Managing Risk

Project Management in the Information Age MASY1-GC 1250

Session 6

V21.6

Project Risk Management

Project Risk Management

• Project risk is an uncertain factor or event that can have a negative or positive effect on meeting project objectives

• Project risk management planning includes developing o A Risk Management Plan o A Risk Register o A Likelihood / Impact Matrix o Risk-related agreements and response plans

3

Negative Risk Events (Threats)

• Uncertain factors events that may occur to the detriment of the project o Performance failure of a product/service o Delays in completing work on schedule o Increases in estimated costs o Supply shortages o Litigation o Labor actions and strikes

4

Positive Risk Events (Opportunities)

• Uncertain factors or events that may enhance project success o Completing work sooner than planned o Unexpectedly reduced cost o Collaborating with suppliers to produce better

products o Good publicity from the project

5

Risk Terminology

• Risk Events o Discrete, specific occurrence that affect a decision, a

plan, or the organization

• Risk Ranking o The ordinal or cardinal rank prioritization of the

risks in various alternatives, projects, or units

6

More Risk Terminology

• Risk Appetite o The greatest acceptable degree of uncertainty one

is willing to accept in anticipation of a reward

• Risk Threshold o The level of risk above which risks must be actively

managed

7

The Problem of Bias

• Human bias affects o Risk identification o Risk analysis

• Behavioral economics o The planning fallacy

• Get management support for risk management! o “Tone at the top”

8

Common Attitudes About Risk Management

• The “head in the sand” mentality o “If I don’t see it, it can’t happen.” o “I don’t want to hear about any threats.”

• The hero mentality o “Whatever happens, we’ll figure it out.”

Both are harmful!

9

The Goal of Project Risk Management

• Answer these questions regarding the project: o What can happen? o How can it happen? o What is the potential harm or benefit? o What, if anything, can be done about it?

Remember: • Project management IS risk management • Project managers ARE risk managers

10

Risk Management Processes

• Plan Risk Management • Identify Risks • Perform Qualitative Risk Analysis • Perform Quantitative Risk Analysis • Plan Risk Responses • Implement Risk Responses • Monitor Risks

11

The Risk Management Plan

• A risk management plan documents the procedures for managing risks throughout the life of a project o Roles and responsibilities o Budget and schedule estimates o Timing for risk-related activities o Risk categories o Probability and impact matrices o Risk documentation and communications

12

Inputs

• Scope • Resource management plan • Schedule • Budget • Organizational assets • Enterprise environmental factors

13

Outputs

• Risk management plan • Risk Breakdown Structure (RBS) • Risk register • Schedule activities • Budget • Probability and impact matrix • Risk response plans

14

Risk Identification Techniques

• Brainstorming • Interviewing • Delphi technique • Root cause analysis • SWOT analysis • Three-point estimation

15

Risk Breakdown Structure

• Possible categories: o External, unpredictable o External, predictable o Internal, non-technical o Internal, technical

• Other RBS “taxonomies” o Deliverables o Functional areas o Project phases

16

Risk Ownership

Assign individual owners to identified risks for: • Ongoing monitoring • Risk response planning and execution

17

Qualitative Risk Analysis

• Description • Comparison • Contrasts • Prioritization • Classification of likelihood and impact:

o High? o Medium? o Low? Determine categories for each!

A starting point for quantitative analysis

18

Qualitative Risk Analysis

19

Likelihood

Impact

Low Medium High

High

Medium

Low

Quantitative Risk Analysis

• The “gold standard” • Usually measured in money • Also based on likelihood and impact • Estimation issues • Some techniques:

o Three-point estimation o Expected monetary value o Monte Carlo analysis

• Remember, models have limits!!!

20

Risk Strategies

Threats • Escalate • Avoid • Transfer • Mitigate • Accept

21

Opportunities • Escalate • Exploit • Share • Enhance • Accept

Complexities of Risk Response Planning

• Combination strategies • Risk dependencies • Residual risks • Secondary risks

22

Risk Plans

• Contingency Plans o Predefined actions that the project team will take if an

identified risk event occurs

• Fallback Plans o For risks that have a high impact on meeting project

objectives

o Put into effect if attempts to reduce the risk are not effective

o Contingency plans of last resort

• Contingency / Management Reserves o Funds held by the project sponsor that can be used to

mitigate cost or schedule overruns if unknown risks occur

23

Agile Risk Management

• Scope uncertainty accepted • Schedule and budget fixed • Adaptive

Techniques: • Prioritization • Incremental delivery • Daily standups • Concurrent testing • Business integration

24

  • Slide 1
  • Slide 2
  • Project Risk Management
  • Negative Risk Events (Threats)
  • Positive Risk Events (Opportunities)
  • Risk Terminology
  • More Risk Terminology
  • The Problem of Bias
  • Common Attitudes About Risk Management
  • The Goal of Project Risk Management
  • Risk Management Processes
  • The Risk Management Plan
  • Inputs
  • Outputs
  • Risk Identification Techniques
  • Risk Breakdown Structure
  • Risk Ownership
  • Qualitative Risk Analysis
  • Qualitative Risk Analysis
  • Quantitative Risk Analysis
  • Risk Strategies
  • Complexities of Risk Response Planning
  • Risk Plans
  • Agile Risk Management