Project Management Questions
If a project has 12 stakeholders what is the total number of communication channels?
|
|
|
10 |
|
|
|
45 |
|
|
|
66 |
|
|
|
24 |
10 points
The goal of controlling communications is to share information regarding the project’s with performance stakeholders and to improve upon the established?
|
|
|
Communication process |
|
|
|
Stakeholder management plan |
|
|
|
Project planning process |
|
|
|
Statement of work |
10 points
The receiver confirms that the message is being received through feedback question is called?
|
|
|
Encoder messaging |
|
|
|
Feedback |
|
|
|
Medium |
|
|
|
Active listening |
10 points
The pitch, tone, and inflections in the sender’s voice affecting the message being sent is known as?
|
|
|
Paralingual |
|
|
|
Decoder |
|
|
|
Active listening |
|
|
|
Receiver |
10 points
The communication approach pulls the information from a central repository like a database of information. The approach is good for a large number of stakeholders who want to access information?
|
|
|
Push |
|
|
|
Pull |
|
|
|
Status review meeting |
|
|
|
Medium |
10 points
The five inputs to a risk management plan include project management plan, charter, stakeholder register, enterprise environmental factors, and ______________?
|
|
|
Scope document |
|
|
|
WBS |
|
|
|
Organizational process assets |
|
|
|
Probability charts and timetables |
10 points
Risk identification involves a systematic process of moving through the project, the project plan, the WBS, and supporting documents to identify all possible risk. Two categories of risk reflect all risk. The two are pure risks and ?
|
|
|
Business risks |
|
|
|
Scope risks |
|
|
|
Resource risks |
|
|
|
Schedule risks |
10 points
Qualitative risk analysis is often the first pass in evaluating risk. Qualitative risk analysis helps prioritize risks based on probability of occurrence and impact on project. Qualitative risk analysis attempts to?
|
|
|
Qualify risks |
|
|
|
Assess risks against company resources |
|
|
|
Evaluate risks in terms of timing within project |
|
|
|
Determine when risks may occur |
10 points
As risk analysis happens throughout the project, one of the documents that is always updated as new risks are identified and known risks re-evaluated is the?
|
|
|
Risk matrix |
|
|
|
Risk management plan |
|
|
|
Risk register |
|
|
|
Risk score card |
10 points
An example of a response to risk is avoidance. One way to avoid the risk is to?
|
|
|
Shut down project |
|
|
|
Accept the risk |
|
|
|
Buy insurance to offset risk if it occurs |
|
|
|
Ignore the risk |