-
ality traits (for a review, see O’Neill, Goffin, & Tett, 2009).
We began with a large pool comprising 35 narrow
personality traits found in two highly regarded and
established personality instruments: the Personality
Research Form (PRF; Jackson, 1989) and the Jackson
Personality Inventory-Revised (JPI-R; Jackson, 1994). A
sample of subject matter experts, comprising eight indus-
trial-organizational psychology faculty and graduate stu-
dents, rated the extent to which each trait would be most
likely to predict team performance (i.e. trait relevance for
predicting team performance; see also Goffin et al., 2009;
Paunonen & Ashton, 2001). These traits were a mix of
Conscientiousness-related and unrelated traits, but only
those with content overlapping with Conscientiousness were
considered in this research for reasons explained earlier.
Second, we examined the literature, including literature
reviews, theoretical articles, and empirical studies (e.g.
English, Griffith, & Steelman, 2004). Third, the character-
istics of the project teams’ tasks, and surrounding context,
were taken into account, and traits were aligned to this
context by theorizing about how they might relate to team
performance. Overall, this approach was consistent with
commonly used methods of identifying potentially job-
related personality traits (see Goffin et al., 2009; Raymark,
Schmit, & Guion, 1997; Tett & Guterman, 2000).
The result of the process outlined above was the selection
of four facets of Conscientiousness, to each of which we
assigned a specific trait operationalization for comparison
with the Big Five at the team level: Organization
(maximum), Cognitive Structure (maximum), Achievement
(mean) and Endurance (mean; see Table 1 for trait
definitions). These traits were identified by Ashton, Jackson,
Table 1. Narrow trait definitions
Personality variable Description
Organization Concerned with keeping personal effects and surroundings neat and organized; dislikes clutter, confusion, lack of organization; interested in developing methods for keeping materials methodically organized.
Cognitive structure Does not like ambiguity or uncertainty in information; wants all questions answered completely; desires to make decisions based upon definite knowledge, rather than upon guesses or probabilities.
Achievement Aspires to accomplish difficult tasks; maintains high standards and is willing towork towards distant goals; responds positively to competition; willing to put forth effort to attain excellence.
Endurance Willing to work long hours; doesn’t give up quickly on a problem; persevering, even in face of great difficulty; patient and unrelenting in work habits.
Note: Definitions modified from Jackson (1989, 1994).
Personality and team performance 33
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Helmes, and Paunonen (1998) as scales that chiefly define
the Conscientiousness factor. Important theoretical ration-
ales for each trait and team-level operationalization
accompanied these decisions, which are described next.
Organization was expected to be important for team
performance as individuals high on this trait should use their
time wisely and avoid procrastination. However, we
predicted that only one team member needed to be high
on Organization in order to manage the team and keep the
work structured and on schedule; thus, we operationalized
Organization using the maximum score within the team. We
also predicted that Cognitive Structure would be important
because individuals high on this trait want to carefully plan
out and research all aspects of a task before getting started.
Again, we expected that only one team member needed to
engage in this systematic planning and forethought to ensure
that the team effectively structured its work and adapted it as
needed over time. Accordingly, we selected the maximum
operationalization for Cognitive Structure.
Those who are high on Achievement tend to set difficult
goals by choosing challenging tasks that they find engaging
(Gellatly, 1996). We surmised that these attributes are
valuable qualities for any team members to possess, and that
the more team members are Achievement-oriented, the more
likely the team is to perform at a superior level. This additive
rationale supports the mean operationalization. We also
predicted that Endurance would be a valuable trait for all
team members to have. The more Endurance team members
have, the higher their team’s performance because members
will be more likely to devote long hours at various milestones
of the project lifecycle (e.g. prototype design, prototype
construction). Thus, the mean approach was used for
operationalizing Endurance.
METHOD
Participants, procedure, and description of teamwork
context
Team personality and performance data were collected from
129 student engineering design teams comprised of three,
four or five team members each. The mean age of the 564
respondents was 18.6 (SD ¼ 2.2), and 81% were male. Data were collected at two points: First, on the day that the project
teams were assembled, personality and demographic data
were collected; second, approximately 6.5 months later,
when the teams completed their work, team performance
data were collected.
Teams participating in this study carried out a complex
design project. Specifically, the project required teams to
develop a functional prototype that either (a) demonstrated
and explained a physical law in an innovative way that would
have pedagogical value in a secondary school setting, or (b)
represented an innovative concept that could help protect the
environment. In addition to building a physical prototype
demonstrating their design concepts, the project required
teams to produce a detailed report of their work and to deliver
a public ‘science fair’ presentation of the prototype.
Outcome interdependence was high given that instructor
ratings of team performance constituted 20% of students’
final course grades.
It should be noted that teammembers spent a great deal of
time interacting with one another over the course of the 6.5
months. In addition to completing the large design project,
teams worked on small course-related projects and tasks
almost every week for the duration of the 6.5 months. They
met for at least 2 hours per week in mandatory laboratory
sessions where they completed required tasks and assign-
ments together. Most of these teams also met extensively
outside of class time, especially during the 3 months prior to
completing the large design project that was our focal
interest in the present research.
Measures
Personality: Narrow traits
The following narrow trait scales from the PRF (Jackson,
1989) and JPI-R (Jackson, 1994) were administered:
Achievement (PRF), Endurance (PRF), Organization (JPI-
R) and Cognitive structure (PRF). Original scales included
20 items (JPI-R) or 16 items (PRF), but, because of time
constraints, we could administer scales that were only eight
items long. To select items, we retained an equal number of
positively- and negatively-keyed items. We also retained
items that were context-relevant, such as those that refer to
work styles and behaviour at work. Ratings were provided on
a typical five-point Likert scale ranging from 1 (strongly
disagree) to 5 (strongly agree).
Personality: Broad traits
Participants completed a version of Goldberg’s (1999)
International Personality Item Pool (IPIP) measure of the Big
Five personality factors, as described in Johnson (2001; see
also Hastings and O’Neill, 2009). The measure includes 24
items for each of the Big Five and uses the usual five-point
Likert scale ranging from 1 (very inaccurate) to 5 (very
accurate). The content measured is intended to reflect the
same content as is found in the NEO-PI-R (Costa &McCrae,
1992), and, supportively, high convergent correlations have
been reported (see Goldberg, 1999; Johnson, 2001).
Team performance
Team performance consisted of a composite of ratings on
several key dimensions associated with the design project.
These included Problem Definition, Design Methodology,
Engineering Validation (i.e. appropriate application of
engineering design principles), Design Documentation,
and Technical Writing. Team performance ratings were
provided by experienced course administrators. Because
administrators did not rate the same teams, interrater
reliability could not be assessed. Thus, we adopted
procedures typically used in similar situations (e.g. Wage-
man & Gordon, 2005). Specifically, to control for the
possibility that raters used different performance distri-
butions (i.e. mean and variance of distributions), we
standardized the composite performance scores within rater.
34 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
RESULTS
Cronbach’s as were calculated on the full sample of individual participants. Reliabilities for the narrow traits
ranged from .65 to .74, whereas for the Big Five they fell
between .81 and .88. Intercorrelations of team-level
personality operationalizations are displayed in Table 2.
That table shows that, whereas within-trait operationaliza-
tions tend to be correlated and are somewhat interdependent,
these correlations are not sufficiently large to suggest
completely overlapping constructs (see also Barrick et al.,
1998). Table 3 presents the mean and variance for each team-
level personality operationalization, as well as the zero-order
correlations among team-level personality and team per-
formance. Table 3 also identifies the trait operationalizations
that were expected to show the strongest team personality-
performance relations for each trait (see underlined values)
and the strongest observed correlations (see boldfaced
values).
Criterion validity of conscientiousness and selected
conscientiousness facets
The criterion validity of the Conscientiousness scale was
generally supported across operationalizations (see Table 3).
The mean was the strongest predictor of team performance,
r ¼ .27, followed by the maximum, r ¼ .21, and the minimum, r ¼ .19. In contrast to findings in Bell’s (2007) meta-analysis, the variance was not predictive of team
performance in this study.
Table 2. Team-level personality correlation matrix
1 2 3 4 5 6 7 8 9 10 11 12 13
Organization 1. Mean 2. Variance �.06 3. Minimum .76 �.57 4. Maximum .71 .56 .30 Cognitive Structure 5. Mean .44 �.03 .27 .27 6. Variance �.11 .19 �.20 .04 �.08 7. Minimum .34 �.14 .32 .14 .67 �.73 8. Maximum .25 .11 .07 .26 .68 .56 .11 Achievement 9. Mean .44 �.12 .35 .24 .30 .05 .14 .24 10. Variance �.14 .26 �.28 .06 .03 .12 �.05 .18 �.13 11. Minimum .43 �.21 .44 .18 .24 �.02 .16 .12 .80 �.61 12. Maximum .27 .10 .08 .28 .26 .12 .07 .33 .72 .51 .34 Endurance 13. Mean .33 .10 .06 .27 .32 .11 .12 .31 .42 .11 .27 .40 14. Variance �.15 .24 �.27 .04 �.01 .08 �.07 .08 .01 .47 �.25 .29 .08 15. Minimum .36 �.07 .32 .20 .27 .03 .17 .19 .37 �.27 .46 .14 .69 16. Maximum .13 .25 �.08 .24 .21 .11 .05 .27 .31 .39 .04 .51 .75 IPIP Conscientiousness 17. Mean .66 .00 .47 .49 .50 �.03 .31 .34 .49 �.10 .47 .37 .43 18. Variance .00 .25 �.13 .17 �.06 .20 �.13 .13 �.04 .21 �.15 .08 .01 19. Minimum .48 �.14 .44 .28 .35 �.16 .31 .12 .40 �.26 .50 .22 .29 20. Maximum .50 .18 .26 .53 .32 .06 .16 .33 .36 .04 .30 .39 .36 IPIP Extraversion 21. Mean �.05 .08 �.07 .03 �.22 .06 �.21 �.12 �.14 .07 �.18 �.07 .23 22. Variance .00 .13 �.12 .06 .06 �.05 .07 .01 .01 .08 .02 .12 �.04 23. Minimum �.04 �.04 .04 �.04 �.18 .08 �.19 �.10 �.12 �.03 �.11 �.16 .15 24. Maximum �.11 .15 �.20 .02 �.14 .03 �.15 �.08 �.15 .14 �.18 .02 .11 IPIP Agreeableness 25. Mean .16 �.05 .15 .09 .11 �.09 .12 .05 .25 �.17 .27 .09 .18 26. Variance .06 .00 .05 .05 .01 �.01 .03 .04 �.01 .19 �.09 .12 .03 27. Minimum .08 �.05 .09 .02 .06 �.09 .09 �.03 .17 �.24 .23 �.04 .08 28. Maximum .14 �.07 .13 .07 .08 �.11 .12 .06 .19 .03 .12 .17 .14 IPIP Neuroticism 29. Mean �.05 �.07 �.02 �.14 .07 �.09 .15 �.03 .05 �.07 .06 �.06 �.22 30. Variance �.10 .05 �.16 �.08 �.07 .07 �.14 �.08 �.02 .15 �.11 .05 �.07 31. Minimum .06 �.12 .15 �.07 .11 �.07 .19 .03 .04 �.20 .15 �.14 �.14 32. Maximum �.08 .01 �.13 �.11 .01 .02 �.02 �.05 .01 .07 �.07 .00 �.16 IPIP Openness 33. Mean �.11 �.07 �.04 �.14 �.09 �.03 �.04 �.08 .02 .02 .03 .06 .14 34. Variance �.09 .21 �.20 .06 �.01 .10 �.06 .13 �.03 .17 �.08 .13 .07 35. Minimum �.01 �.21 .14 �.16 �.05 �.07 .00 �.16 .03 �.11 .09 �.05 .05 36. Maximum �.14 .08 �.17 �.06 �.08 .02 �.08 .00 �.02 .13 �.06 .13 .10
Personality and team performance 35
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Turning to the narrow traits of Conscientiousness that
were identified a priori, all four were significantly related to
team performance using the predicted operationalization:
maximum Organization, r ¼ .30, maximum Cognitive Structure, r ¼ .20, mean Achievement, r ¼ .27 and mean Endurance, r ¼ .19. Further inspection of Table 3 reveals that the mean on facets of Conscientiousness were
significantly and positively related to team performance
for each facet, thereby supporting an additive trend for all
Conscientiousness-related traits. In addition, the maximum
was significantly related to team performance for all facets of
Conscientiousness other than for Achievement, although
minimum scores on Achievement were significantly related
to team performance.
In order to investigate the criterion validity of Conscien-
tiousness versus its facets, we created a unit-weighted
composite of Conscientiousness by summing our Conscien-
tiousness facet scores within each operationalization (e.g.
mean). This allowed us to make a direct comparison of
predictive validities between broad and narrow Conscien-
tiousness variables. Comparing criterion validities across
scales (i.e. the JPI/PRF facets versus the IPIP Conscien-
tiousness scale) could be confounded due to varying content
domains of the measures.
Some observations regarding the validities of the
Conscientiousness composite versus its facets are warranted
(see Table 3). First, there is some evidence that the broad
Conscientiousness composite is a stronger predictor of team
performance than are any of its narrow trait constituents. The
mean operationalization of the Conscientiousness composite
was its most predictive operationalization, r ¼ .31, which exceeded the prediction of all facet-level mean operation-
14 15 16 17 18 19 20 21 22
Organization 1. Mean 2. Variance 3. Minimum 4. Maximum Cognitive Structure 5. Mean 6. Variance 7. Minimum 8. Maximum Achievement 9. Mean 10. Variance 11. Minimum 12. Maximum Endurance 13. Mean 14. Variance 15. Minimum �.59 16. Maximum .67 .16 IPIP Conscientiousness 17. Mean �.05 .38 .28 18. Variance .24 �.15 .15 �.05 19. Minimum �.24 .43 .09 .73 �.61 20. Maximum .07 .25 .33 .74 .52 .31 IPIP Extraversion 21. Mean .01 .10 .13 �.06 .14 �.16 .03 22. Variance .08 �.04 .07 .05 .00 .07 .05 �.02 23. Minimum �.04 .09 .02 �.05 .10 �.13 �.01 .67 �.68 24. Maximum .11 �.03 .15 �.03 .10 �.11 .04 .71 .57 IPIP Agreeableness 25. Mean �.09 .20 .05 .35 �.03 .27 .28 .19 .04 26. Variance .20 �.13 .13 .05 .19 �.10 .14 .00 �.05 27. Minimum �.17 .19 �.06 .20 �.10 .21 .10 .13 .05 28. Maximum .14 �.01 .16 .30 .13 .10 .32 .17 .01 IPIP Neuroticism 29. Mean �.06 �.10 �.18 �.25 �.02 �.17 �.24 �.50 .08 30. Variance .19 �.16 .07 �.20 .13 �.26 �.11 �.12 .15 31. Minimum �.21 .06 �.24 �.09 �.07 .00 �.16 �.31 �.09 32. Maximum .09 �.17 �.04 �.28 .12 �.32 �.19 �.36 .10 IPIP Openness 33. Mean �.02 .09 .05 .04 �.10 .04 �.07 .29 .17 34. Variance .12 �.01 .11 �.14 .10 �.14 .00 .12 �.03 35. Minimum �.12 .11 �.05 .14 �.18 .14 �.09 .10 .18 36. Maximum .07 .02 .10 �.07 �.07 �.07 �.10 .25 .11
Table 2. (Continued)
36 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
alizations (correlations ranged from .19 to .30). Thus, for the
mean operationalization, these results suggest that sub-
optimal prediction may be obtained when considering only
the best-predicting facet of Conscientiousness.
Second, there were some indications that the narrow
Conscientiousness facets provided theoretically interesting
information. For example, the maximum Conscientiousness
composite significantly predicted team performance, but
maximum Organization was a slightly better predictor,
whereas the validity for maximum Achievement was small
and non-significant. We tested the difference in the
magnitudes of the criterion correlations involving maximum
Achievement and maximum Organization using Meng,
Rosenthal, and Rubin’s (1992) Z-test, but the difference was
not significant, Z ¼ 1.45, p > .05. Thus, the observed variability in the magnitude of these correlations could be
due to chance. Another case where lower-level facets
appeared to be potentially informative was for minimum
operationalizations of Conscientiousness-related traits.
Specifically, whereas the minimum operationalization of
the Conscientiousness composite was non-significant, the
minimum score on the facet of Achievement was signifi-
cantly related to team performance, r ¼ .23. Once again, however, the difference in the magnitudes of these criterion
correlations was not significant, Z ¼ 1.29, p > .05.
Criterion validity of other Big Five factors and a priori predictions
Criterion validities for Big Five personality variables other
than Conscientiousness were all non-significant except for
Openness (see Table 3). Note, however, that the findings for
23 24 25 26 27 28 29 30 31 32 33 34 35 36
Organization 1. Mean 2. Variance 3. Minimum 4. Maximum Cognitive Structure 5. Mean 6. Variance 7. Minimum 8. Maximum Achievement 9. Mean 10. Variance 11. Minimum 12. Maximum Endurance 13. Mean 14. Variance 15. Minimum 16. Maximum IPIP Conscientiousness 17. Mean 18. Variance 19. Minimum 20. Maximum IPIP Extraversion 21. Mean 22. Variance 23. Minimum 24. Maximum .16 IPIP Agreeableness 25. Mean .03 .08 26. Variance .07 .06 �.22 27. Minimum �.01 .01 .77 �.74 28. Maximum .06 .13 .69 .46 .23 IPIP Neuroticism 29. Mean �.36 �.32 �.31 .03 �.20 �.26 30. Variance �.23 �.01 �.15 .26 �.26 .04 .21 31. Minimum �.08 �.30 �.19 �.12 �.03 �.28 .70 �.45 32. Maximum �.33 �.20 �.30 .22 �.33 �.12 .73 .77 .18 IPIP Openness 33. Mean .03 .29 .25 .00 .14 .21 �.19 .09 �.26 �.09 34. Variance .09 .10 �.01 .13 �.06 .11 �.09 .09 �.21 �.02 .13 35. Minimum �.06 .14 .18 �.10 .17 .06 �.03 .01 .01 �.03 .68 �.57 36. Maximum .05 .27 .14 .08 .04 .21 �.13 .15 �.31 �.02 .71 .74 .10 Note: n ¼ 129. Correlations above .17 and .22 are significant at p < .05 and p < .01, respectively.
Table 2. (Continued)
Personality and team performance 37
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Openness were in the direction opposite to prediction. Taken
together, these results are surprising given the recent meta-
analysis (Bell, 2007) in which it was reported that all Big
Five personality factors were positively correlated with the
performance of field teams (i.e. with Emotional Stability
coded in the socially desirable direction). This may be due
partly to the nature of our criterion, which we examine in
greater depth later.
In addition to examining the criterion validities of the Big
Five and the facets of Conscientiousness, for each team-level
personality variable we hypothesized which operationaliza-
tion would be most strongly predictive of team performance
(see underlined coefficients in Table 3). A consideration of
context guided these predictions. Our predictions were
supported for nearly all factors and facets that were
significantly related to team performance: Conscientiousness
(mean), Organization (maximum), Cognitive Structure
(maximum) and Endurance (mean). That is, for these
important traits, our a priori predictions regarding which
trait operationalization would be most strongly related to
team performance were all supported. This supports previous
findings and theory emphasizing the advantages of linking
traits to criteria by considering the context and the nature of
the variables involved (e.g. Tett & Christiansen, 2007; Tett,
Jackson, & Rothstein, 1991). One of our predictions that was
not supported was the significant and negative relations
between Openness and team performance. We predicted the
maximum operationalization would be positively related to
team performance, but this finding was not supported,
r ¼ �.11, ns. However, other Openness correlations were significant, although in the direction contrary to prediction.
Mean and minimum Openness correlated significantly and
negatively with team performance, r ¼ �.16 and �.18, respectively.
DISCUSSION
Maximizing the validity of personality in the prediction of
workplace criteria is a top research priority (Rothstein &
Goffin, 2006). In this study, we investigated the extent to
which facets of team-level Conscientiousness could surpass
the predictive validity of a composite Conscientiousness
variable composed of those facets. We also reported the
criterion validity of Big Five traits other than Conscien-
tiousness, and the validity of a priori selected personality
trait operationalization at the team level. Perhaps the most
important finding of the present study was that the substrate
measured by Conscientiousness-related variables was, by
and large, the only predictive personality content regardless
of whether one considered facets, their composite, or the
separate IPIP Conscientiousness scale. Openness was the
Table 3. Means, standard deviations, and correlations between team-level personality variables and team performance
PRF/JPI scales IPIP Big Five scales
Variable Mean SD Team performance Variable Mean SD Team performance
Team Performance 8.33 .86 Organization Conscientiousness Mean 3.19 .33 .26�� Mean 3.62 .26 .27��
SD .54 .21 .13 SD .44 .18 S.03 Minimum 2.58 .43 .06 Minimum 3.13 .36 .19�
Maximum 3.81 .41 .30�� Maximum 4.11 .34 .21�
Cognitive Structure extraversion Mean 3.40 .25 .19� Mean 3.51 .26 .02 SD .47 .21 .11 SD .49 .20 .04 Minimum 2.83 .42 .01 Minimum 2.95 .38 S.04 Maximum 3.90 .34 .20� Maximum 4.04 .33 .05 Achievement Agreeableness Mean 3.40 .30 .27�� Mean 3.56 .26 .01 SD .48 .20 S.15 SD .44 .18 .01 Minimum 2.89 .43 .23�� Minimum 3.05 .39 S.05 Maximum 3.96 .40 .15 Maximum 4.03 .32 S.00 Endurance Neuroticism Mean 3.53 .27 .19� Mean 2.63 .32 S.05 SD .49 .22 .05 SD .50 .25 .09 Minimum 2.98 .39 .09 Minimum 2.07 .33 S.08 Maximum 4.07 .42 .17� Maximum 3.19 .53 .10 Conscientiousness Composite Openness Mean 3.42 .25 .31�� Mean 3.21 .23 S.16�
SD .46 .19 .06 SD .43 .21 S.03 Minimum 2.90 .34 .14 Minimum 2.74 .32 S.18��
Maximum 3.93 .36 .29� Maximum 3.71 .37 S.11
Note: n ¼ 129. Underlined values are the trait operationalizations that were expected, a priori, to be the most appropriate approach for aggregating each factor/ trait in the prediction of team performance. Bold values are the empirically strongest operationalizations in the prediction of team performance (i.e. they
demonstrated the strongest within-factor/trait correlation with team performance).� p < .05; ��p < .01.
38 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
exception, although validities were in the unexpected
direction. We interpret our findings, in turn, beginning with
those related to Conscientiousness, followed by results for
the other Big Five traits and, finally, the accuracy of our
a priori trait operationalizations.
Broad and narrow conceptualizations of
conscientiousness
As this and other research demonstrates, there are cases
where broad factors can exceed the prediction of the narrow
traits they encompass (see also Hastings & O’Neill, 2009).
For instance, the means on the IPIP Conscientiousness scale,
and on the Conscientiousness composite, were more strongly
related to team performance than was any one facet’s mean
operationalization. That the mean Conscientiousness com-
posite was the strongest operationalization, compared to the
narrow traits it comprises, indicates that common variance
among the facets was more important than was their unique
variance for criterion prediction (see Ashton et al., 1995;
Paunonen, 1998).
Notwithstanding the findings described above, we
maintain, as do others (e.g. Ashton et al., 1995; Paunonen
& Ashton, 2001; Rothstein et al., 2009; Schneider, Hough, &
Dunnette, 1996; Tett & Christiansen, 2007), that without
explicit empirical examinations of narrow facets of
personality, such as the one presented here, one can never
truly know whether the predictive variance associated with a
personality factor is primarily due to one or two highly
criterion-relevant facets, in which case misinterpretation of
factor-criterion linkages are likely, or, whether the predictive
variance associated with a personality factor is primarily due
to equally important criterion-relevant contributions from
each facet, in which case appropriate factor-level interpret-
ations are likely. Our view is that until research firmly
establishes that only common variance is relevant for the
prediction of a certain criterion, one should always theorize
in advance regarding the possibility of differential facet-level
predictions. Moreover, we see the continued employment of
measures that allow for empirical examination, and
exploitation, of within-factor variation in criterion validities
as an ongoing priority (see Hough & Oswald, 2008;
Paunonen, Rothstein, & Jackson, 1999; Tett, Steele, &
Beauregard, 2003).
Findings for non-conscientiousness traits
As noted earlier, it was surprising that the other Big Five
traits were mostly unrelated to team performance as this runs
contrary to findings reported by Bell’s (2007) meta-analysis,
where all team-level Big Five factors were valid predictors of
team performance in field settings. One explanation for these
findings is that our criterion emphasized the task perform-
ance of the team, as performance was based entirely on
project report quality. It is likely that different team-related
criteria, such as interpersonal liking and satisfaction with
team members, would be predicted by Big Five factors other
than Conscientiousness (see Barrick et al., 1998). Moreover,
perhaps previous studies using criteria that might have
incorporated the effectiveness of the teams’ interactions,
such as ratings of team performance given by the team
supervisor (e.g. Neuman & Wright, 1999), explain why
Bell’s meta-analysis found criterion validity support for all
Big Five factors of personality, whereas ours did not.
Unexpectedly, minimum andmean operationalizations of
team-level Openness were negatively related to team
performance. We expected that maximum Openness would
relate positively to team performance because of theory on
innovation diffusion (see Valente, 1995). More specifically,
we surmised that open individuals, who tend to be creative,
would present new ideas that other group members could
subsequently develop. Accordingly, only one team member
high on Openness should be needed, because other group
members can further refine that individual’s innovative
proposals. Observed negative relations involving mean and
minimum Openness, however, suggest that the more team
members tend to be characterized by Openness (mean), and
if even one team member is high on Openness (minimum),
team performance may suffer. Perhaps this is because the
Openness scale used in this study measures not only traits
related to creativity, but also traits related to adventurousness
and emotionality. It is possible that the latter traits detracted
from the sustained effort and the task-focus needed to see the
teams’ project through to completion.
On making a priori predictions of personality criterion relations
Previous research has found strong support for the a priori
predictions of those personality traits that are criterion
relevant. In their meta-analysis, Tett et al. (1991) found that
validities were nearly twice as large when traits were linked
to job performance through explicit consideration of the
context and variable content (i.e. job analysis). In the present
study, the four Conscientiousness facets that were identified
as criterion-relevant were in fact empirically related to team
performance. An especially novel finding is that, for both the
Conscientiousness factor and facets, wewere able to identify,
a priori, the most predictive team-level operationalization of
those personality variables. This further supports the
superiority of carefully aligning traits with criteria through
a consideration of their content and the context in which the
study exists (see Bartram, 2005; O’Neill et al., 2009).
The supportive findings for our a priori predictions
regarding Conscientiousness might be tempered against the
unsupported predictions regarding other Big Five factors. We
surmised that certain operationalizations of Agreeabeness,
Extraversion, Neuroticism and Openness would predict team
performance, but these associations were not borne out as
predicted. As argued above, the non-significant findings may
have been a reflection of the task-related nature of our team
performance criterion. The findings for Openness were
contrary to prediction, but again, it is possible that
individuals high on Openness were susceptible to distraction
and avoidance of persistent task-related efforts. Future
research could examine the accuracy in which a priori
predictions of team-level personality operationalizations are
supported for a wider range of criteria.
Personality and team performance 39
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Strengths, limitations, and future research
In this study, we examined a large sample of teams doing
comparable and consequential work over a substantial period
of time. We agree with numerous other researchers (e.g.
Behfar, Peterson, Mannix, & Trochim, 2008; Ilies, Wagner,
& Morgeson, 2007; Tasa, Taggar, & Seijts, 2007) who view
student-based project teams of this sort as a valuable way to
conduct, and advance, research on teamwork. Our teams
were embedded in a larger educational and professional
context (engineering) that has a unique culture and set of
expectations around teamwork. Moreover, the competitive
nature of the context was one that strongly encouraged team
members to treat the projects seriously and to interact
frequently, and intensely, in order to complete their work.
Finally, team performance was consequential as the
administrator rating on each project represented a consider-
able proportion of overall course grades. Taken together, the
teams comprised by our sample met the criteria of many
teamwork definitions; team members had shared, conse-
quential outcomes and goals, and had to work interdepend-
ently over a lengthy period of time to reach those goals (see
Sundstrom, De Meuse, & Futrell, 1990).
One potential limitation of the present research was the
use of only four narrow traits. Researchers comparing broad
factors with narrow traits sometimes use a large number of
narrow traits from which the best predictors of the criterion
are selected post-hoc through statistical procedures (e.g.
stepwise regression, canonical or set correlation; Paunonen,
1998; Tett et al., 2003). These predictors are then pitted
against the Big Five. If a similar approach was used here, we
would have measured many narrow traits and selected only
the predictive ones for comparison to the Big Five. Our
reason for avoiding this approach was that narrow traits
selected post-hoc could capitalize on chance (see Paunonen
& Ashton, 2001); therefore, we see a priori tests of narrow
trait validities as most compelling. Nevertheless, it could be
beneficial to examine a larger number of narrow traits to
assess their predictive validity as well.
Another potential limitation is that the Conscientiousness
facets had much lower scale reliabilities, ranging from .65 to
.74, than did the IPIP Conscientiousness scale (a ¼ .88). Note, however, that the facet scales were one third the length
of the IPIP Conscientiousness scale (8 versus 24 items).
Using longer scales might have resulted in greater validities
for the narrow traits through more reliable measurement (see
Paunonen et al., 1999), although in practice this would
require the administration of more items per facet and would
reduce the number of personality variables one could
feasibly measure. That being the case, the fact that the Big
Five were measured with substantially greater reliability
implies that they may have had an ‘ ‘unfair advantage’ in
terms of predictive validity. One way to equate the broad and
narrow traits, in terms of reliability, would have been to
correct each personality-performance correlation for
measurement error (e.g. Hastings & O’Neill, 2009). Such
corrections require team-level reliabilities of personality
scores; unfortunately, however, these could not be estimated
in the present study because there exists only one
measurement value per team-level trait operationalization
(e.g. mean, minimum). How exactly the reliability of
measurement at the individual level (e.g. a) might play out in
the aggregate team-level operationalizations (e.g. the mean
approach) is not entirely clear, and future research is needed
in that area especially for meta-analytic purposes (but see
Bliese, 1998). Nevertheless, the a reliability of lower-level
traits observed in this study likely reduced their predictive
validity relative to the Big Five.
Final remarks
Steiner’s (1972) observation that ‘research on group
composition always requires a simplification of unmanage-
able complexities’ (p. 107) is clearly still applicable today.
As McGrath (1998) noted, the complexities ‘have made it
highly unlikely that we could build up a substantial body of
research information on any one composition factor, much
less a substantial body of information on all of them’ (p.
258). Almost 10 years later, Bell’s (2007) meta-analysis is a
step in the right direction; however, more studies, across a
wider range of situations (e.g. team types and tasks, lab
versus field, different methodologies and statistical
approaches) are still needed. Also needed are procedures
for the implementation of such knowledge in real life
situations (but see Humphrey et al., 2007). Indeed, there is a
great deal of room for advancements in knowledge related to
team composition, and more research of this type is needed.
ACKNOWLEDGMENTS
Support for this research was provided from the Social
Sciences & Humanities Research Council in the form of a
Doctoral Fellowship (#767-2007-1439) to the first author and
a research grant (#410-2007-0742) to the second author. For
their efforts, support and insights throughout the data
collection process, the authors thank Drs Paul Kurowski and
Ken McIsaac of Western’s Faculty of Engineering, Dr Joy
Klammer of the Royal Military College and members of The
TeamWork Lab at Western. Also greatly appreciated was the
constructive feedback provided by Drs Michael Ashton,
Sampo Paunonen, Richard Goffin and two anonymous
reviewers.
REFERENCES
Allen, N. J., & West, M. A. (2005). Selecting for teamwork. In A. Evers, N. Anderson, & O. Voskuijl (Eds.), The Blackwell handbook of personnel selection (pp. 476–494). Oxford: Black- well Press.
Ashton, M. C. (1998). Personality and job performance: The importance of narrow traits. Journal of Organizational Behavior, 19, 289–303.
Ashton, M. C., Jackson, D. N., Helmes, E., & Paunonen, S. V. (1998). Joint factor analysis of the Personality Research Form and the Jackson Personality Inventory: Comparisons with the Big Five. Journal of Research in Personality, 32, 243–250.
Ashton, M. C., Jackson, D. N., Paunonen, S. V., Helmes, E., & Rothstein, M. G. (1995). The criterion validity of broad factor
40 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
scales versus specific facet scales. Journal of Research in Personality, 29, 432–442.
Barrick, M. R., & Mount, M. K. (1991). The Big Five personality dimensions and job performance: A meta-analysis. Personnel Psychology, 44, 1–26.
Barrick, M. R., Stewart, G. L., Neubert, M. J., & Mount, M. K. (1998). Relating member ability and personality to work-team processes and team effectiveness. Journal of Applied Psychology, 83, 377–391.
Barry, B., & Stewart, G. L. (1997). Composition, process, and performance in self-managed groups: The role of personality. Journal of Applied Psychology, 82, 62–78.
Bartram, D. (2005). The Great Eight competencies: A criterion- centric approach to validation. Journal of Applied Psychology, 90, 1185–1203.
Behfar, K. J., Peterson, R. S., Mannix, E. A., & Trochim, M. K. (2008). The critical role of conflict resolution in teams: A close look at the links between conflict type, conflict management strategies, and team outcomes. Journal of Applied Psychology, 93, 170–188.
Bell, S. T. (2007). Deep-level composition variables as predictors of team performance: A meta-analysis. Journal of Applied Psychology, 92, 595–615.
Bliese, P. D. (1998). Group size, ICC values, and group-level correlations: A simulation. Organizational Research Methods, 1, 355–373.
Chiocchio, F., & Essiembre, H. (2009). Cohesion and performance: A meta-analytic review of disparities between project teams, production teams, and service teams. Small Group Research, 40, 382–420.
Costa, P. T., Jr., & McCrae, R. R. (1992). Revised NEO personality inventory (NEO-PI-R) and NEO five-factor inventory (NEO- FFI): Professional manual. Odessa, FL: Psychological Assess- ment Resources.
Driskell, J. E., Hogan, R., & Salas, E. (1987). Personality and group performance. In C. Hendrick (Ed.), Group processes and intergroup relations (pp. 91–112). Beverly Hills, CA: Sage.
Dudley, N. M., Orvis, K. A., Lebiecki, J. E., & Cortina, J. M. (2006). A meta-analytic investigation of Conscientiousness in the prediction of job performance: Examining the intercorrelations and the incremental validity of narrow traits. Journal of Applied Psychology, 91, 40–57.
English, A., Griffith, R. L., & Steelman, L. A. (2004). Team performance: The effect of team Conscientiousness and task type. Small Group Research, 35, 643–665.
Gellatly, I. R. (1996). Conscientiousness and task performance: Test of a cognitive process model. Journal of Applied Psychology, 81, 474–482.
Goffin, R. D., Rothstein, M. G., Rieder, M. J., Poole, A., Krajewski, H., Powell, D. M., et al. (2009). Choosing job-related personality traits: Criterion-related evidence of validity. Poster presented at the annual meeting of the American Psychological Association: Toronto, Ontario.
Goldberg, L. R. (1999). A broad-bandwidth, public domain, personality inventory measuring the lower-level facets of several five-factor models. In I. Mervielde, I. Deary, F. De Fruyt, & F. Ostendorf (Eds.), Personality psychology in Europe (Vol. 7, pp. 7–28). Tilburg, The Netherlands: Tilburg University Press.
Halfhill, T., Sundstrom, E., Lahner, J., Calderone, W., & Nielsen, T. M. (2005). Group personality composition and group effectiveness: An integrative review of empirical research. Small Group Research, 36, 83–105.
Hastings, S. E., & O’Neill, T. A. (2009). Predicting workplace deviance using broad and narrow personality traits. Personality and Individual Differences, 47, 289–293.
Hecht, T. D., & Allen, N. J. (1999). The complexity of considering personality at the team level. In D. Miller (Ed.), Proceedings of the Administrative Sciences Association of Canada Conference, Organizational Behaviour Division, 20, 50–59.
Hough, L. M. (1992). The ‘‘Big Five’’ personality variables – construct confusion: Description versus prediction. Human Performance, 5, 139–155.
Hough, L. M., & Oswald, F. L. (2008). Personality testing and industrial-organizational psychology: Reflections, progress, and prospects. Industrial and Organizational Psychology, 1, 272– 290.
Humphrey, S. E., Hollenbeck, J. R., Meyer, C. J., & Ilgen, D. R. (2007). Trait configurations in self-managed teams: A conceptual examination of the use of seeding for maximizing and minimizing trait variance in teams. Journal of Applied Psychology, 92, 885–892.
Ilies, R., Wagner, D. T., & Morgeson, F. P. (2007). Explaining affective linkages in teams: Individual differences in suscepti- bility to contagion and individualism-collectivism. Journal of Applied Psychology, 92, 1140–1148.
Jackson, D. N. (1989). Personality research form manual (3rd ed.). Port Huron, MI: Sigma Assessment Systems.
Jackson, D. N. (1994). Jackson personality inventory-revised manual. Port Huron, MI: Sigma Assessment Systems.
Johnson, J. A. (2001). Screening massively large data sets for non- responsiveness in web-based personality inventories. Invited Talk to the joint Bielefeld-Groningen Personality Research Group, University of Groningen, The Netherlands.
Kichuk, S. L., & Wiesner, W. H. (1998). Work teams: Selecting members for optimal performance. Canadian Psychology, 39, 23–32.
Kozlowski, S. W. J., & Ilgen, D. R. (2006). Enhancing the effectiveness of work groups and teams. Psychological Science in the Public Interest, 7, 77–124.
Lepine, J. A. (2003). Team adaptation and postchange performance: Effects of team composition in terms of members’ cognitive ability and personality. Journal of Applied Psychology, 88, 27– 39.
LePine, J. A., Hollenbeck, J. R., Ilgen, D. R., & Hedlund, J. (1997). Effects of individual differences on the performance of hierarchical decision-making teams: Much more than g. Journal of Applied Psychology, 82, 803–811.
McGrath, J. E. (1998). A view of group composition through a group-theoretic lens. In M. A. Neale, E. A. Mannix, & D. H. Gruenfeld (Eds.), Research on managing groups and teams: Composition (Vol. 1, pp. 255–272). Stamford, Connecticut: JAI Press Inc.
Meng, X.-L., Rosenthal, R., & Rubin, D. B. (1992). Comparing correlated correlation coefficients. Psychological Bulletin, 111, 172–175.
Mohammad, S., & Angell, L. C. (2003). Personality heterogeneity in teams: Which difference makes a difference for team performance? Small Group Research, 34, 651–677.
Moynihan, L. M., & Peterson, R. S. (2004). The role of personality in group processes. In B. Schneider, & D. B. Smith (Eds.), Personality and organizations (pp. 317–345). Mahwah, NJ: Laurence Erlbaum.
Neuman, G. A., Wagner, S. H., & Christiansen, N. D. (1999). The relationship between work-team personality composition and the job performance of teams. Group and Organization Manage- ment, 24, 28–45.
Neuman, G. A., & Wright, J. (1999). Team effectiveness: Beyond skills and cognitive ability. Journal of Applied Psychology, 84, 376–389.
O’Neill, T. A., Goffin, R. D., & Tett, R. P. (2009). Content validation is fundamental to optimizing the criterion validity of personality tests. Industrial and Organizational Psychology, 2, 509–513.
Paunonen, S. V. (1998). Hierarchical organization of personality and prediction of behavior. Journal of Personality and Social Psychology, 74, 538–556.
Paunonen, S. V. (2003). Big Five factors of personality and replicated predictions of behavior. Journal of Personality and Social Psychology, 84, 411–424.
Personality and team performance 41
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Paunonen, S. V., & Ashton, M. C. (2001). Big five factors and facets and the prediction of behaviour. Journal of Personality and Social Psychology, 81, 411–424.
Paunonen, S. V., Rothstein, M. G., & Jackson, D. N. (1999). Narrow reasoning about the use of broad personality measures for personnel selection. Journal of Organizational Behavior, 20, 389–405.
Peeters, M. A. G., van Tuijl, H. F. J. M., Rutte, C. G., & Reymen, I. M. M. (2006). Personality and team performance: A meta- analysis. European Journal of Personality, 20, 377–396.
Raymark, P. H., Schmit, M. J., & Guion, R. M. (1997). Identifying potentially useful personality constructs for employee selection. Personnel Psychology, 50, 723–736.
Roberts, B. W., Chernyshenko, O. S., Stark, S., & Goldberg, L. R. (2005). The structure of Conscientiousness: An empirical investigation based on seven major personality questionnaires. Personnel Psychology, 58, 103–139.
Rothstein, M. G., & Goffin, R. D. (2006). The use of personality measures in personnel selection: What does current research support? Human Resouce Management Review, 16, 155–180.
Rothstein, M. G., Goffin, R. D., Rieder, M. J., Poole, A., Krajewski, H. T., Powell, D. M., et al. (2009). The incremental validity of narrow versus broad personality measures. In N.D. Christiansen & A. Billington (Chairs), Trait, criterion, and situational specificity in personality-job performance relations. Symposium presented at the annual meeting of the Society for Industrial and Organizational Psychology, New Orleans, LA.
Schneider, R. J., Hough, L., & Dunnette, M. D. (1996). Broadsided by broad traits: How to sink science in five dimensions or less. Journal of Organizational Behavior, 17, 639–655.
Steiner, I. D. (1972). Group process and productivity. New York: Academic Press.
Stewart, G. L. (2003). Toward an understanding of the multilevel role of personality in teams. In M. R. Barrick, & A. M. Ryan (Eds.), Personality and work: Reconsidering the role of
personality in organizations (pp. 183–204). San Francisco, CA: Jossey-Bass.
Sundstrom, E., De Meuse, K. P., & Futrell, D. (1990). Work teams: Applications and effectiveness. American Psychologist, 45, 120– 133.
Tasa, K., Taggar, S., & Seijts, G. H. (2007). The development of collective efficacy in teams: A multilevel and longitudinal perspective. Journal of Applied Psychology, 92, 17–27.
Tett, R. P., & Christiansen, N. D. (2007). Personality tests at the crossroads: A response to Morgeson, Campion, Dipboye, Hollenbeck, Murphy, and Schmitt. Personnel Psychology, 60, 967–993.
Tett, R. P., & Guterman, H. A. (2000). Situation trait relevance, trait expression, and cross-situational consistency: Testing a principle of trait activation. Journal of Research in Personality, 34, 397– 423.
Tett, R. P., Jackson, D. N., & Rothstein, M. (1991). Personality measures as predictors of job performance: A meta-analytic review. Personnel Psychology, 44, 703–742.
Tett, R. P., Jackson, D. N., Rothstein, M., & Reddon, J. R. (1999). Meta-analysis of bidirectional relations in personality-job performance research. Human Performance, 12, 1–29.
Tett, R. P., Steele, J. R., & Beauregard, R. S. (2003). Broad and narrow measures on both sides of the personality job- performance relationship. Journal of Organizational Behavior, 24, 335–356.
Valente, T. W. (1995). Network models of the diffusion of innovations. Cresskill, NJ: Hampton Press.
Wageman, R., & Gordon, F. M. (2005). As the twig is bent: How group values shape emergent task interdependence in groups. Organizational Science, 16, 687–700.
Williams, H.M., &Allen, N. J. (2008). Teams at work. In J. Barling, & C. L. Cooper (Eds.), The Sage handbook of organizational behavior: Micro approaches (Vol. 1, pp. 124–140). Los Angeles, CA: Sage.
42 T. A. O’Neill and N. J. Allen
Copyright # 2010 John Wiley & Sons, Ltd. Eur. J. Pers. 25: 31–42 (2011) DOI: 10.1002/per
Copyright of European Journal of Personality is the property of John Wiley & Sons, Inc. and its content may
not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written
permission. However, users may print, download, or email articles for individual use.