IT 509 Information Systems Analysis and Design

Assignment #1

Prepare a list to show all tasks and their duration and then develop

Q1: Work breakdown structure (WBS)

Q2: Gantt Chart (Must reflect the WBS)

Q3: PERT chart that shows the project (Must have the slack time)

Q4: Show the critical Path

Additional Instructions:

• You should add one day Slack time for the preparing and delivery of the printing the copies of the handout materials.

• Make sure you have your name is written on each diagram.

• Once you have done with all sections, place them in MS Word document and then submit