Lecture Overview

Why Material Requirements Planning (MRP)?

Definition and Objectives of MRP

MRP Inputs and Outputs

Developing MRP:

Net Requirement

Calculating Net Requirements, Planned Orders and Planned Order Releases

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

2

2

Why Use MRP?

“Material Requirements Planning (MRP) has become a centerpiece for all manufacturing and service systems. Without MRP, we would be totally out of control. It's not a theory - it's the real world”

Al Sondern, Corporate Vice President, Halmark Card, Inc.

 

“MRP is perhaps the most significant contribution to production and distribution systems… ”

William R. Wassweiler, an industry specialist

Service and manufacturing companies with sales of grater than $10 million are likely to utilize computerized MRP systems

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

3

3

Why Use MRP? (Continued)

Corning, Inc.

Before MRP, only 50 percent of its orders were being delivered on time

After MRP implementation, the company:

reduced inventory by approximately 10%

climbed inventory accuracy from 69 to 86 percent,

improved delivery schedules from 50 to 90 percent

SC Corporation, the world's largest producer of evaporative coolers

After two years of MRP implementation, inventory decreased so dramatically that plant could build the new line, doubled its production, and increased profit fivefold 

MRP was applied to plan the NASA's space shuttle missions

To handle the extensive resource demand of each launch, it had design a Flight Operations Planning Schedule (FOPS) which was exactly the same as MRP

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP: Definition and Main Objectives

MRP is a computer based system that determines what final products the firm will make for future periods, and then it specifies production of needed inputs to make those products

The system identifies

Schedules of specific parts and materials and their amounts required to produce end items

Dates when orders for the materials should be released and received

MRP slogan

Getting the right materials in the right place at the right time

“Getting the right quantities at the wrong time does not accomplish anything”

Main objectives of MRP

Improve customer satisfaction

Reduce inventory investment

Improve plant operations efficiency

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP in Enterprise Resource Management

Master Demand Schedule (MDS)

Master Production Schedule (MPS)

Material Requirements Planning (MRP)

Capacity Requirements Planning (CRP)

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP Inputs and Outputs

Inventory Information

Cost information

Material Requirements Planning (MRP)

Capacity Requirements Planning (CRP)

Purchasing and Supply Management

Work-in-Process Short-Term Schedules

Bill of Materials

Master Schedule

Supply Chain Bill Assignment Set

Accounting Material Costs

Changes and Exception Data

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP Major Inputs

Master Schedule

MDS/MPS schedule including quantity and dates of end items production (gross or net requirements)

Incorporates sales orders including their quantity and dates

Bills of Materials

Product structure including single-level and other model BOM

Supply Chain Bill/Assignment Set

Supply chain relationships including all suppliers, customers, and quantities transferred

Inventory Information

Item attributes including lead times, safety stocks, amount on hand, make/buy items, MRP planned, order quantities, scheduled receipts, order entry, etc.

Cost Information

Provide cost of resources (labor, materials, and capacity) used in MRP as well as the end product prices in order to identify the total cost and gross profit for each MRP schedule

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Bell Computer: MDS Plan

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Product Structure Tree (Bill of Materials)

Bell 4000 Laptop Series

01-bell-4000

CD/DVD/RW Drive

01-cd

I/Lithium Battery

01-battery

4000 System Assembly

01-assembly-4000

19’’ LED Panel

01-led

Keyboard

01-kboard

 

CPU Core i7 Processor

01-cpu

Memory

2GB

01-memory

Power Supply

01-psupply

500 GB Hard Drive

01-hdrive

Assembly Case

01-case

Office Suite

01-office

1

2

1

1

1

1

1

1

3

2

1

1

Windows System

01-windows

Anti-virus Software

01-antivirus

Touchpad Mouse

01-mouse

 

1

1

Bell 8000 Laptop Series

01-bell-8000

CD/DVD/RW Drive

01-cd

I/Lithium Battery

01-battery

8000 System Assembly

01-assembly -4000

19’’ LED Panel

01-led

Keyboard

01-kboard

 

CPU Core i7 Duo Mobile

01-cpu

Memory

2GB

01-memory

Power Supply

01-psupply

500 GB Hard Drive

01-hdrive

Assembly Case

01-case

Office Suite

01-office

1

2

1

1

1

1

1

1

5

4

1

1

Windows System

01-windows

Anti-virus Software

01-antivirus

Touchpad Mouse

01-mouse

 

1

1

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Bell Computer: Supply Chain Bill

Item Name Item Description Item Type Supplier
01-bell-computer Bell Computers Planning item
01-bell-4000 Bell 4000 Laptop Series Finished Good Boston Manufacturing – M2
01-bell-8000 Bell 8000 Laptop Series Finished Good Boston Manufacturing – M2
01-cd CD/DVD/RW Drive Purchased Item Seattle Manufacturing – M1
01-battery Ion Lithium Battery Purchased Item Seattle Manufacturing – M1
01-assembly-4000 4000 System Assembly Intermediate Assembly Boston Manufacturing – M2
01-assembly-8000 8000 System Assembly Intermediate Assembly Boston Manufacturing – M2
01-cpu CPU Core i7 Processor Purchased Item Chicago Subassembly Plant – S1
01-memory 2 GB Shared Dual Channel Memory Purchased Item Chicago Subassembly Plant – S1
01-hdrive 500 GB Hard Drive 5400 RPM Purchased Item Dallas Manufacturing – M3
01-kboard Keyboard Purchased Item Dallas Manufacturing – M3
01-mouse Touchpad Mouse Purchased Item Dallas Manufacturing – M3
01-psupply Power Supply Purchased Item Dallas Manufacturing – M3
01-case Assembly case Purchased Item Dallas Manufacturing – M3
01-led 19” LED Panel Purchased Item Seattle Manufacturing – M1
01-windows Windows Operating System Purchased Item Chicago Subassembly Plant – S1
01-office Office Suite Software Purchased Item Chicago Subassembly Plant – S1
01-antivirus Anti-virus Software Purchased Item Chicago Subassembly Plant – S1

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Bell Computer: Inventory Records

Item Name Item Description Lead Time, days Safety Stock, units On-hand Inv., units Inventory Policy
01-bell-4000 Bell 4000 Laptop Series 5 50 145 Lot-for-lot
01-bell-8000 Bell 8000 Laptop Series 5 50 120 Lot-for-lot
01-cd CD/DVD/RW Drive 5 100 135 Lot-for-lot
01-battery Ion Lithium Battery 5 100 120 Lot-for-lot
01-assembly-4000 4000 System Assembly 5 50 84 Lot-for-lot
01-assembly-8000 8000 System Assembly 5 50 65 Lot-for-lot
01-cpu CPU Core i7 Processor 10 120 170 Lot-for-lot
01-memory 1 GB Shared Dual Channel Memory 10 120 200 Lot-for-lot
01-hdrive 500 GB Hard Drive 5400 RPM 5 100 130 Lot-for-lot
01-kboard Keyboard 5 100 112 Lot-for-lot
01-mouse Touchpad Mouse 5 120 140 Lot-for-lot
01-psupply Power Supply 5 120 150 Lot-for-lot
01-case Assembly case 5 120 180 Lot-for-lot
01-lcd 19” LED Panel 5 100 110 Lot-for-lot
01-windows Windows Operating System 10 100 120 Lot-for-lot
01-office Office Suite Software 10 100 125 Lot-for-lot
01-antivirus Anti-virus Software 10 100 115 Lot-for-lot

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP Processing

 The MRP program operates in the following way:

Determines the number of end products and planned parts

Analyzes input files and determines the gross requirements of each item and its lead time 

Calculates the net requirements for each item using the gross requirements, amount on hand, safety stock:

 

Net Gross Safety On

Requirement = Requirement + Stock -- Hand

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Example of MRP

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

MRP Processing (Continued)

After MRP calculates the net requirements, it develops planned order (planned order receipts) and planned order releases

Planned orders (planned-order receipts)

is the quantity of each material to be received in each time period of the planning horizon

Planned order releases

is the quantity of each item to be ordered in each time period of the planning horizon. This schedule is determined by offsetting the planned order receipts schedule to allow for lead times 

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Example of MRP

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Enterprise Resources Management Applications

Create Inventory Items

(Part Numbers)

Create Bill of Materials (BOM)

Develop Supply Chain Bill (SCB)

Input Forecast and Customer Orders

Develop Master Demand Schedule

(MDS)

Develop Capacity Requirements Plan

(CRP)

Develop Material Requirements Plan

(MRP)

Short-Term Scheduling

MGMT 365 Enterprise Resource Planning

Dr. Z. Radovilsky

‹#›

MGMT 6130 Enterprise Planning

Dr. Z. Radovilsky

‹#›

Month

Demand forecast

WeekWeek 5Week 6Week 7Week 8Week 9

MDS for 01-bell-4000430.0376.0410.0376.0376.0

MDS for 01-bell-800094.0105.094.0100.094.0

July

2350

JuneJuly

Week 1Week 2Week 3Week 4Week 5

01-bell-4000 (finished good, L=1 week)

Gross Requirements430

Safety Stock5050

Amount on Hand145145

Net Requirements335

Planned Orders335

Planned Order Releases 335

01-bell-8000 (finished good, L=1 week)

Gross Requirements94

Safety Stock50 50

Amount on Hand120120

Net Requirements24

Planned Orders24

Planned Order Releases24

01-assembly-4000 (subassembly, L=1 week)

Gross Requirements335

Safety Stock5050

Amount on Hand8484

Net Requirements301

Planned Orders301

Planned Order Releases301

01-assembly-8000 (subassembly, L=1week)

Gross Requirements24

Safety Stock5050

Amount on Hand6565

Net Requirements9

Planned Orders9

Planned Order Releases9

JuneJuly

Week 1Week 2Week 3Week 4Week 5

01-assembly-4000 (subassembly, L=1 week)

Gross Requirements335

Safety Stock5050

Amount on Hand8484

Net Requirements301

Planned Orders301

Planned Order Releases301

01-assembly-8000 (subassembly, L=1week)

Gross Requirements24

Safety Stock5050

Amount on Hand6565

Net Requirements9

Planned Orders9

Planned Order Releases9

01-cpu (Supplier S1, L=2weeks)

Gross Requirements310

Safety Stock120120

Amount on Hand170170

Net Requirements260

Planned Orders260

Planned Order Releases260

01-memory (Supplier S1, L=2weeks)

Gross Requirements948

Safety Stock120120

Amount on Hand200200

Net Requirements868

Planned Orders 868

Planned Order Releases868