ID: Task List: Duration: Predecessors: Resources:
1 Northwood Project
2 Contract Design
3 Customer selections 1w ` Sales[25%]
4 Write specifications 1d 3 Specifications
5 Write contract 4h 4 Counsel
6 Plans 16d 5 Drafting[50%]
7 Signatures 1h 6FS+2d Sales
8 Contract begins 0d 7
9 Foundation Stage
10 Excavation 1d 8FS+2d Excavation Contractor
11 Footing/foundation 10d 10 Excavation Contractor
12 Water service 1d 11 Water utility
13 Electrical service 1d 11 Electric Utility
14 Inspection 1h 13FS+1d Building Inspector
15 Foundation stage complete 0d 14
16 Framing Stage 15
17 Wood framing 18d 14 Framing Crew[700%]
18 Roofing 4d 17 Framing Crew[500%]
19 Plumbing 3d 17 Mech/Plumb Contractor
20 Electrical wiring 3d 17 Electrical Contractor
21 Inspection 1h 18,19,20 Building Inspector
22 framing stage complete 0h 21
23 Finishing Stage 22
24 Wallboard 1w 22 Wallboard Crew[500%]
25 Stairway 5d 22 Finish Carpenters
26 Painting 1w 24 Paint Crew[800%]
27 Trim 1w 26SS+33% Finish Carpenters
28 Landscaping 5d 27
29 Customer walk through 3h 26FS+2d,27
30 Punch list corrections 4d 29
31 Final inspection 3h 28,30 Building Inspector
32 Finishing stage complete 0d 31
33 Close-out Stage 32
34 Administrative closure 1d 32
35 Project complete 0d 34