It's tough to make predictions, especially about the future.

─ Yogi Berra

INTRODUCTION

Risk and risk management are concepts that leaders and their staffs have come to appreciate in

increasing levels of sophistication. Operational Risk Management (ORM) is a process taught at

all levels in the Department of Defense. Yet, and somewhat ironically, senior civilian Defense

Department leadership has often been quite critical of the military services for their limited

understanding of, and general aversion to, risk. While one can build a defensible case for the

military’s penchant to avoid risk, the purpose of this paper is to examine more fully the

challenges that make astute risk management so difficult. As part of that discussion, we will

briefly examine the difficulties inherent in determining risk for low-probability but catastrophic

events. We will also examine briefly the processes used in risk management and the challenges

leaders face in making risk management decisions. Finally, we will address the challenges all

organizations face when communicating the rationale for their choices given the risks involved.

RISK

In a July 2004 study commissioned by the British government entitled Public Perception of Risk,

J. Richard Eiser noted that: “Risk is a feature of all human activity that results in some probable

benefit but also includes a potential cost or harm.”1 He further noted:

[E]verything that is important about risk arises from actual or perceived uncertainty ...

it is only because we need to act under conditions of uncertainty that the concept of risk

is of interest. If we felt there was nothing we could ever do to affect what might

happen to us, we would have no decisions to take and there would be no point in

worrying about the likelihood or value of future events. ... It is because these

consequences are uncertain, and may leave us better or worse off, that we talk about

risk.2

Risk is typically defined as “the combination of the probability of an event occurring and its

consequences.”3 Usually, organizations perceive those consequences in a negative context.

Within the Department of Defense, the term risk clearly has a negative implication defined as

“the probability and severity of a potential loss that may result from hazards...”4 Similarly, the

Naval War College characterizes risk as “the likelihood of failure and the consequence of

failure…”5 These definitions equate risk to the probability that an organization’s vulnerabilities

or weaknesses will permit an unwanted and/or harmful event to occur that will limit its ability to

achieve a desired goal or objective. Thus risk is perceived to increase as either the probability of

the unwanted event increases or the severity of the consequences rise.

Often overlooked in an organization’s treatment of risk are its positive aspects. Risk usually

entails the possibility that a future event could have a positive effect or be advantageous to the

organization. This aspect of risk, while acknowledged by most organizations, is just as often

likely to be ignored, as their aversion to risk too greatly discounts the potential benefits of a risky

2

choice. Many organizations fail to appreciate that risk is more than a simple articulation of the

bad things that could happen; it is also about the good things that will not happen.

Organizational success or failure is not simply dependent on the ability to identify and avoid

harmful risk, but is also reliant on the ability to recognize and “to capitalize on fleeting

opportunities.”6

UNCERTAINTY

Risk occurs because the precise likelihood of a future event is unknowable. If we knew with

certainty that an event was going to happen, there would be no discussion about risk.

Unfortunately, the future is simply and unequivocally unknowable. We are frequently forced to

make choices about the future without really knowing how things will turn out. As the

consequences of those choices increase, so too does the perceived need to eliminate as much

uncertainty as possible.

Organizational uncertainty arises from three basic circumstances: 1) uncertainty about how the

organization’s environment is changing; 2) uncertainty about how those changes will harm or

benefit the organization; and 3) uncertainty about the best way to respond to those changes to

either limit the harm or assure the benefits occur.7 Uncertainty is further complicated by the very

nature of the doubt that creates the risky situation under consideration. Uncertainty results from

two basic conditions: vagueness and ambiguity.

• Vague uncertainty occurs when there is a lack of clear or definitive information about the range of probable future outcomes.

• Ambiguous uncertainty, which occurs when there is clear but conflicting information on (or general disagreement about) the range of future outcomes.8

While uncertainty due to vagueness can be reduced by gathering more information about the

situation, uncertainty due to ambiguity usually cannot be resolved by additional or new

information. Clearly, it behooves the risk practitioner to first seek to understand the basic nature

of the uncertainty faced by the organization before deciding how to diminish it. How we identify

relevant data, develop information and act on that knowledge is dictated by how we perceive and

judge risk as either a danger to be avoided or an opportunity to be seized. Judgment about risk is

influenced by two elements: risk perception and risk propensity.

RISK PERCEPTION

Risk is not a physical entity into itself, but rather is a concept or a way of thinking about the

impact of something that has yet to happen. As such, risk is a subjective judgment of the likely

consequences of a future uncertain event. Yet risk is more than merely a function of uncertainty.

It is also a judgment about how we value the different possible results (good and bad) that might

occur. Those judgments color and bias our perceptions of risk.9 Value judgments play an

especially large role in the way we estimate risk for low probability, but highly destructive

events. Thus, risk perception is the product of one’s judgment about the likelihood an event will

occur, the extent of harm or benefit that future event is likely to bring, and the level of

confidence one has in those estimates.10

3

RISK PROPENSITY

Risk propensity is often defined as “an individual’s current tendency to take or avoid risks…”11

It is usually viewed in one of two ways:

• Risk averse characterizes those who view risk as a harmful consequence to be avoided at all costs regardless the potential benefits. As a result, those who are risk averse

usually seek to avoid risk in the decisions they make.

• Risk tolerant characterizes those who value the potentially beneficial consequences of an event more than they fear the associated potential harm. Hence, those who are risk

tolerant are willing to accept risk commensurate with the potential gain in the

decisions they make.

Our perceptions of risk are relative to our basic tendencies towards risk. While perception of

risk may drive one person’s risk tolerance, another’s propensity to assume risk probably drives

their perception of the risk involved. Decision makers must be aware of both aspects in order to

fully appreciate which element is most influencing their decision or the estimates of others. To

be too risk averse forgoes opportunity, while being too risk tolerant may be foolhardy.

The Risk Dilemma. Adding to the complexity of organizational perception of risk is the

influence of important key stakeholders. Returning to Eiser’s report on risk perception for the

British government:

Risk-mitigation decisions may be influenced by public perceptions of risk in ways

that may distort priorities away from actual risk reductions. Policy makers may

feel the need to be seen to be doing something about particular risks, even where

the risks are relatively small and the actions undertaken are more visible than they

are effective. The other side of the story is that the general public can sometimes

appear frustratingly complacent about the seriousness of other kinds of risks, and

so be resistant to policies and actions that could lead to risk reduction.12

How people perceive risk depends on: what they value, how the risk is framed, and their level of trust in the organization or institution responsible for identifying and characterizing the risk.

Studies have shown that there appears to be a clear inverse relationship between perceived risk

and perceived benefit and an individual’s evaluation of a hazard. That is to say, where an

activity or issue is perceived in a positive light, people tend to judge its benefits as high and its

risks as low. But where the situation or endeavor is seen in a negative light, people are likely to

dwell on the dangerous or harmful aspects of the issue and perceive the risks as high.13 As a

consequence, the astute risk decision maker must always strive to understand which aspect of

risk (potential harm or benefit) is being emphasized or minimized to ensure that how a problem

has been framed does not prejudice the risk decision.

The “Wicked” Problem14 – Low Probability-High Consequence (LP/HC) Threat. One

of the most perplexing problems that confronts national security organizations like DoD and the

Department of Homeland Security is how best to identify and characterize the risk associated

4

with low-probability events that have highly dangerous or catastrophic consequences should they

occur. LP/HC threats include such things as the release of a Weapon of Mass Destruction

(WMD) in a metropolitan area like New York City, or global pandemics like drug-resistant

Tuberculosis, Smallpox or the Avian Flu.

As the diagram at the right shows, when the

severity of the consequences of an event is

judged to be relatively low, the risk is

usually judged to be “low” regardless of the

likelihood that the event will occur. If the

event is highly probable and its

consequences are highly harmful, the risk is

judged appropriately to be “high.” Problems

arise, however, when we are forced to

characterize events that have a very low

probability of occurring, but if they do occur

have disastrous consequences. Identifying

appropriate criteria to characterize such risk as either high or low is not only highly problematic,

but equally difficult to explain.

LP/HC threats are by their nature complex ─ complex in the sense that the cause-and-effect

chain is usually dynamic, often not well understood, and generally is open to reasonable

debate. When the complexity of a threat exceeds the layperson’s ability to understand the

important technical issues, cultural values and the public’s trust of national institutions become

an integral part of the risk calculus. As a result, expert opinions or scientific analysis often are

insufficient in and of themselves to provide universal or wholly accepted characterizations of

the risk.15 When the issues are complex, public perceptions of risk are influenced by two

dimensions: the extent and clarity of the knowledge about the threat and the level of

conformity among stakeholder values that shape perceptions about how much risk is involved.

Such problems have been called “wicked problems” because:

1) The problem and solutions exist in the “eye of the beholder,” hence there is no

single accepted formulation of the problem;

2) Outcomes are not scientifically predictable;

3) The decision maker cannot know when all feasible and desirable solutions have

been explored; and

4) The decision-maker is not allowed to be wrong.16

DIFFERENT KINDS OF RISK

When addressing risk, frequently there is a tendency to assume that others see and understand the

context of risk the same way that we do. Such a presumption is ill-founded and lays at the heart

of most misunderstandings about risk. As one author noted when researching the subject, an

internet search engine recently took 0.18 seconds to identify 510 million written works on the

single word “risk.” It is highly doubtful that all of those authors were using it in the same way or

in the same context.17

P ro

b a

b il it y o

f H

a z a rd

o u s E

v e n t O

c c u rr

in g

(U n

c e

rt a

in ty

)

None Severity of the Consequence Catastrophic

0%

100%

Low Risk

Low Risk High Risk

?

5

There is no commonly accepted standard that establishes the categories or kinds of risk that

confront decision makers. For many, risk is basically comprised of the inherent or pure risk that

naturally emanates from our environment as opposed to assumed risk that springs from

individual or collective activity or behavior. For others, risk is simply comprised of individual

risk or societal risk. Within those broad constructs, risk can also refer to the potential harm to a

physical asset (building, information system, transportation system, etc.) or to intangible but real

assets (victory, profit, market share, reputation, etc.). Some commonly used categories or

descriptions of risk include the following:

• Organizational risk (technical, personnel, systems/process, performance);

• Business risk (credit, product/market, regulatory/legal, transactional, investment);

• Project management risk (cost, schedule and performance);

• Operational risk (mission, resources, processes, tactics);

• Strategic risk (competitive environment, risks that arise in the pursuit of enterprise objectives);

• Political risk (constituencies, alliances, coalitions); and

• Security risk (public safety and health, information systems, infrastructure).

The Defense Department categorizes risk into four groups (personnel management,

operational, future challenges and institutional). These lists are by no means exhaustive, but

serve to show why, when speaking about risk, it is imperative to ensure all participants in a

risk decision are proceeding with a common understanding of the risk that is under

consideration.

RISK MANAGEMENT

In 2002, the National Infrastructure Protection Center defined risk management as the:

Systematic and analytical process by which an organization identifies, reduces, and

controls its potential risks and losses. This process allows organizations to determine

the magnitude and effect of the potential loss, the likelihood of such a loss actually

happening, and counter-measures that could lower the probability or magnitude of

loss ... countermeasures should be identified and evaluated to select those which

offer an optimal trade-off between risk reduction and cost.18

The term risk management is often (and incorrectly) used interchangeably with risk assessment,

but the terms are not synonymous. Risk management is the administrative process designed to

manage an organization’s exposure to risk to an acceptable level. From a military perspective, it

is often useful to consider two aspects of risk: risk to mission and risk to forces. Risk

assessment is a component part of risk management that describes the process used to identify

and prioritize the risks that confront an organization. Risk management is comprised of four

basic phases: assessing risk, deciding how to control the risk, implementing risk control

6

measures, and measuring risk control effectiveness. According to Shortreed, et al., in

Benchmark Framework for Risk Management:

The objective of risk management is to ensure that significant risks are identified and

that appropriate action is taken to manage these risks to the extent that is reasonably

achievable [emphasis added]. Appropriate actions are determined based on a

balance between: risk treatment (or control) strategies; their effectiveness and cost;

and the needs, issues and concerns of stakeholders.19

Implicit in the statement above is recognition of a critical point: in all risk management

decisions, risk can only be minimized, but it can never be eliminated. The reason is quite

simple, risk is comprised in part by uncertainty and while we can reduce uncertainty, we can

never completely do away with it. Risk itself cannot be managed, only the operations and

decisions that respond to the perceived risk can be managed.20

RISK FRAMEWORK – SEVEN WAYS TO DEAL WITH RISK

Once an organization has completed its risk assessment, it must decide how best to control the

risk that comes with a choice to either proceed with an activity that holds the possibility of

causing desired effects or to forego such activity. Often we have a choice to engage in risky

behavior, but it’s also important to note that some risks are unavoidable (weather or other natural

disasters like earthquakes). Responses to risk can be divided into four basic approaches:21

Avoid: Some risks may only be treated or contained to acceptable levels by terminating

the intended operations or activity. A military operation whose potential benefits or gains

do not outweigh the potential negative consequences of failing should be terminated or

cancelled.

Transfer: For some risks, the best response may be to transfer wholly or partly the

activity to another organization that has the capacity to better handle the risk and

uncertainty. An infrastructure reconstruction project might better be transferred to a

civilian contractor rather than assigned to a military construction battalion that has

capability but marginal expertise. That said, one should proceed with caution when

attempting to transfer any kind of risk because in most cases, responsibility and

accountability for the results will likely remain with the original organization.

Tolerate: At times an organization’s ability to do anything about some risks may be

limited, or the cost to mitigate negative consequences may be disproportionate to the

potential benefit gained. In this circumstance, the only course of action may be to endure

the potential negative consequences of the decision. In large scale military operations,

casualties are inevitable, sometimes even extensive, but often the operational or strategic

goals are so important that casualties must be endured.

Assume and Control: When the decision is made to pursue a course of action that is

inherently risky, steps are usually taken to mitigate as much as possible any negative

consequences that may result from that action. Such steps are not taken necessarily to

eliminate the risk, but to contain or limit the negative consequences to a tolerable level.

Said another way, the purpose of this category of control is to contain the potentially

7

harmful effects of risk rather than to eliminate it. Controls can be classified in one of

four ways:22

• Redundancies: These controls are designed to ensure that a particularly important outcome is achieved or an intolerable event is avoided. The opposite of this is putting

all of one’s eggs in a single basket. Generally this consists of backup plans and

redundant systems. However, it can also include elements of hedging and

diversifying. Hedging is putting into place safeguards to protect against undesired

outcomes. For example, one way to hedge against the possible negative

consequences with building a lighter, smaller conventional force is to maintain a

nuclear strategic capability to assure a country’s national survival. Another

redundancy approach to limit risk is by diversifying. Using the example of a nuclear

strategic capability, the United States uses three different weapon delivery systems

(land-based missiles, sea-based missiles and bombers) to complicate an adversary’s

defense mechanisms.

• Directive Controls: These controls are designed to limit the possibility of an undesirable outcome from occurring. Procedures designed to prevent mishaps in

organizations belong in this category. Examples include prohibition against the entry

of cargo or individuals coming from a particular country or port of origin that does

not have sufficient controls in place to assure the security of follow-on ports of entry.

• Detective Controls: These controls are designed to identify instances of undesirable outcomes occurring. Detective controls are, by definition, “after the fact” and only

appropriate when it is possible to bear the negative consequences incurred. Examples

include monitoring devices in ports of entry to detect the presence of WMD or

passport control systems to detect attempted entry by illegal immigrants or unwanted

visitors.

• Corrective Controls: These controls are designed to correct the undesirable outcomes which have occurred. They describe the planned response to any loss or damage that

result from the organization’s actions. An example of these controls includes the

response of local, state and federal officials to contain or limit the effects of a WMD

device or the effects of a particularly virulent and widespread disease or pandemic.

Since every control action has an associated cost, the benefits of control must be judged

against those costs. Seldom, if ever, is it possible to afford all the controls that could

limit or contain the risk involved in a situation. Hence, the risk practitioner must choose

a balance between implementing controls (e.g., redundancies, directive controls, detective

controls, and corrective controls) and doing nothing (i.e., avoid, transfer, and tolerate).

LIMITS TO PLANNING FOR AND MANAGING RISK

While everyone generally recognizes that things rarely ever turn out exactly as expected, there is

a natural tendency to expect that they will. While most leaders and managers assume they are

proficient in handling risk and uncertainty, they probably are not as good at risk management as

they think they are.23 There are several possible reasons for this:

8

• Overly narrow or misguided perceptions of what might happen in the future;

• Insufficient relevant knowledge and/or poor situational awareness;

• Pressure from stakeholders to ignore or assume away critical uncertainty; and

• Lack of a systemic and logical framework to collect and process all relevant information that influences perception of the inherent uncertainties and risks.24

Risk practitioners must take care to guard against cognitive errors that cloud or bias their

judgments about risk and uncertainty. People are prone to error when estimating probabilities

and/or thinking about future events for a number of reasons:25

• Wishful thinking. Estimates of particular outcomes may reflect personal preferences

concerning those outcomes. Sometimes those responsible for planning and executing an

operation are more optimistic than uninvolved individuals.

• Selective perception. People may not include all the factors that matter when estimating

subjective probability.

• Experiential bias. When considering a risky situation, knowledge about similar previous

events may lead people to prejudice their perception of risk in the current situation even

though the circumstances may be completely different.

• Framing effects. The way people define the issue or problem usually influences their

estimation of the probability of either a beneficial or harmful outcome occurring.

• Overconfidence. People often overrate their ability to estimate the probability of future

events. Research has shown that individuals are not as good at making predictions as

they think they are.

• Confirming evidential bias. People sometimes have a preferred outcome at a subconscious level, before they decide how they will justify their choice. In such cases,

their biases affect the kinds of evidence they search for, and how they interpret the

evidence they find.26

While the issues raised above seem pretty straightforward, “recognizing that we are prone to bias

and errors of reasoning is one thing, but knowing what to do about it is quite another ... The

problem is that we don’t typically know when we’re making a mistake until afterwards, and

sometimes not even then. Even bad decisions can feel right.”27 As noted above, the reasons for

our mistakes are myriad, if for no other reason than we truly believe we are acting as rationally

and objectively as possible. The danger, however, lies in the fact that,

... it is extremely difficult to unlearn habits of thought and action that have been built

up over a longer time. ... Our previous experience ‘got us here;’ on the other hand,

we generally have very little insight into how we got here or what we have missed

out on in the process. ... We don’t know what we don’t know, and find it difficult to

imagine how things could be otherwise than as they appear to us.28

9

MORAL AND ETHICAL ISSUES

Individual or collective choices that involve risk pose potential harm to others. As a

consequence, they are irrevocably influenced by the moral values and ethical characteristics of

the organization and the individuals who make such decisions. Moral and ethical considerations

are rarely black or white, but encompass many shades of gray based on the perceptions of all

involved in risk decisions. As such, there are no absolutes or hard guidelines or checklists to

guide a leader faced with difficult choices. Hence, decision makers might do well to reflect on

the following:

• How will the consequences affect various individuals or groups;

• How perceptions of the likelihood or the consequences of a threat will likely vary among those affected;

• When the consequences will likely occur (in the near-term or distant future);

• Where the consequences of a decision will be felt (outside as well as inside the organization); and

• The likelihood that there will be a wide range of opinion about what is morally or ethically just.29

In the final analysis, the decision maker must be able to answer a basic question: “What factors

define what should be done to assure the well-being of the organization and the individuals who

are a part of that organization?” Further: “What are our obligations to those outside the

organization who will be affected by our choices?” Such judgments are wholly enveloped by

individually and collectively held values that influence our perceptions of a situation.30

COMMUNICATING RISK

This article has concentrated on the issues that inform the risk management process and dealing

with uncertainty and the complex nature of risk. Decision makers must be ready to explain their

choices, given the risks involved, to key stakeholders including the public. Felix Kloman, noted

author of several articles on risk management observed: “Few organizations take the time to

reduce what they know ─ and what they do not know ─ about risk, its organizational

implications, and its responses into terms understandable to stakeholders.”31 He further and

strongly asserts that organizational leaders have a basic responsibility to simplify our

descriptions of risk in ways that most people can understand. To assure the public trust, he

notes: “It is essential to communicate to stakeholders our understanding of risks, their

interactions and our planned responses. When we obfuscate definitions with jargon and

convoluted prose, we lose the audience we must reach.”32

CONCLUSION

Uncertainty and risk are the constant companions of all leaders. As organizations and their

competitive environments expand in scope and complexity, the uncertainty and the risk inherent

in those surroundings will correspondingly increase. Leaders must provide their followers as

10

much clarity about the future as possible (within the constraints and limitations posed by the

basic unknowable nature of the future) and offer guidance that bounds where and how much risk

will be tolerated, and gives guidance about how to manage or control the risk assumed. To do

that well, requires the astute risk practitioner to have a good understanding of the complexity

inherent in any decision about risk and uncertainty.

ENDNOTES

1 J. Richard Eiser, “Public Perception of Risk,” report prepared for the British Government Foresight Office of

Science and Technology, July 2004, 2, available online at <http://www.foresight.gov.uk/Intelligent

%20Infrastructure%20Systems/Reports%20and%20Publications/Public%20Perception%20of%20Risk/long_paper.p

df> [accessed 4 December 2005]. 2 Ibid, 4. 3 Definition provided by he International Standards Organization (ISO). 4 FM 100-14 Risk Management, Headquarters, Department of the Army, (Washington D.C.: U.S. Government

Printing Office, 1998), 1-1. 5 Richmond M. Lloyd, “Strategy and Force Planning Framework,” Strategy and Force Planning, 3rd ed., eds. Lloyd

et.al., (Newport, RI.: Naval War College, 2000), 13. 6 Jan Emblemsvag and Lars Endre Kjolstad, “Strategic Risk Analysis – A Field Version,” Management Decision,

40/9 (2002), 843, available online at <http://www.dnv.com/binaries/StrategicRiskAnalyses_tcm4-10751.pdf>

[accessed 3 December 2005]. 7 Jean Hartley, “Leading and Managing Uncertainty of Strategic Change,” Chapter 8, Managing Strategy

Implementation, 109-121, eds. Tony Dromgoole, Patrick Flood, Liam Gorman, and Stephen Carroll, (Oxford:

Blackwell Publishing, 2000). 110-111. 8 For a greater understanding of vague or ambiguous uncertainty the reader is encouraged to refer to the work of

Daniel C. Molder and E. Tory Higgins in “Categorization Under Uncertainty: Resolving Vagueness and Ambiguity

With Eager Versus Vigilant Strategies,” Social Cognition, Vol. 22:2, 2004, 248-277 available online at

<http://www.psych.northwestern.edu/~molden/documents/RFCategorize_SC04.pdf> [accessed 5 December 2005]. 9 Eiser, 58. 10 Sim B. Sitkin and Luarie R. Weingart, “Determinants of Risky Decision-Making Behavior: A Test of the

Mediating Role of Risk Perceptions and Propensity,” Academy of Management Journal, 38:6 (December 1995):

1573-1575. 11 Sitken and Wiengart. 12 Eiser, 5. 13 Walters, Lawrence C., Peter J. Balint, Anand Desai, and Ronald E. Stewart, “Risk and Uncertainty in

Management of the Sierra Nevada National Forests,” a Report submitted to Jack Blackwell, Regional Forester

USDA Forest Service, Pacific Southwest Region, 6-7, Available online at: <http://classweb.gmu.edu/

pbalint/Final%20report.pdf> [accessed 7 December 2005]. 14 Adapted from Walters, et.al. 15 Ibid, 7-9.. 16 Ibid. 17 Eiser, 3. 18 National Infrastructure Protection Center, “Risk Management: An Essential Guide to Protecting Critical Assets,”

November 2002. Available online at <http://www.psaudit.com/images/images_updated/ white_paper.pdf>

[accessed 5 December 2005]. 19 J.H. Shortreed, L. Craig, and S. McColl, “Benchmark Framework for Risk Management,” Network for

Environmental Risk Assessment and Management, available on line at <http://www.irr-neram.ca/pdf_files/

Benchmark2001.pdf,> [accessed 3 December 2005]. 20 McNamee, David, “The New Risk Management,” Mc2 Management Control Concepts. Available online at

<http://www.mc2consulting.com/riskart5.htm> [accessed 4 December 2005]. 21 Department of Defense, Defense Acquisition University, Risk Management Guide For DOD Acquisition,

February 2001, available online at <http://www.dau.mil/pubs/gdbks/RMG%20June%2003.pdf> [accessed 13 June

2005].

11

22 British Government, Management of Risk-A Strategic Overview, Her Majesty’s Treasury Department, January

2001, available online at: <http://www.hm-treasury.gov.uk/media/EC612/orange-book.pdf> [accessed 13 June

2005]. 23 Matthew Leitch, “Risk Management – The Basics,” 18 March 2003. Available online at

<http://homepage.ntlworld.com/ m.leitch1/mluck/basics/> [accessed 31 December 2003]. 24 Ibid. 25 For a more detailed discussion of errors mentioned in the text, and related errors, see Max Bazerman, Judgment in

Managerial Decision Making, 4th Edition. (New York: John Wiley & Sons, 1998). See also Hammond, Keeney and

Raiffa, Smart Choices, (New York: Broadway Books, 1999), 189-216. 26 Hammond et al., 1999. 27 Eiser, 35. 28 Ibid. 29 Douglas R May, Timothy D. Hodges, Adrian Y.L.Chan, and Bruce Avolio, “Developing the Moral Component of

Authentic Leadership,” Organizational Dynamics, 32:3, 2003, 251. 30 Ibid. 31 Kloman, Felix, “Four Cubed,” Risk Management, September 2001, 23-24. 32 Ibid.