5-2 Activity: Risk Register
Risk 163
Risk Log
Risk Probability Impact Response Action
Requested completion date not workable
High Very high
Negotiate Procurement lead
Necessary personnel not available to meet schedule
High Very high
Negotiate Procurement lead
Team meetings not attended
Moderate High Determine better meeting time and place
Procurement lead
No competitors in market
Moderate Very high
Find and research competitors in this industry and market
Financial analyst
IBP insists on sole- sourced process
Moderate Very high
RFS completely filled out and signed; advise management
Procurement lead
Scope of work not detailed enough
High Very high
Face-to-face (or telephone) interview with SME
Procurement lead
Funding not adequate to provide requested services
Moderate Very high
Negotiate funding levels Procurement lead
Funding level does not provide savings
Moderate Low Negotiate lower spend levels Negotiation lead
RFP not delivered on time
High Very high
Allow enough time for drafting and reviewing RFP
Procurement lead (RFP writer)
RFP responses late Moderate High Allow enough time for questions, responses, and finalizing responses
Procurement lead
RFP responses inadequate
Moderate Very high
Include extremely detailed scope of work, specifications, draft contract, responses to all RFP questions from suppliers; amend RFP as needed
Procurement lead (RFP writer)
Response evaluation delayed
High Very high
Negotiate work assignments of team members as necessary
Procurement lead
Top three competitors’ oral presentations delayed schedule
Moderate High Allow enough time Procurement lead
Weather adversely impacted oral presentation schedule
Low High Allow float time for oral presentation schedule
Procurement lead
Figure 7-9. Risk log with actions.